WisDOT contract 20250114004 bid tabulation

Bergen - Emerald Grove; Illinois State Line to V Clinton (STH 140, Rock County STH 140). Let by Wisconsin DOT on January 14, 2025, Rock. 3 bids received; low bid $8,598,719 by Rock Road Companies, Inc..

Owner
Wisconsin DOT
Letting
14 JAN 2025
Pay items
191
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Rock Road Companies, Inc.$8,598,719Low
2Hoffman Construction Company$9,166,729+7.0%
3Musson Bros., Inc.$9,745,179+13%
WisDOT contract 20250114004: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Rock Road Companies, Inc.2. Hoffman Construction Company3. Musson Bros., Inc.
1Clearing (201.0105)STA100$195.00$263.75$195.00
2Grubbing (201.0205)STA100$99.00$42.20$99.00
3Removing small pipe culverts (203.0100)EACH25$199.87$640.00$363.71
4Abatement of asbestos containing material (structure) 01. C-53-2024 (203.0211.S)EACH1$6,888.00$6,888.00$6,888.00
5Abatement of asbestos containing material (structure) 02. C-53-3016 (203.0211.S)EACH1$6,888.00$6,888.00$6,888.00
6Abatement of asbestos containing material (project) 01. 3320-02-70 (203.0216.S)EACH1$1,280.00$1,280.00$1,280.00
7Removing structure over waterway remove debris (structure) 01. C-53- 2024 (203.0250)EACH1$3,000.00$3,000.00$3,000.00
8Removing structure over waterway remove debris (structure) 02. C-53- 3016 (203.0250)EACH1$3,000.00$3,000.00$3,000.00
9Removing concrete pavement (204.0100)SY29,980$2.47$2.00$3.60
10Removing asphaltic surface butt joints (204.0115)SY33$9.51$20.00$20.00
11Removing asphaltic surface milling (204.0120)SY341$17.07$20.00$20.00
12Removing guardrail (204.0165)LF477$4.00$4.00$4.00
13Removing fence (204.0170)LF2,540$3.00$3.00$3.00
14Removing delineators and markers (204.0180)EACH50$40.00$40.00$40.00
15Removing concrete bases (204.0195)EACH6$233.19$200.00$360.07
16Removing utility poles (204.0205)EACH2$349.78$400.00$389.98
17Removing building (station) 01. 187+68 (204.0231)EACH1$5,981.62$5,000.00$28,815
18Abandoning wells (204.0265)EACH1$1,500.00$5,000.00$2,042.25
19Excavation common (205.0100)CY138,128$9.92$8.00$11.02
20Excavation for structures culverts (structure) 01. C-53-2037 (206.2001)EACH1$5,000.00$5,000.00$105,000
21Excavation for structures culverts (structure) 02. C-53-3031 (206.2001)EACH1$5,000.00$5,000.00$5,000.00
22Backfill coarse aggregate (size) 01. no. 2 (209.0300.S)CY248$0.01$108.00$54.13
23Backfill structure type B (210.2500)TON2,913$16.00$16.00$16.00
24Prepare foundation for base aggregate (211.0500)STA251$378.05$0.01$350.22
25Finishing roadway (project) 01. 3320-02-70 (213.0100)EACH1$5,806.29$500.00$500.00
26Base aggregate dense 3/4-inch (305.0110)TON4,121$21.02$0.01$18.73
27Base aggregate dense 1 1/4-inch (305.0120)TON87,024$11.54$0.01$15.85
28Breaker run (311.0115)CY295$20.00$20.00$20.00
29Select crushed material (312.0110)TON98,758$12.06$0.01$14.16
30QMP base aggregate dense 1 1/4- inch compaction (371.2000.S)EACH68$200.00$735.00$996.71
31Coloring concrete wisdot red (405.0100)CY395$95.00$95.00$95.00
