WisDOT contract 20260310010 bid tabulation
5571-00-72. Let by Wisconsin DOT on March 10, 2026, Rock. 2 bids received; low bid $6,553,518 by Rock Road Companies, Inc..
- Owner
- Wisconsin DOT
- Letting
- 10 MAR 2026
- Pay items
- 213
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rock Road Companies, Inc. | $6,553,518 | Low |
| 2 | Payne and Dolan, Inc | $7,131,686 | +9.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rock Road Companies, Inc. | 2. Payne and Dolan, Inc |
|---|---|---|---|---|---|
| 1 | Grubbing (201.0205) | STA | 24 | $300.00 | $325.00 |
| 2 | Removing small pipe culverts (203.0100) | EACH | 6 | $516.34 | $700.00 |
| 3 | Removing structure (structure) 01. B-53-0140 (203.0220) | EACH | 1 | $8,070.00 | $8,070.00 |
| 4 | Removing concrete pavement (204.0100) | SY | 530 | $13.91 | $15.75 |
| 5 | Removing concrete surface partial depth (204.0109.S) | SF | 111,200 | $0.17 | $0.01 |
| 6 | Removing asphaltic surface (204.0110) | SY | 250 | $3.00 | $4.60 |
| 7 | Removing asphaltic surface butt joints (204.0115) | SY | 1,170 | $5.62 | $0.01 |
| 8 | Removing asphaltic surface milling (204.0120) | SY | 194,970 | $0.50 | $0.01 |
| 9 | Removing curb & gutter (204.0150) | LF | 1,759 | $10.43 | $11.25 |
| 10 | Removing concrete sidewalk (204.0155) | SY | 620 | $11.25 | $25.25 |
| 11 | Removing guardrail (204.0165) | LF | 806 | $3.00 | $3.00 |
| 12 | Removing fence (204.0170) | LF | 1,505 | $1.50 | $1.50 |
| 13 | Removing delineators and markers (204.0180) | EACH | 6 | $25.00 | $25.00 |
| 14 | Removing (item description) 01. concrete culvert pipe 66X60-inch (204.9060.S) | EACH | 1 | $3,485.33 | $1,400.00 |
| 15 | Removing (item description) 02. apron endwalls for culvert pipe steel 60-inch (204.9060.S) | EACH | 2 | $1,161.78 | $700.00 |
| 16 | Excavation common (205.0100) | CY | 15,870 | $12.91 | $14.50 |
| 17 | Excavation rock (205.0200) | CY | 337 | $35.00 | $67.00 |
| 18 | Excavation for structures culverts (structure) 01. B-53-0140 (206.2001) | EACH | 1 | $6,000.00 | $6,000.00 |
| 19 | Cofferdams (structure) 01. B-53- 0140 (206.5001) | EACH | 1 | $12,000 | $12,000 |
| 20 | Borrow (208.0100) | CY | 2,710 | $0.01 | $0.01 |
| 21 | Backfill structure type B (210.2500) | TON | 271 | $23.00 | $23.00 |
| 22 | Prepare foundation for asphaltic paving (project) 01. 5571-00-72 (211.0101) | EACH | 1 | $3,306.72 | $20,000 |
| 23 | Prepare foundation for asphaltic shoulders (211.0400) | STA | 1,163 | $9.32 | $0.01 |
| 24 | Finishing roadway (project) 01. 5571-00-72 (213.0100) | EACH | 1 | $5,150.68 | $100.00 |
| 25 | Base aggregate dense 3/4-inch (305.0110) | TON | 21,790 | $0.01 | $0.01 |
| 26 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 12,214 | $13.65 | $17.25 |
| 27 | Breaker run (311.0115) | CY | 48 | $25.00 | $25.00 |
| 28 | Select crushed material (312.0110) | TON | 14,120 | $13.72 | $16.25 |
| 29 | Coloring concrete wisdot red (405.0100) | CY | 226 | $115.00 | $120.00 |
| 30 | Concrete truck apron 12-inch (415.2010) | SY | 677 | $120.00 | $98.00 |
| 31 | HMA cold weather paving (450.4000) | TON | 2,690 | $2.50 | $0.01 |
| 32 | Tack coat (455.0605) | GAL | 12,689 | $4.50 | $2.00 |
