Breaker run, WisDOT 311.0115

Low bidders on WisDOT contracts carried a median of $27.59 per CY for this item, over the 24 months to 10 NOV 2026, across 15 low bids. Half of all 51 bids fell between $25.00 and $42.40.

Owner
Wisconsin DOT
Item
311.0115
Unit
CY
Data through
10 NOV 2026

WisDOT prints this item as “Breaker Run”.

$27.59Low bidder's median, per CY
$32.00Median of all bids, per CY
15Contracts in the window

By year of letting

Breaker run, WisDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20221818$58.1460$50.00
20231515$48.6049$50.00
202476$29.7316$39.86
202566$25.0018$34.00
202677$27.5930$32.50

Bid prices as published, not adjusted for inflation.

By quantity

Quantity (CY)Low bidsLow-bid median
21 to 293$25.00
48 to 704$27.23
110 to 2404$42.20
241 to 1,6034$20.00
Breaker run, WisDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

Breaker run, WisDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
12 MAY 202620260512024Racine63$32.00$32.004Zignego Company, Inc.WisDOT
14 APR 202620260414001Columbia29$27.59$27.134Chippewa Concrete Services, Inc.WisDOT
14 APR 202620260414005Crawford21$25.00$25.001Iverson Construction, A Div. of Mathy CoWisDOT
10 MAR 202620260310010Rock48$25.00$25.002Rock Road Companies, Inc.WisDOT
10 FEB 202620260210003Dane1,603$12.42$30.136James Peterson Sons, Inc.WisDOT
10 FEB 202620260210047Dane204$42.00$38.677Integrity Grading and Excavating, Inc.WisDOT
13 JAN 202620260113047Dunn110$51.80$51.806Sheet Piling Services LLCWisDOT
11 NOV 202520251111005Sauk24$25.00$25.001D L Gasser ConstructionWisDOT
14 OCT 202520251014015Pierce240$42.40$42.405Lunda Construction CompanyWisDOT
13 MAY 202520250513020Brown331$50.00$62.504Vinton Construction CompanyWisDOT
11 MAR 202520250311008Crawford241$20.00$22.504Brennan Construction CompanyWisDOT
14 JAN 202520250114004Rock295$20.00$20.003Rock Road Companies, Inc.WisDOT
14 JAN 202520250114035Taylor62$25.00$25.001American Asphalt of WisconsinWisDOT
12 NOV 202420241112002Rock142$30.00$24.982Payne and Dolan, IncWisDOT
12 NOV 202420241112021Walworth70$29.46$29.461Payne and Dolan, IncWisDOT
Latest WisDOT contracts carrying Breaker run

Filter this item by your own quantity, county and period, or check your price against it, in the WisDOT explorer.

How these prices were read

WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WisDOT's own: this item is compared with WisDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the WisDOT letting of 10 NOV 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.