32Concrete truck apron 12-inch (415.2010)SY1,184$84.40$84.40$84.40
33Tack coat (455.0605)GAL11,681$3.20$0.01$0.01
34HMA percent within limits (PWL) test strip volumetrics (460.0105.S)EACH2$3,500.00$1,500.00$1,500.00
35HMA percent within limits (PWL) test strip density (460.0110.S)EACH2$3,500.00$1,500.00$1,500.00
36Incentive density PWL HMA pavement (460.2005)DOL17,630$1.00$1.00$1.00
37Incentive density HMA pavement longitudinal joints (460.2007)DOL19,380$1.00$1.00$1.00
38Incentive air voids HMA pavement (460.2010)DOL28,900$1.00$1.00$1.00
39HMA pavement 3 MT 58-28 S (460.6223)TON16,550$60.00$56.75$56.75
40HMA pavement 4 MT 58-28 S (460.6224)TON12,581$61.00$57.75$57.75
41HMA pavement 4 MT 58-28 H (460.6424)TON1,034$80.00$65.00$65.00
42Asphaltic surface driveways and field entrances (465.0120)TON56$122.34$250.00$250.00
43Asphaltic flumes (465.0315)SY120$59.28$60.00$60.00
44Asphaltic rumble strips, shoulder (465.0520)LF29,552$0.25$0.34$0.34
45Asphaltic rumble strips, centerline (465.0560)LF16,751$0.25$0.34$0.34
46Concrete masonry culverts (504.0100)CY311$1,050.00$1,050.00$1,050.00
47Bar steel reinforcement HS structures (505.0400)LB52,973$1.10$1.10$1.10
48Bar steel reinforcement HS coated structures (505.0600)LB6,639$1.30$1.30$1.30
49Piling steel sheet temporary (512.1000)SF2,800$5.00$5.00$5.00
50Rubberized membrane waterproofing (516.0500)SY56$37.00$37.00$37.00
51Apron endwalls for culvert pipe 18- inch (520.1018)EACH36$403.38$470.00$462.56
52Apron endwalls for culvert pipe 21- inch (520.1021)EACH8$429.09$495.00$711.35
53Apron endwalls for culvert pipe 24- inch (520.1024)EACH18$469.85$575.00$651.97
54Apron endwalls for culvert pipe 30- inch (520.1030)EACH6$824.26$890.00$1,082.17
55Apron endwalls for culvert pipe 36- inch (520.1036)EACH2$1,070.80$1,120.00$1,326.32
56Culvert pipe class III-A 18-inch (520.3318)LF544$68.29$48.00$71.39
57Culvert pipe class III-A 21-inch (520.3321)LF252$84.14$59.00$86.71
58Culvert pipe class III-A 24-inch (520.3324)LF290$82.47$60.00$90.43
59Culvert pipe class III-A 30-inch (520.3330)LF136$95.35$70.00$121.76
60Culvert pipe class IV 18-inch (520.4118)LF34$95.73$64.00$105.63
61Culvert pipe class IV 30-inch (520.4130)LF54$113.81$98.00$135.94
62Culvert pipe class IV 36-inch (520.4136)LF246$116.67$104.00$151.23
63Apron endwalls for culvert pipe sloped cross drains steel 36-inch 4 to 1 (521.0336)EACH6$5,350.99$4,250.00$5,007.96
64Apron endwalls for culvert pipe sloped cross drains steel 36-inch 6 to 1 (521.0436)EACH10$6,158.83$5,000.00$5,977.98
65Apron endwalls for culvert pipe sloped side drains steel 21-inch 6 to 1 (521.1521)EACH8$1,750.10$1,850.00$1,821.80
66Apron endwalls for culvert pipe sloped side drains steel 30-inch 6 to 1 (521.1530)EACH4$3,739.91$4,500.00$4,120.80
67Culvert pipe reinforced concrete class IV 24-inch (522.0424)LF86$112.37$86.00$129.00
68Culvert pipe reinforced concrete class IV 30-inch (522.0430)LF136$135.12$126.00$159.99
69Culvert pipe reinforced concrete class IV 36-inch (522.0436)LF464$169.00$162.00$198.46
70Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024)EACH3$1,391.96$1,280.00$1,489.41
71Apron endwalls for culvert pipe reinforced concrete 30-inch (522.1030)EACH4$1,563.68$1,480.00$1,684.67
72Culvert pipe reinforced concrete horizontal elliptical class HE-IV 19X30-inch (522.2419)LF152$184.09$174.00$211.56
73Culvert pipe reinforced concrete horizontal elliptical class HE-IV 24X38-inch (522.2424)LF94$209.56$208.00$251.81
74Culvert pipe reinforced concrete horizontal elliptical class HE-IV 29X45-inch (522.2429)LF72$268.61$272.00$323.87
75Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 19X30-inch (522.2619)EACH4$1,451.97$1,340.00$1,557.64
76Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 24X38-inch (522.2624)EACH2$1,755.18$1,700.00$1,984.85
77Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 29X45-inch (522.2629)EACH2$2,050.74$2,020.00$2,394.19
78Concrete curb & gutter 30-inch type D (601.0411)LF1,625$24.50$24.50$24.50
79Concrete curb & gutter 4-inch sloped 36-inch type D (601.0553)LF1,589$27.50$27.50$27.50
80Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557)LF1,933$32.90$32.90$32.90
81Concrete curb & gutter 4-inch sloped 36-inch type T (601.0582)LF333$32.90$32.90$32.90
82Concrete sidewalk 4-inch (602.0405)SF10,829$5.30$5.30$5.30
83Riprap light (606.0100)CY63$83.13$174.00$255.20
84Riprap medium (606.0200)CY160$64.25$174.00$232.65
85Riprap heavy (606.0300)CY122$80.00$174.00$231.28
86Storm sewer pipe reinforced concrete class IV 12-inch (608.0412)LF146$73.13$58.00$89.25
87Storm sewer pipe reinforced concrete class IV 24-inch (608.0424)LF171$106.20$86.00$118.17
88Storm sewer pipe reinforced concrete class IV 30-inch (608.0430)LF128$132.93$134.00$168.01
89Inlet covers type H (611.0624)EACH4$1,054.91$1,100.00$1,249.41
90Inlet covers type HM (611.0627)EACH4$1,054.91$1,100.00$1,249.41
91Inlet covers type T (611.0652)EACH2$1,369.44$1,400.00$1,563.50
92Catch basins 4-FT diameter (611.1004)EACH5$3,377.50$2,900.00$3,073.56
93Manholes 5-FT diameter (611.2005)EACH1$4,377.63$4,800.00$4,729.16
94Inlets 2X3-FT (611.3230)EACH4$2,588.45$2,000.00$2,064.35
95Drain tile exploration (612.0700)LF890$12.94$10.50$6.70
96Apron endwalls for underdrain reinforced concrete 6-inch (612.0806)EACH3$372.64$340.00$355.99
97Salvaged rail (614.0920)LF162.50$6.00$6.00$6.00
98Salvaged guardrail end treatments (614.0925)EACH2$250.00$250.00$250.00
99MGS guardrail 3 (614.2300)LF762.50$30.00$30.00$30.00
100MGS guardrail 3 L (614.2340)LF200$38.00$38.00$38.00
101MGS guardrail terminal eat (614.2610)EACH8$4,200.00$4,200.00$4,200.00
102MGS guardrail terminal type 2 (614.2620)EACH2$3,800.00$3,800.00$3,800.00
103Fence safety (616.0700.S)LF590$8.50$8.50$8.50
104Maintenance and repair of haul roads (project) 01. 3320-02-70 (618.0100)EACH1$0.01$1.00$1.25
105Mobilization (619.1000)EACH1$327,403$3,349,500$290,305
106Concrete median sloped nose (620.0300)SF411$13.00$13.00$13.00
107Water (624.0100)MGAL1,288$0.01$0.01$26.41
108Salvaged topsoil (625.0500)SY174,290$0.01$1.50$0.92
109Mulching (627.0200)SY135,889$0.20$0.20$0.20
110Silt fence (628.1504)LF5,715$2.25$2.25$2.25
