WisDOT contract 20250114035 bid tabulation

Thorp - Ingram; STH 64 W to CTH M West Jct (STH 073, Taylor County Thorp - Ingram). Let by Wisconsin DOT on January 14, 2025, Taylor. 1 bid received; low bid $3,161,069 by American Asphalt of Wisconsin.

Owner
Wisconsin DOT
Letting
14 JAN 2025
Pay items
93
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1American Asphalt of Wisconsin$3,161,069Low
WisDOT contract 20250114035: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. American Asphalt of Wisconsin
1Removing structure over waterway minimal debris (structure) 01. C-60- 800 (203.0260)EACH1$11,020
2Removing asphaltic surface (204.0110)SY640$10.50
3Removing asphaltic surface butt joints (204.0115)SY316$25.59
4Removing asphaltic surface milling (204.0120)SY108,640$2.09
5Excavation for structures culverts (structure) 01. C-60-23 (206.2001)EACH1$22,710
6Backfill structure type B (210.2500)TON1,082$19.25
7Prepare foundation for asphaltic paving (project) 01. 8210-00-72 (211.0101)EACH1$6,956.88
8Prepare foundation for asphaltic shoulders (211.0400)STA6$115.95
9Finishing roadway (project) 01. 8210-00-72 (213.0100)EACH1$2,840.87
10Base aggregate dense 3/4-inch (305.0110)TON1,710$27.18
11Base aggregate dense 1 1/4-inch (305.0120)TON500$19.72
12Base aggregate open-graded (310.0110)TON36$0.01
13Breaker run (311.0115)CY62$25.00
14Tack coat (455.0605)GAL15,210$3.97
15HMA percent within limits (PWL) test strip volumetrics (460.0105.S)EACH1$3,500.00
16HMA percent within limits (PWL) test strip density (460.0110.S)EACH2$3,500.00
17Incentive density PWL HMA pavement (460.2005)DOL16,656$1.00
18Incentive density HMA pavement longitudinal joints (460.2007)DOL12,630$1.00
19Incentive air voids HMA pavement (460.2010)DOL21,290$1.00
20HMA pavement 4 MT 58-34 V (460.6644)TON21,290$90.06
21Material transfer vehicle (460.9000.S)EACH1$30,000
22Asphaltic surface (465.0105)TON645$153.14
23Asphaltic surface patching (465.0110)TON200$157.92
24Asphaltic surface detours (465.0115)TON50$246.15
25Asphaltic surface driveways and field entrances (465.0120)TON5$233.67
26Asphaltic rumble strips, centerline (465.0560)LF26,765$0.22
27Concrete masonry culverts (504.0100)CY99$864.00
28Bar steel reinforcement HS structures (505.0400)LB8,833$1.05
29Bar steel reinforcement HS coated structures (505.0600)LB1,951$1.45
30Rubberized membrane waterproofing (516.0500)SY20$45.00
31Cleaning culvert pipes (520.8700)EACH1$800.00
32Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024)EACH2$1,750.00
33Culvert pipe salvaged 24-inch (524.0124)LF50$125.00
34Riprap heavy (606.0300)CY105$70.00
35Barrier system grading shaping finishing (614.0010)EACH2$7,950.00
36Adjusting steel plate beam guard (614.0400)LF360$9.00
37Salvaged rail (614.0920)LF360$4.00
38Salvaged guardrail end treatments (614.0925)EACH4$250.00
39Replacing guardrail posts and blocks (614.0950)EACH8$90.00
40Replacing guardrail rail and hardware (614.0951)LF50$17.00
41Replacing guardrail reflectors (614.0952)EACH2$12.00
42MGS guardrail 3 L (614.2340)LF205$28.00
43MGS guardrail terminal eat (614.2610)EACH4$3,100.00
44Maintenance and repair of haul roads (project) 01. 8210-00-72 (618.0100)EACH1$1.00
45Mobilization (619.1000)EACH1$199,794
46Water (624.0100)MGAL10$50.00
47Salvaged topsoil (625.0500)SY243$3.95
48Silt fence (628.1504)LF1,252$2.20
49Silt fence maintenance (628.1520)LF1,252$0.02
50Mobilizations erosion control (628.1905)EACH3$100.00
51Mobilizations emergency erosion control (628.1910)EACH2$50.00
52Erosion mat urban class I type A (628.2006)SY183$1.95
53Erosion mat urban class I type B (628.2008)SY1,190$1.95
54Polyethylene sheeting (628.5505)SY230$1.00
55Temporary ditch checks (628.7504)LF82$8.00
56Culvert pipe checks (628.7555)EACH8$12.00
57Rock bags (628.7570)EACH210$12.00
58Fertilizer type B (629.0210)CWT0.20$85.00
59Seeding mixture no. 20 (630.0120)LB1.60$8.80
60Seeding mixture no. 60 (630.0160)LB3.60$18.00
61Seeding temporary (630.0200)LB6.80$4.00
62Seed water (630.0500)MGAL30.30$2.00
63Markers culvert end (633.5200)EACH6$55.00
64Posts wood 4X6-inch X 14-FT (634.0614)EACH2$77.00
65Signs type II reflective F (637.2230)SF18.14$24.80
66Moving signs type II (638.2102)EACH1$100.00
67Removing signs type II (638.2602)EACH4$20.00
68Removing small sign supports (638.3000)EACH1$20.00
69Moving small sign supports (638.4000)EACH1$95.00
70Field office type B (642.5001)EACH1$9,575.00
71Traffic control drums (643.0300)DAY2,640$0.30
72Traffic control barricades type III (643.0420)DAY1,064$1.00
73Traffic control warning lights type A (643.0705)DAY2,048$0.10
74Traffic control signs (643.0900)DAY18,660$0.50
75Traffic control covering signs type II (643.0920)EACH8$25.00
76Traffic control signs PCMS (643.1050)DAY14$38.00
77Temporary marking line paint 6- inch (643.3165)LF12,672$1.80
78Traffic control (643.5000)EACH1$1,900.00
79Geotextile type C (645.0105)SY168$4.00
80Geotextile type HR (645.0120)SY45$5.00
81Marking line grooved wet ref epoxy 6-inch (646.2040)LF77,160$1.35
82Marking line grooved wet ref epoxy 10-inch (646.4040)LF520$2.90
83Marking railroad crossing epoxy (646.5320)EACH5$1,200.00
84Marking removal line water blasting wide (646.9210)LF72$5.00
85Marking removal special marking water blasting (646.9310)EACH5$180.00
86Construction staking pipe culverts (650.6000)EACH1$500.00
87Construction staking structure layout (structure) 01. C-60-23 (650.6501)EACH1$2,500.00
88Construction staking resurfacing reference (650.8000)LF31,612$0.07
89Construction staking supplemental control (project) 01. 8210-00-72 (650.9911)EACH1$10.00
90Sawing asphalt (690.0150)LF145$12.85
91Incentive iri ride (740.0440)DOL24,000$1.00
92On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS2,000$5.00
93On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS1,320$5.00
WisDOT contract 20250114035: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of January 14, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy