WisDOT contract 20260310025 bid tabulation
1520-00-74. Let by Wisconsin DOT on March 10, 2026, Wood. 7 bids received; low bid $4,344,262 by Haas Sons, Inc..
- Owner
- Wisconsin DOT
- Letting
- 10 MAR 2026
- Pay items
- 176
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Haas Sons, Inc. | $4,344,262 | Low |
| 2 | Earth, Inc. | $4,429,543 | +2.0% |
| 3 | Mashuda Contractors, Inc. | $4,452,247 | +2.0% |
| 4 | James Peterson Sons, Inc. | $4,560,664 | +5.0% |
| 5 | McCabe Construction, Inc. | $4,621,230 | +6.0% |
| 6 | Gerke Excavating Inc | $4,680,901 | +8.0% |
| 7 | Integrity Grading and Excavating, Inc. | $4,754,748 | +9.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Haas Sons, Inc. | 2. Earth, Inc. | 3. Mashuda Contractors, Inc. | 4. James Peterson Sons, Inc. | 5. McCabe Construction, Inc. | 6. Gerke Excavating Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing small pipe culverts (203.0100) | EACH | 5 | $1,063.96 | $1,000.00 | $350.00 | $500.00 | $800.00 | $739.40 |
| 2 | Removing structure (structure) 01. C-71-9002 (203.0220) | EACH | 1 | $11,519 | $12,000 | $4,000.00 | $1,500.00 | $7,150.00 | $5,820.12 |
| 3 | Removing concrete pavement (204.0100) | SY | 92 | $150.66 | $10.00 | $10.00 | $12.57 | $11.00 | $10.74 |
| 4 | Removing asphaltic surface (204.0110) | SY | 2,817 | $6.48 | $6.00 | $3.00 | $10.00 | $4.00 | $3.06 |
| 5 | Removing asphaltic surface butt joints (204.0115) | SY | 786 | $3.79 | $11.00 | $11.30 | $11.30 | $11.75 | $2.65 |
| 6 | Removing asphaltic surface milling (204.0120) | SY | 32,340 | $2.46 | $3.15 | $3.43 | $3.43 | $3.57 | $1.70 |
| 7 | Removing gutter (204.0140) | LF | 1,430 | $5.46 | $4.00 | $2.00 | $3.00 | $3.00 | $2.01 |
| 8 | Removing curb & gutter (204.0150) | LF | 4,767 | $9.66 | $5.00 | $3.75 | $5.48 | $5.00 | $3.20 |
| 9 | Removing concrete sidewalk (204.0155) | SY | 660 | $8.12 | $10.00 | $10.00 | $33.50 | $10.00 | $4.93 |
| 10 | Removing inlets (204.0220) | EACH | 2 | $524.71 | $500.00 | $500.00 | $450.00 | $400.00 | $248.16 |
| 11 | Removing storm sewer (size) 01. 24-inch (204.0245) | LF | 120 | $20.69 | $20.00 | $25.00 | $36.40 | $22.00 | $12.41 |
| 12 | Excavation common (205.0100) | CY | 26,105 | $9.11 | $9.00 | $7.67 | $9.83 | $14.35 | $13.20 |
| 13 | Finishing roadway (project) 01. 1520-00-74 (213.0100) | EACH | 1 | $725.12 | $5,000.00 | $550.00 | $2,500.00 | $1,305.00 | $3,545.36 |
| 14 | Finishing roadway (project) 02. 1620-02-77 (213.0100) | EACH | 1 | $2,175.37 | $5,000.00 | $325.00 | $2,500.00 | $1,305.00 | $3,545.36 |
| 15 | Base aggregate dense 3/4-inch (305.0110) | TON | 546 | $26.49 | $26.00 | $26.46 | $28.87 | $24.25 | $26.82 |
| 16 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 18,625 | $15.99 | $15.25 | $17.05 | $18.56 | $17.50 | $17.30 |