111Silt fence maintenance (628.1520)LF6,150$0.01$0.01$0.01
112Mobilizations erosion control (628.1905)EACH8$1.00$1.00$1.00
113Mobilizations emergency erosion control (628.1910)EACH5$1.00$1.00$1.00
114Erosion mat class I type B (628.2004)SY44,800$1.10$1.10$1.10
115Erosion mat class II type C (628.2027)SY2,000$3.75$3.75$3.75
116Polyethylene sheeting (628.5505)SY2,436$0.01$2.50$1.59
117Inlet protection type C (628.7015)EACH9$100.00$100.00$100.00
118Temporary ditch checks (628.7504)LF3,730$5.00$5.00$5.00
119Culvert pipe checks (628.7555)EACH159$20.00$20.00$20.00
120Fertilizer type B (629.0210)CWT110$150.00$150.00$150.00
121Seeding mixture no. 10 (630.0110)LB4,699$6.85$6.85$6.85
122Seeding mixture no. 80 (630.0180)LB3$300.00$300.00$300.00
123Seed water (630.0500)MGAL35,185$0.01$0.01$0.01
124Markers culvert end (633.5200)EACH37$85.00$85.00$85.00
125Posts wood 4X6-inch X 14-FT (634.0614)EACH26$130.00$130.00$130.00
126Posts wood 4X6-inch X 16-FT (634.0616)EACH59$140.00$140.00$140.00
127Posts wood 4X6-inch X 18-FT (634.0618)EACH6$160.00$160.00$160.00
128Posts wood 4X6-inch X 20-FT (634.0620)EACH8$180.00$180.00$180.00
129Posts tubular steel 2X2-inch X 8-FT (634.0808)EACH8$210.00$210.00$210.00
130Posts tubular steel 2X2-inch X 9.5- FT (634.0809)EACH8$210.00$210.00$210.00
131Signs type II reflective H (637.2210)SF869.85$26.00$26.00$26.00
132Signs type II reflective F (637.2230)SF133.28$29.00$29.00$29.00
133Removing signs type II (638.2602)EACH84$35.00$35.00$35.00
134Removing small sign supports (638.3000)EACH94$35.00$35.00$35.00
135Field office type C (642.5201)EACH1$11,250$15,000$31,244
136Traffic control barricades type III (643.0420)DAY7,951$1.00$0.60$1.00
137Traffic control warning lights type A (643.0705)DAY14,250$0.09$0.10$0.09
138Traffic control signs (643.0900)DAY132,881$0.15$0.30$0.15
139Traffic control covering signs type II (643.0920)EACH29$25.00$25.00$25.00
140Traffic control signs PCMS (643.1050)DAY28$69.99$30.00$69.99
141Traffic control (643.5000)EACH1$10,000$22,500$10,000
142Geotextile type C (645.0105)SY628$3.00$3.00$3.00
143Geotextile type HR (645.0120)SY636$1.46$4.50$4.15
144Geotextile type R (645.0130)SY273$0.96$4.50$2.96
145Geogrid type SR (645.0220)SY9,915$1.53$1.50$2.29
146Marking line epoxy 6-inch (646.2020)LF18,091$0.75$0.75$0.66
147Marking line grooved wet ref epoxy 6-inch (646.2040)LF57,887$1.20$1.20$1.28
148Marking line epoxy 10-inch (646.4020)LF287$1.80$1.80$1.15
149Marking line grooved wet ref epoxy 10-inch (646.4040)LF400$3.00$3.00$2.75
150Marking arrow epoxy (646.5020)EACH4$350.00$350.00$220.00
151Marking word epoxy (646.5120)EACH2$360.00$360.00$240.00
152Marking stop line epoxy 18-inch (646.6120)LF60$18.00$18.00$12.00
153Marking dotted extension epoxy 18-inch (646.6320)LF95$12.00$12.00$15.00
154Marking diagonal epoxy 12-inch (646.7120)LF563$7.00$7.00$9.00
155Marking curb epoxy (646.8120)LF353$8.00$8.00$8.00
156Marking island nose epoxy (646.8220)EACH6$335.00$335.00$250.00
157Locating no-passing zones (648.0100)MI4.09$600.00$600.00$400.00