| 33 | HMA percent within limits (PWL) test strip volumetrics (460.0105.S) | EACH | 2 | $3,500.00 | $100.00 |
| 34 | HMA percent within limits (PWL) test strip density (460.0110.S) | EACH | 2 | $3,500.00 | $100.00 |
| 35 | Incentive density HMA pavement (460.2000) | DOL | 6,600 | $1.00 | $1.00 |
| 36 | Incentive density PWL HMA pavement (460.2005) | DOL | 46,880 | $1.00 | $1.00 |
| 37 | Incentive density HMA pavement longitudinal joints (460.2007) | DOL | 13,070 | $1.00 | $1.00 |
| 38 | Incentive air voids HMA pavement (460.2010) | DOL | 60,700 | $1.00 | $1.00 |
| 39 | HMA pavement 3 LT 58-28 S (460.5223) | TON | 26,260 | $60.26 | $70.00 |
| 40 | HMA pavement 4 LT 58-28 S (460.5224) | TON | 20,435 | $61.14 | $74.80 |
| 41 | HMA pavement 4 MT 58-28 H (460.6424) | TON | 7,790 | $82.92 | $75.00 |
| 42 | Asphaltic surface (465.0105) | TON | 12 | $188.72 | $80.00 |
| 43 | Asphaltic surface driveways and field entrances (465.0120) | TON | 143 | $167.31 | $250.00 |
| 44 | Asphaltic flumes (465.0315) | SY | 24 | $54.58 | $40.00 |
| 45 | Asphaltic rumble strips, edge line (465.0540) | LF | 108,410 | $0.18 | $0.18 |
| 46 | Asphaltic rumble strips, centerline (465.0560) | LF | 53,910 | $0.18 | $0.18 |
| 47 | Adhesive anchors no. 4 bar (502.4204) | EACH | 98 | $25.00 | $25.00 |
| 48 | Concrete masonry culverts (504.0100) | CY | 43 | $2,900.00 | $2,900.00 |
| 49 | Bar steel reinforcement HS coated structures (505.0600) | LB | 5,470 | $1.50 | $1.50 |
| 50 | Temporary shoring (structure) 01. B-53-0140 (511.1200) | SF | 475 | $50.00 | $50.00 |
| 51 | Rubberized membrane waterproofing (516.0500) | SY | 27 | $44.00 | $44.00 |
| 52 | Apron endwalls for culvert pipe 15- inch (520.1015) | EACH | 2 | $452.17 | $840.00 |
| 53 | Apron endwalls for culvert pipe 24- inch (520.1024) | EACH | 2 | $496.62 | $2,100.00 |
| 54 | Culvert pipe class III-A 15-inch (520.3315) | LF | 54 | $53.59 | $47.50 |
| 55 | Concrete collars for pipe (520.8000) | EACH | 2 | $660.28 | $1,600.00 |
| 56 | Cleaning culvert pipes (520.8700) | EACH | 6 | $1,250.00 | $1,900.00 |
| 57 | Apron endwalls for culvert pipe steel 60-inch (521.1060) | EACH | 2 | $3,395.39 | $4,000.00 |
| 58 | Apron endwalls for pipe arch sloped side drains steel 35X24- inch 4 to 1 (521.1708) | EACH | 1 | $2,626.66 | $3,000.00 |
| 59 | Apron endwalls for pipe arch sloped side drains steel 35X24- inch 10 to 1 (521.1835) | EACH | 1 | $5,121.38 | $5,400.00 |
| 60 | Culvert pipe corrugated steel 60- inch (521.3160) | LF | 23 | $261.34 | $60.00 |
| 61 | Pipe arch polymer coated corrugated steel 35X24-inch (521.5735) | LF | 26 | $133.11 | $130.00 |
| 62 | Culvert pipe reinforced concrete class III 36-inch (522.0136) | LF | 86 | $240.58 | $150.00 |
| 63 | Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012) | EACH | 4 | $992.49 | $1,900.00 |
| 64 | Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024) | EACH | 2 | $1,248.91 | $2,100.00 |
| 65 | Apron endwalls for culvert pipe reinforced concrete 30-inch (522.1030) | EACH | 1 | $1,704.78 | $2,600.00 |
| 66 | Apron endwalls for culvert pipe reinforced concrete 36-inch (522.1036) | EACH | 2 | $2,578.57 | $3,000.00 |