| 17 | Base aggregate open-graded (310.0110) | TON | 147 | $24.63 | $25.00 | $40.50 | $21.33 | $35.00 | $63.93 |
| 18 | Select crushed material (312.0110) | TON | 17,857 | $14.94 | $14.00 | $19.95 | $15.86 | $17.52 | $18.41 |
| 19 | QMP base aggregate dense 1 1/4- inch compaction (371.2000.S) | EACH | 9 | $737.04 | $750.00 | $750.00 | $775.00 | $766.00 | $773.89 |
| 20 | Coloring concrete wisdot red (405.0100) | CY | 352 | $100.00 | $100.00 | $82.95 | $82.95 | $86.27 | $87.10 |
| 21 | Concrete truck apron 12-inch (415.2010) | SY | 1,055 | $107.00 | $107.00 | $93.18 | $93.18 | $96.91 | $97.84 |
| 22 | Tack coat (455.0605) | GAL | 6,664 | $5.45 | $5.50 | $5.45 | $5.45 | $5.67 | $5.72 |
| 23 | Incentive density HMA pavement (460.2000) | DOL | 7,391 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 24 | HMA pavement 4 MT 58-28 S (460.6224) | TON | 3,247 | $110.20 | $110.50 | $110.20 | $110.20 | $114.62 | $115.71 |
| 25 | HMA pavement 4 MT 58-28 H (460.6424) | TON | 3,247 | $115.80 | $116.00 | $115.80 | $115.80 | $120.45 | $121.59 |
| 26 | HMA pavement 3 HT 58-28 S (460.7223) | TON | 3,609 | $110.40 | $110.54 | $110.40 | $110.40 | $114.83 | $115.92 |
| 27 | HMA pavement 4 HT 58-28 V (460.7624) | TON | 1,442 | $119.50 | $119.50 | $119.50 | $119.50 | $124.29 | $125.48 |
| 28 | Asphaltic surface (465.0105) | TON | 562 | $164.45 | $164.50 | $164.45 | $164.45 | $171.05 | $172.67 |
| 29 | Asphaltic surface patching (465.0110) | TON | 104 | $214.45 | $214.50 | $214.45 | $214.45 | $223.05 | $225.17 |
| 30 | Asphaltic surface driveways and field entrances (465.0120) | TON | 93 | $210.10 | $210.50 | $210.10 | $210.10 | $218.53 | $220.61 |
| 31 | Asphaltic flumes (465.0315) | SY | 100 | $88.95 | $89.00 | $88.95 | $88.95 | $92.52 | $93.40 |
| 32 | Asphaltic rumble strips, centerline (465.0560) | LF | 218 | $15.00 | $16.00 | $6.41 | $6.41 | $6.67 | $15.75 |
| 33 | Apron endwalls for culvert pipe 18- inch (520.1018) | EACH | 7 | $882.61 | $275.00 | $710.00 | $269.65 | $521.00 | $996.86 |
| 34 | Apron endwalls for culvert pipe 21- inch (520.1021) | EACH | 2 | $589.02 | $300.00 | $444.00 | $346.28 | $460.00 | $486.04 |
| 35 | Apron endwalls for culvert pipe 24- inch (520.1024) | EACH | 3 | $1,063.29 | $400.00 | $740.00 | $175.00 | $460.00 | $1,027.76 |
| 36 | Culvert pipe class III-A 18-inch (520.3318) | LF | 96 | $58.90 | $80.00 | $61.00 | $96.53 | $65.00 | $38.37 |
| 37 | Culvert pipe class III-A 21-inch (520.3321) | LF | 50 | $58.90 | $83.00 | $66.25 | $101.13 | $76.00 | $41.61 |
| 38 | Culvert pipe class III-A 24-inch (520.3324) | LF | 112 | $58.90 | $88.00 | $74.75 | $105.33 | $125.00 | $45.61 |
| 39 | Culvert pipe reinforced concrete class III 96-inch (522.0196) | LF | 86 | $1,266.29 | $1,245.00 | $1,372.00 | $1,205.61 | $1,150.00 | $1,474.36 |
| 40 | Culvert pipe reinforced concrete class IV 36-inch (522.0436) | LF | 67 | $302.02 | $245.00 | $261.25 | $257.47 | $350.00 | $380.96 |
| 41 | Apron endwalls for culvert pipe reinforced concrete 36-inch (522.1036) | EACH | 2 | $2,301.19 | $5,000.00 | $2,168.00 | $2,989.81 | $2,600.00 | $2,971.70 |
| 42 | Concrete curb & gutter 18-inch type A (601.0405) | LF | 195 | $24.80 | $25.00 | $42.65 | $42.65 | $44.36 | $44.78 |
| 43 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 3,654 | $21.00 | $21.00 | $35.83 | $35.83 | $37.26 | $37.62 |
| 44 | Concrete curb & gutter 4-inch sloped 36-inch type A (601.0551) | LF | 636 | $28.00 | $28.00 | $25.25 | $25.25 | $26.26 | $26.51 |
| 45 | Concrete curb & gutter 4-inch sloped 36-inch type D (601.0553) | LF | 1,543 | $27.20 | $27.50 | $25.25 | $25.25 | $26.26 | $26.51 |
| 46 | Concrete curb & gutter 4-inch sloped 30-inch type R (601.0581) | LF | 368 | $28.00 | $28.00 | $39.78 | $39.78 | $41.37 | $41.77 |
| 47 | Concrete curb pedestrian (601.0600) | LF | 326 | $39.00 | $39.00 | $34.87 | $34.87 | $36.26 | $36.61 |
| 48 | Concrete sidewalk 4-inch (602.0405) | SF | 8,171 | $6.40 | $7.00 | $5.92 | $5.92 | $6.16 | $6.22 |
| 49 | Concrete sidewalk 5-inch (602.0410) | SF | 14,577 | $7.80 | $8.00 | $9.32 | $9.32 | $10.20 | $9.79 |
| 50 | Concrete sidewalk 6-inch (602.0415) | SF | 76 | $9.90 | $10.00 | $9.94 | $9.94 | $10.34 | $10.44 |
| 51 | Curb ramp detectable warning field yellow (602.0505) | SF | 618 | $61.00 | $61.00 | $59.37 | $59.37 | $61.74 | $62.34 |
| 52 | Curb ramp detectable warning field radial yellow (602.0605) | SF | 143 | $65.00 | $65.00 | $66.89 | $66.89 | $69.57 | $70.23 |
| 53 | Concrete driveway 6-inch (602.0810) | SY | 86 | $85.00 | $85.00 | $68.62 | $68.62 | $84.15 | $72.05 |
| 54 | Riprap light (606.0100) | CY | 31 | $64.49 | $100.00 | $95.00 | $130.00 | $110.00 | $82.97 |
| 55 | Riprap medium (606.0200) | CY | 22 | $110.82 | $110.00 | $100.00 | $193.00 | $110.00 | $79.00 |
| 56 | Riprap heavy (606.0300) | CY | 12 | $145.30 | $120.00 | $110.00 | $141.00 | $110.00 | $111.89 |
| 57 | Storm sewer pipe reinforced concrete class III 12-inch (608.0312) | LF | 124 | $84.99 | $70.00 | $106.50 | $127.30 | $85.00 | $96.95 |
| 58 | Storm sewer pipe reinforced concrete class III 18-inch (608.0318) | LF | 352 | $85.35 | $72.00 | $105.75 | $119.77 | $86.00 | $68.88 |
| 59 | Storm sewer pipe reinforced concrete class III 24-inch (608.0324) | LF | 76 | $111.01 | $98.00 | $138.25 | $140.11 | $120.00 | $93.02 |
| 60 | Inlet covers type HM-GJ-S (611.0633) | EACH | 1 | $1,262.38 | $1,350.00 | $1,240.00 | $1,816.17 | $1,085.00 | $1,132.68 |
| 61 | Inlet covers type HM-S (611.0636) | EACH | 6 | $1,045.55 | $1,250.00 | $955.00 | $1,695.77 | $990.00 | $1,031.21 |
| 62 | Inlet covers type H-S (611.0639) | EACH | 4 | $1,045.55 | $1,200.00 | $955.00 | $1,655.17 | $960.00 | $997.92 |
| 63 | Inlet covers type MS (611.0642) | EACH | 1 | $862.57 | $1,100.00 | $620.00 | $974.20 | $600.00 | $760.77 |
| 64 | Inlet covers type T (611.0652) | EACH | 2 | $5,232.18 | $1,750.00 | $1,230.00 | $2,016.37 | $1,245.00 | $1,296.56 |
| 65 | Manholes 5-FT diameter (611.2005) | EACH | 1 | $4,800.72 | $6,600.00 | $6,016.00 | $5,816.30 | $5,260.00 | $5,397.02 |
| 66 | Inlets 4-FT diameter (611.3004) | EACH | 1 | $2,904.17 | $3,600.00 | $3,210.00 | $3,059.33 | $2,765.00 | $3,206.28 |
| 67 | Inlets 2X2.5-FT (611.3225) | EACH | 1 | $2,661.59 | $2,400.00 | $3,096.00 | $2,438.30 | $2,000.00 | $2,683.06 |
| 68 | Inlets 2X3-FT (611.3230) | EACH | 10 | $2,355.59 | $2,500.00 | $3,193.00 | $2,517.94 | $2,150.00 | $2,909.70 |
| 69 | Inlets median 1 grate (611.3901) | EACH | 1 | $3,804.83 | $4,000.00 | $4,413.00 | $3,949.92 | $3,380.00 | $3,997.16 |
| 70 | Adjusting manhole covers (611.8110) | EACH | 10 | $542.03 | $1,000.00 | $900.00 | $652.64 | $525.00 | $751.22 |
| 71 | Adjusting inlet covers (611.8115) | EACH | 23 | $433.62 | $750.00 | $1,100.00 | $766.17 | $420.00 | $796.16 |
| 72 | Pipe underdrain 6-inch (612.0106) | LF | 2,568 | $8.79 | $12.00 | $12.55 | $10.57 | $12.00 | $17.33 |
| 73 | Fence safety (616.0700.S) | LF | 456 | $2.65 | $3.00 | $2.65 | $2.65 | $2.76 | $2.78 |
| 74 | Maintenance and repair of haul roads (project) 01. 1520-00-74 (618.0100) | EACH | 1 | $100.00 | $1,000.00 | $1.00 | $550.00 | $1.00 | $0.01 |
| 75 | Maintenance and repair of haul roads (project) 02. 1620-02-77 (618.0100) | EACH | 1 | $100.00 | $1,000.00 | $1.00 | $550.00 | $1.00 | $0.01 |
| 76 | Mobilization (619.1000) | EACH | 1 | $259,927 | $238,450 | $218,822 | $304,045 | $170,000 | $263,440 |
| 77 | Concrete median sloped nose (620.0300) | SF | 386 | $15.00 | $18.00 | $11.01 | $11.01 | $11.45 | $11.56 |
| 78 | Water (624.0100) | MGAL | 191.80 | $47.34 | $35.00 | $35.00 | $50.00 | $42.00 | $29.15 |
| 79 | Topsoil (625.0100) | SY | 17,781 | $5.67 | $2.00 | $2.50 | $3.50 | $5.50 | $5.45 |
| 80 | Silt fence (628.1504) | LF | 4,311 | $1.94 | $2.10 | $1.94 | $1.94 | $2.02 | $2.04 |
| 81 | Silt fence maintenance (628.1520) | LF | 4,311 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 82 | Mobilizations erosion control (628.1905) | EACH | 10 | $50.00 | $50.00 | $50.00 | $50.00 | $52.01 | $52.50 |
| 83 | Mobilizations emergency erosion control (628.1910) | EACH | 10 | $50.00 | $50.00 | $50.00 | $50.00 | $52.01 | $52.50 |
| 84 | Erosion mat class I type A (628.2002) | SY | 352 | $1.06 | $2.00 | $1.06 | $1.06 | $1.10 | $1.11 |
| 85 | Erosion mat class I type B (628.2004) | SY | 13,840 | $1.06 | $2.10 | $1.06 | $1.06 | $1.10 | $1.11 |
| 86 | Erosion mat urban class I type A (628.2006) | SY | 991 | $1.77 | $1.77 | $1.77 | $1.77 | $1.84 | $1.86 |
| 87 | Erosion mat urban class I type B (628.2008) | SY | 2,586 | $1.85 | $1.85 | $1.85 | $1.85 | $1.92 | $1.94 |
| 88 | Inlet protection type A (628.7005) | EACH | 14 | $100.00 | $100.00 | $100.00 | $100.00 | $104.01 | $105.00 |
| 89 | Inlet protection type B (628.7010) | EACH | 1 | $62.00 | $65.00 | $62.00 | $62.00 | $64.49 | $65.10 |
| 90 | Inlet protection type C (628.7015) | EACH | 68 | $65.00 | $65.00 | $65.00 | $65.00 | $67.61 | $68.25 |
| 91 | Inlet protection type D (628.7020) | EACH | 13 | $142.75 | $143.00 | $142.75 | $142.75 | $148.48 | $149.89 |
| 92 | Temporary ditch checks (628.7504) | LF | 88 | $7.50 | $7.50 | $7.50 | $7.50 | $7.80 | $7.88 |
| 93 | Culvert pipe checks (628.7555) | EACH | 62 | $16.55 | $17.00 | $16.55 | $16.55 | $17.21 | $17.38 |
| 94 | Rock bags (628.7570) | EACH | 50 | $15.80 | $16.00 | $15.80 | $15.80 | $16.43 | $16.59 |
| 95 | Fertilizer type B (629.0210) | CWT | 13 | $103.00 | $105.00 | $103.00 | $103.00 | $107.13 | $108.15 |
| 96 | Seeding mixture no. 20 (630.0120) | LB | 683 | $7.55 | $7.75 | $7.55 | $7.55 | $7.85 | $7.93 |
| 97 | Seeding mixture no. 40 (630.0140) | LB | 107 | $18.00 | $18.00 | $18.00 | $18.00 | $18.72 | $18.90 |
| 98 | Seed water (630.0500) | MGAL | 404.90 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 99 | Markers culvert end (633.5200) | EACH | 10 | $62.00 | $65.00 | $62.00 | $62.00 | $64.49 | $65.10 |
| 100 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 7 | $88.25 | $90.00 | $88.25 | $88.25 | $91.79 | $92.66 |
| 101 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 31 | $94.25 | $95.00 | $94.25 | $94.25 | $98.03 | $98.96 |
| 102 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 11 | $108.25 | $110.00 | $108.25 | $108.25 | $112.59 | $113.66 |
| 103 | Posts wood 4X6-inch X 20-FT (634.0620) | EACH | 6 | $120.75 | $121.00 | $120.75 | $120.75 | $125.59 | $126.79 |
| 104 | Posts wood 4X6-inch X 22-FT (634.0622) | EACH | 6 | $128.75 | $129.00 | $128.75 | $128.75 | $133.92 | $135.19 |
| 105 | Posts tubular steel 2X2-inch X 14- FT (634.0814) | EACH | 19 | $253.00 | $255.00 | $253.00 | $253.00 | $263.15 | $265.65 |
| 106 | Signs type II reflective H (637.2210) | SF | 734.54 | $18.65 | $19.00 | $18.65 | $18.65 | $19.40 | $19.58 |
| 107 | Signs type II reflective F (637.2230) | SF | 56 | $22.25 | $22.50 | $22.25 | $22.25 | $23.14 | $23.36 |
| 108 | Removing signs type II (638.2602) | EACH | 68 | $18.00 | $18.00 | $18.00 | $18.00 | $18.72 | $18.90 |
| 109 | Removing small sign supports (638.3000) | EACH | 74 | $18.00 | $18.00 | $18.00 | $18.00 | $18.72 | $18.90 |
| 110 | Field office type C (642.5201) | EACH | 1 | $15,500 | $12,500 | $8,000.00 | $13,125 | $8,000.00 | $13,164 |
| 111 | Traffic control drums (643.0300) | DAY | 12,047 | $0.50 | $1.00 | $0.15 | $0.15 | $0.16 | $0.53 |