158Construction staking storm sewer (650.4000)EACH13$50.00$105.00$105.00
159Construction staking subgrade (650.4500)LF27,675$0.01$0.01$0.01
160Construction staking base (650.5000)LF27,675$0.01$1.50$1.50
161Construction staking curb gutter and curb & gutter (650.5500)LF5,480$0.50$2.00$2.00
162Construction staking pipe culverts (650.6000)EACH59$25.00$130.00$130.00
163Construction staking structure layout (structure) 01. C-53-2037 (650.6501)EACH1$2,500.00$1,000.00$1,000.00
164Construction staking structure layout (structure) 02. C-53-3031 (650.6501)EACH1$2,500.00$1,000.00$1,000.00
165Construction staking electrical installations (project) 01. 3320-02- 70 (650.8501)EACH1$2,500.00$5,962.50$5,962.50
166Construction staking supplemental control (project) 01. 3320-02-70 (650.9911)EACH1$8,000.00$2,500.00$2,500.00
167Construction staking slope stakes (650.9920)LF28,209$0.10$0.50$0.50
168Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF1,360$10.00$9.00$10.00
169Conduit rigid nonmetallic schedule 40 3-inch (652.0235)LF615$12.00$12.00$12.00
170Pull boxes non-conductive 24X42- inch (653.0164)EACH9$1,850.00$1,800.00$1,850.00
171Concrete bases type 5 (654.0105)EACH16$1,100.00$1,000.00$1,100.00
172Concrete control cabinet bases type L30 (654.0230)EACH1$200.00$2,000.00$2,000.00
173Electrical wire lighting 12 AWG (655.0610)LF10,660$1.00$1.10$1.00
174Electrical wire lighting 10 AWG (655.0615)LF2,555$1.15$1.20$1.15
175Electrical service meter breaker pedestal (location) 01. cabinet A (656.0201)EACH1$2,000.00$2,000.00$2,000.00
176Transformer bases breakaway 11 1/2-inch bolt circle (657.0255)EACH16$600.00$675.00$600.00
177Poles type 5-aluminum (657.0322)EACH16$2,150.00$1,775.00$2,150.00
178Luminaire arms single member 4 1/2-inch clamp 6-FT (657.0610)EACH16$305.00$700.00$305.00
179Luminaires utility LED A (659.1115)EACH16$200.00$200.00$200.00
180Lighting control cabinets 120/240 30-inch (659.2130)EACH1$8,000.00$8,000.00$8,000.00
181Sawing asphalt (690.0150)LF327$1.40$1.40$1.95
182Incentive strength concrete structures (715.0502)DOL1,872$1.00$1.00$1.00
183Incentive iri ride (740.0440)DOL14,638.64$1.00$1.00$1.00
184On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS2,500$5.00$5.00$5.00
185On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS1,500$5.00$5.00$5.00
186Special 01. sand bags (SPV.0060)EACH189$18.00$55.00$14.09
187Special 02. verfiy landmark reference monuments (SPV.0060)EACH3$1,250.00$600.00$952.19
188Special 03. apron endwalls for culvert pipe sloped cross drains steel 30-inch 6 to 1 (SPV.0060)EACH4$7,065.26$4,600.00$346.33
189Special 01. pipe underdrain (6-inch) with geotextile fabric and aggregate (SPV.0090)LF1,390$17.31$56.00$12.26
190Special 01. excavating, hauling, and disposal of lead contaminated soil (SPV.0195)TON2,322$33.32$33.50$44.01
191Special 02. traffic control base course (SPV.0195)TON10,000$11.54$0.01$10.00
WisDOT contract 20250114004: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of January 14, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy