WisDOT contract 20251209002 bid tabulation

Dodgeville - Mount Horeb; CTH F Intersection (USH 018, Dane County Dodgeville - Mount Horeb). Let by Wisconsin DOT on December 9, 2025, Dane. 4 bids received; low bid $2,454,567 by Rock Road Companies, Inc..

Owner
Wisconsin DOT
Letting
09 DEC 2025
Pay items
146
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Rock Road Companies, Inc.$2,454,567Low
2H. James & Sons, Inc$2,526,124+3.0%
3Parisi Construction, LLC$2,678,325+9.0%
4Integrity Grading and Excavating, Inc.$2,728,027+11%
WisDOT contract 20251209002: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Rock Road Companies, Inc.2. H. James & Sons, Inc3. Parisi Construction, LLC4. Integrity Grading and Excavating, Inc.
1Grubbing (201.0205)STA2$1,000.00$1,160.00$1,500.00$1,300.00
2Removing asphaltic surface milling (204.0120)SY1,065$17.14$16.00$18.00$16.00
3Removing curb & gutter (204.0150)LF340$6.21$7.88$9.41$8.78
4Removing guardrail (204.0165)LF472$4.00$4.00$4.50$4.00
5Removing delineators and markers (204.0180)EACH1$25.00$25.00$28.25$25.00
6Removing inlets (204.0220)EACH2$505.36$750.00$670.00$741.81
7Excavation common (205.0100)CY8,368$13.18$14.00$14.50$20.00
8Borrow (208.0100)CY4,551$29.94$21.00$20.00$29.00
9Prepare foundation for asphaltic paving (project) 01. 1204-05-77 (211.0101)EACH1$0.01$12,285$4,300.00$10,000
10Finishing roadway (project) 01. 1204-05-77 (213.0100)EACH1$5,352.17$1,000.00$500.00$500.00
11Base aggregate dense 3/4-inch (305.0110)TON664$30.13$31.84$27.00$57.54
12Base aggregate dense 1 1/4-inch (305.0120)TON19,061$14.79$22.13$18.25$17.25
13QMP base aggregate dense 1 1/4- inch compaction (371.2000.S)EACH18$300.00$800.00$790.00$696.50
14Tack coat (455.0605)GAL1,120$2.87$1.00$1.10$1.00
15Incentive density HMA pavement (460.2000)DOL3,238$1.00$1.00$1.00$1.00
16HMA pavement 4 MT 58-28 H (460.6424)TON5,055$95.79$97.50$110.00$97.50
17Asphaltic flumes (465.0315)SY12$65.86$65.00$74.00$65.00
18Apron endwalls for culvert pipe 24- inch (520.1024)EACH4$870.33$990.74$1,000.00$885.62
19Culvert pipe class III-A 24-inch (520.3324)LF220$77.49$77.27$73.00$87.27
20Concrete collars for pipe (520.8000)EACH2$525.97$1,000.00$670.00$3,991.11
21Apron endwalls for culvert pipe sloped side drains steel 24-inch 10 to 1 (521.1624)EACH2$4,217.13$4,214.07$4,700.00$1,475.79
22Culvert pipe corrugated steel 72- inch (521.3172)LF8$860.58$526.07$360.00$1,092.21
23Culvert pipe reinforced concrete class III 60-inch (522.0160)LF14$634.33$491.99$420.00$819.71
24Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 19X30-inch (522.2619)EACH1$1,606.18$1,983.69$3,700.00$2,354.19
25Apron endwalls for culvert pipe salvaged 60-inch (524.0660)EACH1$1,081.84$1,439.80$1,400.00$1,560.20
26Apron endwalls for culvert pipe salvaged 72-inch (524.0672)EACH1$1,081.84$1,060.00$1,400.00$1,180.35
27Concrete masonry ancillary structures type NS (531.1100)CY2$995.00$995.00$1,100.00$995.00
28Steel reinforcement HS ancillary structures type NS (531.1140)LB220$4.00$4.00$4.50$4.00
29Drilling shaft 24-inch (531.2024)LF16$75.00$75.00$85.00$75.00
30Concrete curb & gutter 6-inch sloped 30-inch type J (601.0415)LF2,711$25.00$25.00$25.00$25.00
31Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557)LF1,222$29.75$26.00$29.75$29.75
32Concrete sidewalk 5-inch (602.0410)SF6,225$6.60$7.00$6.60$6.60
33Riprap light (606.0100)CY17$123.13$175.00$110.00$111.15
34Riprap medium (606.0200)CY122$123.13$90.00$100.00$111.15
35Storm sewer rock excavation (608.0005)CY207$55.00$65.00$130.02$260.00
36Storm sewer pipe reinforced concrete class III 18-inch (608.0318)LF16$231.08$146.42$78.00$116.84
37Storm sewer pipe reinforced concrete class IV 12-inch (608.0412)LF115$106.04$98.87$98.00$109.88
38Storm sewer pipe reinforced concrete class IV 15-inch (608.0415)LF426$77.50$71.99$95.00$88.11
39Storm sewer pipe reinforced concrete class IV 18-inch (608.0418)LF420$79.66$75.00$98.00$90.54
40Storm sewer pipe reinforced concrete class IV 24-inch (608.0424)LF714$102.32$98.56$120.00$111.55
41Storm sewer pipe reinforced concrete horizontal elliptical class HE-IV 19X30-inch (608.2419)LF90$163.27$160.27$180.00$200.43
42Inlet covers type HM-GJ (611.0630)EACH18$1,035.23$1,221.37$1,100.00$1,101.20
43Inlet covers type MS (611.0642)EACH1$709.52$550.00$920.00$748.54
44Catch basins 5-FT diameter (611.1005)EACH2$3,933.79$3,530.00$4,100.00$4,692.12
45Inlets 4-FT diameter (611.3004)EACH12$2,754.38$2,432.43$2,800.00$3,519.75
46Inlets 2X3-FT (611.3230)EACH4$2,076.42$1,559.69$2,300.00$3,179.52
47Inlets median 1 grate (611.3901)EACH3$2,743.07$2,432.60$3,300.00$3,989.21
48Salvaged inlet covers (611.9710)EACH2$214.52$722.50$720.00$558.11
49Pipe grates (size) 01. 24-inch (611.9850.S)EACH6$1,694.64$1,615.62$2,200.00$1,819.88
50Pipe grates (size) 02. 19X30-inch (611.9850.S)EACH1$1,139.30$1,260.75$1,600.00$1,314.95
51MGS guardrail 3 (614.2300)LF462$30.00$30.00$34.00$30.00
52MGS guardrail terminal eat (614.2610)EACH1$4,200.00$4,200.00$4,800.00$4,200.00
53MGS guardrail terminal type 2 (614.2620)EACH1$2,500.00$2,500.00$2,800.00$2,500.00
54Fence woven wire (height) 01. 4.5- FT (616.0100)LF440$15.00$15.00$17.00$15.00
55Maintenance and repair of haul roads (project) 01. 1204-05-77 (618.0100)EACH1$0.01$1,000.00$350.00$500.00
56Mobilization (619.1000)EACH1$164,000$61,250$60,000$148,000
57Concrete median sloped nose (620.0300)SF402$12.50$13.00$12.50$12.50
58Water (624.0100)MGAL300$0.01$25.00$38.75$46.66
59Salvaged topsoil (625.0500)SY20,629$0.01$2.66$3.10$2.00
60Silt fence (628.1504)LF2,178$2.10$2.10$2.40$2.10
61Silt fence maintenance (628.1520)LF2,178$0.01$0.01$0.01$0.01
62Mobilizations erosion control (628.1905)EACH6$100.00$100.00$110.00$100.00
63Mobilizations emergency erosion control (628.1910)EACH5$100.00$100.00$110.00$100.00
64Erosion mat urban class I type A (628.2006)SY2,202$1.65$1.65$1.90$1.65
65Erosion mat class II type B (628.2023)SY18,428$1.65$1.65$1.90$1.65
66Inlet protection type A (628.7005)EACH3$110.00$110.00$120.00$110.00
67Inlet protection type C (628.7015)EACH18$60.00$60.00$68.00$60.00
68Temporary ditch checks (628.7504)LF140$8.50$8.50$9.60$8.50
69Culvert pipe checks (628.7555)EACH13$20.00$20.00$22.75$20.00
70Tracking pads (628.7560)EACH5$700.00$0.01$860.00$1,000.00
71Fertilizer type B (629.0210)CWT12$90.00$90.00$100.00$90.00
72Seeding mixture no. 30 (630.0130)LB934$8.75$8.75$9.90$8.75
73Seeding temporary (630.0200)LB560$4.00$4.00$4.50$4.00
74Seed water (630.0500)MGAL1,163$10.00$10.00$11.25$10.00
75Posts wood 4X6-inch X 16-FT (634.0616)EACH83$87.00$87.00$98.00$87.00
76Sign supports structural steel HS (635.0200)LB1,928$4.00$4.00$4.50$4.00
77Signs type II reflective H (637.2210)SF1,300.25$20.00$20.00$22.75$20.00
78Moving signs type I (638.2101)EACH1$800.00$800.00$910.00$800.00
79Moving signs type II (638.2102)EACH5$200.00$200.00$230.00$200.00
80Removing signs type II (638.2602)EACH31$35.00$35.00$39.50$35.00
81Removing small sign supports (638.3000)EACH26$35.00$35.00$39.50$35.00
82Field office type B (642.5001)EACH1$6,750.00$7,840.00$8,400.00$12,000
83Traffic control drums (643.0300)DAY10,408$0.25$0.25$0.30$0.25
84Digital speed reduction system (DSRS) (643.0370.S)DAY140$199.00$199.00$230.00$199.00
85Traffic control barricades type III (643.0420)DAY950$1.00$1.00$1.10$1.00
86Traffic control warning lights type A (643.0705)DAY1,900$0.25$0.25$0.30$0.25
87Traffic control warning lights type C (643.0715)DAY1,891$0.25$0.25$0.30$0.25
88Traffic control connected arrow boards (643.0810)DAY114$30.00$30.00$34.00$30.00
89Traffic control signs (643.0900)DAY2,548$0.25$0.25$0.30$0.25
90Traffic control covering signs type II (643.0920)EACH22$25.00$25.00$28.25$25.00
91Traffic control signs PCMS (643.1050)DAY140$35.00$35.00$39.50$35.00
92Traffic control connected work zone start and end location markers (643.1220)DAY70$25.00$25.00$28.25$25.00
93Temporary marking line paint 6- inch (643.3165)LF160$1.10$1.10$1.20$1.10
94Temporary marking line removable tape 6-inch (643.3180)LF4,899$1.10$1.10$1.20$1.10
95Temporary marking arrow removable tape (643.3550)EACH4$79.99$79.99$91.00$79.99
96Temporary marking word removable tape (643.3650)EACH2$105.00$105.00$120.00$105.00
97Temporary marking diagonal paint 12-inch (643.3905)LF23$5.00$5.00$5.70$5.00
98Traffic control (643.5000)EACH1$7,600.00$7,600.00$8,600.00$7,600.00
99Geotextile type HR (645.0120)SY320$2.08$4.83$3.90$2.37
100Geotextile type R (645.0130)SY53$1.24$15.00$6.10$4.88
101Marking line epoxy 4-inch (646.1020)LF1,453$1.00$1.00$1.10$1.00
102Marking line epoxy 6-inch (646.2020)LF397$1.50$1.50$1.70$1.50
103Marking line grooved black epoxy 6-inch (646.2025)LF3,759$1.32$1.32$1.50$1.32
104Marking line grooved wet ref epoxy 6-inch (646.2040)LF29,825$1.37$1.37$1.60$1.37
105Marking line grooved permanent tape 6-inch (646.2050)LF3,759$8.00$8.00$9.10$8.00
106Marking line grooved permanent tape 10-inch (646.4050)LF8,321$10.25$10.25$11.50$10.25
107Marking arrow epoxy (646.5020)EACH20$230.00$230.00$260.00$230.00
108Marking word epoxy (646.5120)EACH8$250.00$250.00$280.00$250.00
109Marking stop line epoxy 18-inch (646.6120)LF63$13.00$13.00$14.75$13.00
110Marking yield line epoxy 18-inch (646.6220)EACH40$45.00$45.00$51.00$45.00
111Marking diagonal epoxy 12-inch (646.7120)LF263$10.00$10.00$11.25$10.00
112Marking chevron epoxy 12-inch (646.7320)LF630$10.00$10.00$11.25$10.00
113Marking curb epoxy (646.8120)LF258$7.50$7.50$8.50$7.50
114Marking island nose epoxy (646.8220)EACH8$300.00$300.00$340.00$300.00
115Marking removal line 4-inch (646.9000)LF8,705$0.45$0.45$0.50$0.45
116Construction staking storm sewer (650.4000)EACH24$200.00$200.00$230.00$200.00
117Construction staking subgrade (650.4500)LF8,910$0.02$0.02$0.02$0.02
118Construction staking base (650.5000)LF8,910$0.30$0.30$0.35$0.30
119Construction staking curb gutter and curb & gutter (650.5500)LF2,711$0.50$0.50$0.55$0.50
120Construction staking pipe culverts (650.6000)EACH4$200.00$200.00$230.00$200.00
121Construction staking electrical installations (project) 01. 1204-05- 77 (650.8501)EACH1$300.00$300.00$340.00$300.00
122Construction staking sidewalk (project) 01. 1204-05-77 (650.9500)EACH1$1,000.00$1,000.00$1,100.00$1,000.00
123Construction staking supplemental control (project) 01. 1204-05-77 (650.9911)EACH1$100.00$100.00$110.00$100.00
124Construction staking slope stakes (650.9920)LF6,085$0.50$0.50$0.55$0.50
125Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF3,460$12.00$12.00$13.50$12.00
126Conduit rigid nonmetallic schedule 40 3-inch (652.0235)LF60$16.00$16.00$18.00$16.00
127Conduit rigid nonmetallic schedule 80 2-inch (652.0325)LF430$14.00$14.00$15.75$14.00
128Conduit special 2-inch (652.0605)LF355$30.00$30.00$34.00$30.00
129Pull boxes non-conductive 24X42- inch (653.0164)EACH13$2,100.00$2,100.00$2,400.00$2,100.00
130Concrete bases type 5 (654.0105)EACH21$1,250.00$1,250.00$1,400.00$1,250.00
131Concrete control cabinet bases type L30 (654.0230)EACH1$2,000.00$2,000.00$2,300.00$2,000.00
132Electrical wire lighting 12 AWG (655.0610)LF6,464$1.25$1.25$1.40$1.25
133Electrical wire lighting 6 AWG (655.0625)LF22,880$1.90$1.90$2.20$1.90
134Electrical service meter breaker pedestal (location) 01. CB100 (656.0201)EACH1$2,500.00$2,500.00$2,800.00$2,500.00
135Transformer bases breakaway 11 1/2-inch bolt circle (657.0255)EACH21$650.00$650.00$740.00$650.00
136Poles type 5-aluminum (657.0322)EACH21$2,159.00$2,159.00$2,400.00$2,159.00
137Luminaire arms truss type 4 1/2- inch clamp 12-FT (657.0710)EACH38$675.00$675.00$760.00$675.00
138Luminaires utility LED B (659.1120)EACH38$325.00$325.00$370.00$325.00
139Lighting control cabinets 120/240 30-inch (659.2130)EACH1$8,500.00$8,500.00$9,600.00$8,500.00
140Sawing asphalt (690.0150)LF9,497$1.10$1.09$1.20$1.09
141Incentive iri ride (740.0440)DOL1,290$1.00$1.00$1.00$1.00
142On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS2,000$5.00$5.00$5.00$5.00
143On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS1,320$5.00$5.00$5.00$5.00
144Special 01. research and locate existing land parcel monuments (SPV.0060)EACH1$200.00$200.00$230.00$200.00
145Special 02. verify and replace existing land parcel monuments (SPV.0060)EACH1$200.00$200.00$230.00$200.00
146Special 01. foundation drilling 20- inch diameter (SPV.0090)LF105$100.00$100.00$110.00$100.00
WisDOT contract 20251209002: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of December 9, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way