| 67 | Culvert pipe reinforced concrete horizontal elliptical class HE-IV 19X30-inch (522.2419) | LF | 26 | $241.90 | $150.00 |
| 68 | Culvert pipe reinforced concrete horizontal elliptical class HE-IV 29X45-inch (522.2429) | LF | 148 | $299.68 | $240.00 |
| 69 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 19X30-inch (522.2619) | EACH | 2 | $1,248.91 | $1,400.00 |
| 70 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 29X45-inch (522.2629) | EACH | 4 | $2,817.77 | $2,300.00 |
| 71 | Concrete curb & gutter 18-inch type A (601.0405) | LF | 324 | $32.00 | $31.25 |
| 72 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 3,546 | $44.65 | $42.00 |
| 73 | Concrete curb & gutter 6-inch sloped 30-inch type G (601.0413) | LF | 414 | $35.00 | $35.00 |
| 74 | Concrete curb & gutter 4-inch sloped 36-inch type A (601.0551) | LF | 382 | $35.00 | $38.00 |
| 75 | Concrete curb & gutter 4-inch sloped 30-inch type R (601.0581) | LF | 412 | $35.00 | $34.25 |
| 76 | Concrete curb pedestrian (601.0600) | LF | 107 | $45.00 | $55.00 |
| 77 | Concrete sidewalk 4-inch (602.0405) | SF | 7,180 | $12.20 | $12.50 |
| 78 | Concrete sidewalk 5-inch (602.0410) | SF | 7,553 | $8.50 | $6.30 |
| 79 | Curb ramp detectable warning field yellow (602.0505) | SF | 490 | $45.00 | $55.00 |
| 80 | Curb ramp detectable warning field radial yellow (602.0605) | SF | 15 | $75.00 | $69.00 |
| 81 | Concrete driveway 6-inch (602.0810) | SY | 140 | $110.00 | $80.00 |
| 82 | Riprap medium (606.0200) | CY | 88 | $78.92 | $98.00 |
| 83 | Riprap heavy (606.0300) | CY | 63 | $78.92 | $100.00 |
| 84 | Storm sewer pipe reinforced concrete class III 12-inch (608.0312) | LF | 156 | $82.71 | $95.00 |
| 85 | Storm sewer pipe reinforced concrete class III 24-inch (608.0324) | LF | 16 | $98.51 | $140.00 |
| 86 | Storm sewer pipe reinforced concrete class III 30-inch (608.0330) | LF | 222 | $125.75 | $140.00 |
| 87 | Storm sewer pipe reinforced concrete class IV 12-inch (608.0412) | LF | 295 | $82.71 | $90.00 |
| 88 | Storm sewer pipe reinforced concrete class IV 24-inch (608.0424) | LF | 84 | $98.51 | $110.00 |
| 89 | Storm sewer pipe reinforced concrete class IV 30-inch (608.0430) | LF | 26 | $129.32 | $140.00 |
| 90 | Storm sewer pipe class III-A 30- inch (608.3030) | LF | 189 | $98.05 | $89.00 |
| 91 | Reconstructing inlets (611.0430) | EACH | 1 | $1,473.98 | $2,900.00 |
| 92 | Manhole covers type J (611.0530) | EACH | 1 | $887.05 | $1,100.00 |
| 93 | Manhole covers type Q (611.0555) | EACH | 1 | $874.12 | $1,530.00 |
| 94 | Inlet covers type H (611.0624) | EACH | 8 | $1,130.94 | $550.00 |
| 95 | Inlet covers type HM (611.0627) | EACH | 3 | $1,130.94 | $770.00 |
| 96 | Inlet covers type HM-GJ (611.0630) | EACH | 3 | $1,130.94 | $820.00 |
| 97 | Inlet covers type HM-GJ-S (611.0633) | EACH | 2 | $1,130.94 | $1,300.00 |
| 98 | Inlet covers type MS (611.0642) | EACH | 1 | $899.58 | $1,100.00 |
| 99 | Inlet covers type T (611.0652) | EACH | 3 | $1,454.60 | $1,700.00 |
| 100 | Catch basins 5-FT diameter (611.1005) | EACH | 3 | $4,216.99 | $4,000.00 |
| 101 | Catch basins 6-FT diameter (611.1006) | EACH | 1 | $6,383.50 | $6,300.00 |
| 102 | Manholes 5-FT diameter (611.2005) | EACH | 1 | $3,656.28 | $4,000.00 |
| 103 | Manholes 5X5-FT (611.2055) | EACH | 1 | $15,656 | $11,000 |
| 104 | Inlets 4-FT diameter (611.3004) | EACH | 15 | $2,662.49 | $2,600.00 |
| 105 | Inlets median 2 grate (611.3902) | EACH | 1 | $6,795.89 | $6,400.00 |
| 106 | Adjusting manhole covers (611.8110) | EACH | 19 | $754.31 | $960.00 |
| 107 | MGS guardrail 3 (614.2300) | LF | 125 | $30.00 | $30.00 |
| 108 | MGS guardrail 3 K (614.2330) | LF | 138 | $39.00 | $39.00 |
| 109 | MGS guardrail terminal eat (614.2610) | EACH | 4 | $4,000.00 | $4,000.00 |
| 110 | Anchor post assembly top mount (614.8010) | EACH | 14 | $950.00 | $950.00 |
| 111 | Fence safety (616.0700.S) | LF | 70 | $5.00 | $5.00 |
| 112 | Maintenance and repair of haul roads (project) 01. 5571-00-72 (618.0100) | EACH | 1 | $0.01 | $0.01 |
| 113 | Mobilization (619.1000) | EACH | 1 | $128,500 | $140,000 |
| 114 | Concrete median sloped nose (620.0300) | SF | 14 | $15.00 | $13.50 |
| 115 | Water (624.0100) | MGAL | 213 | $0.01 | $39.00 |
| 116 | Topsoil (625.0100) | SY | 17,453 | $0.01 | $7.70 |
| 117 | Salvaged topsoil (625.0500) | SY | 6,470 | $0.01 | $2.50 |
| 118 | Mulching (627.0200) | SY | 15,881 | $0.35 | $0.35 |
| 119 | Silt fence (628.1504) | LF | 2,036 | $2.00 | $2.00 |
| 120 | Silt fence maintenance (628.1520) | LF | 2,036 | $0.01 | $0.01 |
| 121 | Mobilizations erosion control (628.1905) | EACH | 9 | $100.00 | $100.00 |
| 122 | Mobilizations emergency erosion control (628.1910) | EACH | 5 | $100.00 | $100.00 |
| 123 | Erosion mat class I type B (628.2004) | SY | 5,491 | $1.00 | $1.00 |
| 124 | Erosion mat urban class I type A (628.2006) | SY | 2,550 | $1.75 | $1.75 |
| 125 | Inlet protection type A (628.7005) | EACH | 1 | $175.00 | $175.00 |
| 126 | Inlet protection type C (628.7015) | EACH | 19 | $60.00 | $60.00 |
| 127 | Temporary ditch checks (628.7504) | LF | 310 | $8.00 | $8.00 |
| 128 | Culvert pipe checks (628.7555) | EACH | 27 | $20.00 | $20.00 |
| 129 | Fertilizer type B (629.0210) | CWT | 15 | $85.00 | $85.00 |
| 130 | Seeding mixture no. 30 (630.0130) | LB | 1,070 | $8.25 | $8.25 |
| 131 | Seeding mixture no. 80 (630.0180) | LB | 8 | $110.00 | $110.00 |
| 132 | Seed water (630.0500) | MGAL | 123 | $20.00 | $20.00 |
| 133 | Markers culvert end (633.5200) | EACH | 17 | $65.00 | $65.00 |
| 134 | Posts wood 4X6-inch X 12-FT (634.0612) | EACH | 30 | $85.00 | $85.00 |
| 135 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 9 | $90.00 | $90.00 |
| 136 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 37 | $95.00 | $95.00 |
| 137 | Signs type II reflective H (637.2210) | SF | 449 | $22.00 | $22.00 |
| 138 | Signs type II reflective F (637.2230) | SF | 52 | $22.00 | $22.00 |
| 139 | Moving signs type II (638.2102) | EACH | 28 | $175.00 | $175.00 |
| 140 | Removing signs type II (638.2602) | EACH | 14 | $35.00 | $35.00 |
| 141 | Removing small sign supports (638.3000) | EACH | 42 | $35.00 | $35.00 |
| 142 | Field office type B (642.5001) | EACH | 1 | $9,450.00 | $5,000.00 |
| 143 | Traffic control drums (643.0300) | DAY | 2,190 | $0.71 | $0.71 |
| 144 | Traffic control barricades type III (643.0420) | DAY | 9,400 | $0.72 | $0.72 |
| 145 | Traffic control warning lights type A (643.0705) | DAY | 18,500 | $0.13 | $0.13 |
| 146 | Traffic control signs (643.0900) | DAY | 18,770 | $0.58 | $0.58 |
| 147 | Traffic control covering signs type I (643.0910) | EACH | 1 | $92.38 | $92.38 |
| 148 | Traffic control covering signs type II (643.0920) | EACH | 12 | $46.19 | $46.19 |
| 149 | Traffic control signs PCMS (643.1050) | DAY | 14 | $60.00 | $60.00 |
| 150 | Traffic control (643.5000) | EACH | 1 | $12,335 | $12,335 |
| 151 | Temporary pedestrian surface asphalt (644.1410) | SF | 300 | $8.37 | $30.00 |
| 152 | Temporary pedestrian surface plate (644.1430) | SF | 160 | $6.49 | $6.49 |
| 153 | Temporary pedestrian curb ramp (644.1601) | DAY | 378 | $15.35 | $15.35 |
| 154 | Temporary pedestrian detectable warning field (644.1605) | SF | 60 | $16.68 | $16.68 |
| 155 | Temporary audible message devices (644.1900.S) | DAY | 378 | $2.16 | $2.16 |
| 156 | Geotextile type C (645.0105) | SY | 85 | $3.00 | $3.00 |
| 157 | Geotextile type HR (645.0120) | SY | 132 | $1.54 | $3.50 |
| 158 | Geotextile type R (645.0130) | SY | 75 | $1.03 | $2.40 |
| 159 | Marking line epoxy 6-inch (646.2020) | LF | 6,025 | $0.68 | $0.68 |
| 160 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 224,170 | $1.10 | $1.10 |
| 161 | Marking line epoxy 10-inch (646.4020) | LF | 241 | $1.05 | $1.05 |
| 162 | Marking railroad crossing epoxy (646.5320) | EACH | 2 | $1,850.00 | $1,850.00 |
| 163 | Marking stop line epoxy 18-inch (646.6120) | LF | 60 | $14.75 | $14.75 |
| 164 | Marking dotted extension epoxy 18-inch (646.6320) | LF | 69 | $14.75 | $14.75 |
| 165 | Cold weather marking epoxy 6-inch (646.6466) | LF | 9,185 | $0.35 | $0.35 |
| 166 | Cold weather marking epoxy 10- inch (646.6470) | LF | 241 | $0.55 | $0.55 |
| 167 | Marking diagonal epoxy 12-inch (646.7120) | LF | 311 | $12.00 | $12.00 |
| 168 | Marking island nose epoxy (646.8220) | EACH | 5 | $300.00 | $300.00 |
| 169 | Marking parking stall epoxy (646.8320) | LF | 304 | $17.00 | $17.00 |
| 170 | Locating no-passing zones (648.0100) | MI | 13 | $435.00 | $435.00 |
| 171 | Construction staking storm sewer (650.4000) | EACH | 28 | $1.00 | $130.00 |
| 172 | Construction staking subgrade (650.4500) | LF | 6,010 | $0.01 | $0.01 |
| 173 | Construction staking base (650.5000) | LF | 6,010 | $0.01 | $1.75 |
| 174 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 5,078 | $1.00 | $2.50 |
| 175 | Construction staking pipe culverts (650.6000) | EACH | 3 | $1.00 | $150.00 |
| 176 | Construction staking resurfacing reference (650.8000) | LF | 67,020 | $0.02 | $0.20 |
| 177 | Construction staking electrical installations (project) 01. 5571-00- 73 (650.8501) | EACH | 1 | $500.00 | $1,680.00 |
| 178 | Construction staking curb ramps (650.9000) | EACH | 31 | $1.00 | $250.00 |
| 179 | Construction staking sidewalk (project) 01. 5571-00-72 (650.9500) | EACH | 1 | $1,500.00 | $1,000.00 |
| 180 | Construction staking sidewalk (project) 02. 5571-00-73 (650.9500) | EACH | 1 | $1,500.00 | $1,000.00 |
| 181 | Construction staking supplemental control (project) 01. 5571-00-72 (650.9911) | EACH | 1 | $1,500.00 | $1,500.00 |
| 182 | Construction staking supplemental control (project) 02. 5571-00-73 (650.9911) | EACH | 1 | $1,500.00 | $6,500.00 |
| 183 | Construction staking slope stakes (650.9920) | LF | 6,010 | $0.02 | $0.75 |
| 184 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 1,085 | $6.35 | $6.35 |
| 185 | Conduit rigid nonmetallic schedule 40 3-inch (652.0235) | LF | 765 | $8.16 | $8.16 |
| 186 | Pull boxes non-conductive 24X42- inch (653.0164) | EACH | 12 | $2,365.87 | $2,365.87 |
| 187 | Removing pull boxes (653.0905) | EACH | 4 | $113.64 | $500.00 |
| 188 | Concrete bases type 5 (654.0105) | EACH | 15 | $1,425.28 | $1,425.28 |
| 189 | Concrete control cabinet bases type L30 (654.0230) | EACH | 1 | $1,133.96 | $1,133.96 |
| 190 | Electrical wire lighting 12 AWG (655.0610) | LF | 9,100 | $0.97 | $0.97 |
| 191 | Electrical wire lighting 10 AWG (655.0615) | LF | 2,895 | $1.21 | $1.21 |
| 192 | Electrical service meter breaker pedestal (location) 01. STH 213 & CTH Q (656.0201) | EACH | 1 | $2,019.22 | $2,019.22 |
| 193 | Transformer bases breakaway 11 1/2-inch bolt circle (657.0255) | EACH | 15 | $781.39 | $781.39 |
| 194 | Poles type 5-aluminum (657.0322) | EACH | 15 | $2,433.27 | $2,433.27 |
| 195 | Luminaire arms single member 4 1/2-inch clamp 6-FT (657.0610) | EACH | 15 | $414.29 | $414.29 |
| 196 | Luminaires utility LED A (659.1115) | EACH | 15 | $315.76 | $315.29 |
| 197 | Lighting control cabinets 120/240 30-inch (659.2130) | EACH | 1 | $9,420.28 | $9,420.28 |
| 198 | Public land reference monument verify and reset (680.0100) | EACH | 7 | $250.00 | $2,500.00 |
| 199 | Sawing asphalt (690.0150) | LF | 756 | $1.01 | $1.95 |
| 200 | Sawing concrete (690.0250) | LF | 535 | $2.02 | $2.55 |
| 201 | Incentive compressive strength concrete pavement (715.0720) | DOL | 500 | $1.00 | $1.00 |
| 202 | Incentive iri ride (740.0440) | DOL | 50,490 | $1.00 | $1.00 |
| 203 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 3,600 | $5.00 | $5.00 |
| 204 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 3,800 | $5.00 | $5.00 |
| 205 | Special 01. adjusting water valve box (SPV.0060) | EACH | 29 | $422.50 | $500.00 |
| 206 | Special 02. grading, shaping, and finishing intersections - curb ramps (SPV.0060) | EACH | 30 | $857.39 | $1,140.00 |
| 207 | Special 03. install state supplied solar flashing beacon (SPV.0060) | EACH | 4 | $884.04 | $884.04 |
| 208 | Special 04. removing existing flashing beacon (SPV.0060) | EACH | 4 | $770.37 | $770.37 |
| 209 | Special 05. temporary lighting system (SPV.0060) | EACH | 1 | $2,856.20 | $2,856.20 |
| 210 | Special 01. transverse joint and crack plunge milling and patching (SPV.0090) | LF | 4,400 | $17.21 | $1.00 |
| 211 | Special 02. cold weather marking epoxy 12-inch (SPV.0090) | LF | 311 | $0.75 | $0.75 |
| 212 | Special 03. cold weather marking epoxy 18-inch (SPV.0090) | LF | 69 | $1.20 | $1.20 |
| 213 | Special 04. pipe underdrain 6-inch with geotextile fabric and aggregate (SPV.0090) | LF | 924 | $22.93 | $18.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of March 10, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.