| 112 | Traffic control barricades type III (643.0420) | DAY | 5,422 | $1.00 | $1.50 | $0.45 | $0.45 | $0.47 | $1.05 |
| 113 | Traffic control warning lights type A (643.0705) | DAY | 1,438 | $1.00 | $0.10 | $0.10 | $0.10 | $0.10 | $1.05 |
| 114 | Traffic control signs (643.0900) | DAY | 45,330 | $0.35 | $1.10 | $0.17 | $0.17 | $0.18 | $0.37 |
| 115 | Traffic control covering signs type II (643.0920) | EACH | 41 | $25.00 | $35.00 | $110.00 | $110.00 | $114.41 | $26.25 |
| 116 | Traffic control signs fixed message (643.1000) | SF | 90 | $25.00 | $11.30 | $14.50 | $14.50 | $15.08 | $26.25 |
| 117 | Temporary marking crosswalk removable tape 6-inch (643.3350) | LF | 2,673 | $1.50 | $2.50 | $2.25 | $2.25 | $2.34 | $1.58 |
| 118 | Traffic control (643.5000) | EACH | 1 | $25,000 | $20,000 | $54,500 | $54,500 | $56,687 | $26,250 |
| 119 | Temporary pedestrian surface plate (644.1430) | SF | 148 | $10.00 | $15.00 | $12.10 | $12.10 | $12.59 | $10.50 |
| 120 | Temporary pedestrian surface matting (644.1440) | SF | 2,351 | $5.00 | $15.00 | $2.75 | $2.75 | $2.86 | $5.25 |
| 121 | Temporary pedestrian curb ramp (644.1601) | DAY | 1,997 | $7.00 | $10.00 | $7.00 | $7.00 | $7.28 | $7.35 |
| 122 | Temporary pedestrian detectable warning field (644.1605) | SF | 830 | $9.00 | $8.00 | $6.00 | $6.00 | $6.24 | $9.45 |
| 123 | Temporary pedestrian barricade (644.1810) | LF | 3,880 | $4.00 | $14.00 | $5.00 | $5.00 | $5.20 | $4.20 |
| 124 | Geotextile type DF schedule A (645.0111) | SY | 1,588 | $0.81 | $2.00 | $2.75 | $0.86 | $1.50 | $1.74 |
| 125 | Geotextile type HR (645.0120) | SY | 115 | $7.00 | $4.00 | $11.00 | $7.45 | $6.50 | $5.84 |
| 126 | Geotextile type R (645.0130) | SY | 122 | $3.89 | $5.00 | $6.75 | $4.13 | $5.80 | $5.58 |
| 127 | Geotextile type sas (645.0140) | SY | 18,315 | $1.27 | $2.10 | $1.15 | $1.95 | $1.52 | $1.34 |
| 128 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 40,526 | $1.40 | $1.40 | $1.30 | $1.30 | $1.35 | $1.47 |
| 129 | Marking line grooved wet ref epoxy 10-inch (646.4040) | LF | 260 | $3.00 | $3.00 | $2.76 | $2.76 | $2.87 | $3.15 |
| 130 | Marking stop line epoxy 18-inch (646.6120) | LF | 359 | $20.00 | $20.00 | $15.49 | $15.49 | $16.11 | $21.00 |
| 131 | Marking dotted extension epoxy 18-inch (646.6320) | LF | 72 | $20.00 | $20.00 | $15.49 | $15.49 | $16.11 | $21.00 |
| 132 | Marking diagonal epoxy 12-inch (646.7120) | LF | 261 | $16.00 | $16.00 | $15.07 | $15.07 | $15.67 | $16.80 |
| 133 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 2,438 | $13.00 | $13.00 | $14.66 | $14.66 | $15.25 | $13.65 |
| 134 | Marking curb epoxy (646.8120) | LF | 40 | $25.00 | $25.00 | $7.40 | $7.40 | $7.70 | $26.25 |
| 135 | Marking island nose epoxy (646.8220) | EACH | 4 | $330.00 | $330.00 | $279.18 | $279.18 | $290.38 | $346.50 |
| 136 | Construction staking storm sewer (650.4000) | EACH | 18 | $100.00 | $150.00 | $150.00 | $150.00 | $156.02 | $157.50 |
| 137 | Construction staking subgrade (650.4500) | LF | 3,692 | $0.01 | $1.00 | $0.01 | $0.01 | $0.01 | $0.01 |
| 138 | Construction staking base (650.5000) | LF | 3,692 | $0.75 | $0.66 | $0.66 | $0.66 | $0.69 | $0.69 |
| 139 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 6,335 | $0.80 | $0.62 | $0.62 | $0.62 | $0.64 | $0.65 |
| 140 | Construction staking pipe culverts (650.6000) | EACH | 3 | $125.00 | $150.00 | $150.00 | $150.00 | $156.02 | $157.50 |
| 141 | Construction staking resurfacing reference (650.8000) | LF | 7,873 | $0.10 | $0.13 | $0.13 | $0.13 | $0.14 | $0.14 |
| 142 | Construction staking electrical installations (project) 01. 1520-00- 74 (650.8501) | EACH | 1 | $3,000.00 | $1,200.00 | $1,200.00 | $1,200.00 | $1,248.14 | $1,260.00 |
| 143 | Construction staking curb ramps (650.9000) | EACH | 63 | $190.00 | $135.00 | $135.00 | $135.00 | $140.42 | $141.75 |
| 144 | Construction staking sidewalk (project) 01. 1520-00-74 (650.9500) | EACH | 1 | $3,000.00 | $800.00 | $800.00 | $800.00 | $832.10 | $840.00 |
| 145 | Construction staking sidewalk (project) 02. 1620-02-77 (650.9500) | EACH | 1 | $3,000.00 | $800.00 | $800.00 | $800.00 | $832.10 | $840.00 |
| 146 | Construction staking supplemental control (project) 01. 1520-00-74 (650.9911) | EACH | 1 | $2,000.00 | $900.00 | $900.00 | $900.00 | $936.11 | $945.00 |
| 147 | Construction staking supplemental control (project) 02. 1620-02-77 (650.9911) | EACH | 1 | $2,500.00 | $900.00 | $900.00 | $900.00 | $936.11 | $945.00 |
| 148 | Construction staking slope stakes (650.9920) | LF | 6,210 | $0.80 | $0.77 | $0.77 | $0.77 | $0.80 | $0.81 |
| 149 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 75 | $7.50 | $8.00 | $7.50 | $7.50 | $7.80 | $7.88 |
| 150 | Conduit rigid nonmetallic schedule 40 3-inch (652.0235) | LF | 969 | $12.00 | $12.00 | $12.00 | $12.00 | $12.48 | $12.60 |
| 151 | Pull boxes non-conductive 24X42- inch (653.0164) | EACH | 9 | $1,960.00 | $1,960.00 | $1,960.00 | $1,960.00 | $2,038.64 | $2,058.00 |
| 152 | Concrete bases type 5 (654.0105) | EACH | 15 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,040.12 | $1,050.00 |
| 153 | Concrete control cabinet bases type L24 (654.0224) | EACH | 1 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 | $2,600.30 | $2,625.00 |
| 154 | Electrical wire lighting 12 AWG (655.0610) | LF | 2,430 | $0.90 | $1.00 | $0.90 | $0.90 | $0.94 | $0.95 |
| 155 | Electrical wire lighting 10 AWG (655.0615) | LF | 10,316 | $1.20 | $1.25 | $1.20 | $1.20 | $1.25 | $1.26 |
| 156 | Electrical service meter breaker pedestal (location) 01. LCC B (656.0201) | EACH | 1 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 | $2,600.30 | $2,625.00 |
| 157 | Transformer bases breakaway 11 1/2-inch bolt circle (657.0255) | EACH | 15 | $650.00 | $650.00 | $650.00 | $650.00 | $676.08 | $682.50 |
| 158 | Poles type 5-aluminum (657.0322) | EACH | 15 | $2,800.00 | $2,800.00 | $2,800.00 | $2,800.00 | $2,912.34 | $2,940.00 |
| 159 | Luminaire arms single member 4 1/2-inch clamp 8-FT (657.0615) | EACH | 15 | $650.00 | $650.00 | $650.00 | $650.00 | $676.08 | $682.50 |
| 160 | Luminaires utility LED A (659.1115) | EACH | 15 | $300.00 | $300.00 | $300.00 | $300.00 | $312.04 | $315.00 |
| 161 | Lighting control cabinets 120/240 24-inch (659.2124) | EACH | 1 | $10,000 | $10,000 | $10,000 | $10,000 | $10,401 | $10,500 |
| 162 | Public land reference monument verify and reset (680.0100) | EACH | 1 | $2,000.00 | $1,000.00 | $950.00 | $950.00 | $988.11 | $997.50 |
| 163 | Sawing asphalt (690.0150) | LF | 2,593 | $1.65 | $3.50 | $1.65 | $1.65 | $1.72 | $1.58 |
| 164 | Sawing concrete (690.0250) | LF | 253 | $4.60 | $6.00 | $2.30 | $2.30 | $2.39 | $2.63 |
| 165 | Incentive iri ride (740.0440) | DOL | 4,221 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 166 | Installing and maintaining climbing turtle exclusion fence (999.2100.S) | LF | 6,437 | $2.32 | $2.75 | $2.32 | $2.32 | $2.41 | $2.44 |
| 167 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,000 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 168 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 1,260 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 169 | Special 01. temporary water diversion - sta 636+37 (SPV.0060) | EACH | 1 | $2,250.00 | $5,000.00 | $1.00 | $2,500.00 | $1,750.00 | $6,527.67 |
| 170 | Special 02. temporary water diversion - sta 1555+67 (SPV.0060) | EACH | 1 | $2,750.00 | $25,000 | $75,000 | $6,500.00 | $17,000 | $18,265 |
| 171 | Special 03. cored holes 6-inch (SPV.0060) | EACH | 11 | $240.86 | $1,500.00 | $400.00 | $375.00 | $165.00 | $346.99 |
| 172 | Special 04. adjusting water valve boxes (SPV.0060) | EACH | 1 | $433.62 | $500.00 | $500.00 | $375.00 | $400.00 | $973.45 |
| 173 | Special 05. apron endwalls for culvert pipe reinforced concrete 96-inch (SPV.0060) | EACH | 2 | $9,665.34 | $12,500 | $9,543.00 | $11,879 | $9,000.00 | $10,435 |
| 174 | Special 06. temporary lighting system, STH 73/STH 80 roundabout (SPV.0060) | EACH | 1 | $10,000 | $10,000 | $10,000 | $10,000 | $10,400 | $10,500 |
| 175 | Special 01. seeding no mow fescue (SPV.0085) | LB | 17 | $53.00 | $55.00 | $53.00 | $53.00 | $55.13 | $55.65 |
| 176 | Special 01. removing distressed pavement milling (SPV.0180) | SY | 734 | $3.79 | $10.00 | $11.30 | $11.30 | $11.75 | $2.65 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of March 10, 2026. Compiled by Mirage Metrics.