WisDOT contract 20251209007 bid tabulation
Mazomanie - Sun Prairie; Division Street to River Road (STH 019, Dane County Mazomaine - Sun Prairie). Let by Wisconsin DOT on December 9, 2025, Dane. 5 bids received; low bid $7,074,843 by Mashuda Contractors, Inc..
- Owner
- Wisconsin DOT
- Letting
- 09 DEC 2025
- Pay items
- 230
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Mashuda Contractors, Inc. | $7,074,843 | Low |
| 2 | Payne and Dolan, Inc | $7,080,692 | 0.0% |
| 3 | James Peterson Sons, Inc. | $7,415,821 | +5.0% |
| 4 | Integrity Grading and Excavating, Inc. | $7,557,702 | +7.0% |
| 5 | Hoffman Construction Company | $7,749,378 | +10% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Mashuda Contractors, Inc. | 2. Payne and Dolan, Inc | 3. James Peterson Sons, Inc. | 4. Integrity Grading and Excavating, Inc. | 5. Hoffman Construction Company |
|---|---|---|---|---|---|---|---|---|
| 1 | Grubbing (201.0210) | SY | 2,156 | $0.01 | $3.25 | $6.28 | $3.25 | $3.25 |
| 2 | Removing small pipe culverts (203.0100) | EACH | 11 | $1,000.00 | $1,000.00 | $1,200.00 | $252.89 | $850.00 |
| 3 | Removing asphaltic surface (204.0110) | SY | 121 | $4.00 | $4.00 | $20.00 | $5.41 | $32.00 |
| 4 | Removing asphaltic surface butt joints (204.0115) | SY | 651 | $4.60 | $40.00 | $12.00 | $1.96 | $12.00 |
| 5 | Removing asphaltic surface milling (204.0120) | SY | 62,616 | $1.23 | $2.25 | $2.50 | $0.89 | $2.50 |
| 6 | Removing curb & gutter (204.0150) | LF | 3,210 | $5.40 | $5.31 | $3.00 | $5.04 | $8.54 |
| 7 | Removing concrete sidewalk (204.0155) | SY | 265 | $5.94 | $5.94 | $25.00 | $5.88 | $10.00 |
| 8 | Removing concrete bases (204.0195) | EACH | 17 | $500.00 | $500.00 | $500.00 | $280.99 | $300.00 |
| 9 | Removing manholes (204.0210) | EACH | 1 | $700.00 | $700.00 | $500.00 | $1,293.05 | $400.00 |
| 10 | Removing inlets (204.0220) | EACH | 10 | $630.00 | $626.40 | $350.00 | $1,290.85 | $1,040.00 |
| 11 | Removing storm sewer (size) 01. 12-inch (204.0245) | LF | 305 | $8.75 | $8.75 | $20.00 | $43.81 | $12.00 |
| 12 | Excavation common (205.0100) | CY | 36,451 | $11.05 | $11.05 | $13.59 | $13.95 | $20.00 |
| 13 | Prepare foundation for asphaltic paving (project) 01. 5290-02-71 (211.0101) | EACH | 1 | $100.00 | $6,524.02 | $33,000 | $500.00 | $100.00 |
| 14 | Finishing roadway (project) 01. 5290-02-71 (213.0100) | EACH | 1 | $1,250.00 | $100.00 | $5,000.00 | $500.00 | $500.00 |
| 15 | Base aggregate dense 3/4-inch (305.0110) | TON | 1,810 | $19.66 | $19.66 | $34.38 | $43.24 | $33.31 |
| 16 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 37,020 | $15.58 | $15.58 | $14.28 | $18.75 | $19.22 |
| 17 | Shaping shoulders (305.0500) | STA | 261 | $35.00 | $0.01 | $45.00 | $148.22 | $36.00 |
| 18 | Select crushed material (312.0110) | TON | 26,449 | $15.46 | $15.46 | $14.10 | $16.15 | $18.00 |
| 19 | Tack coat (455.0605) | GAL | 12,636 | $2.75 | $0.01 | $2.75 | $2.75 | $2.75 |
| 20 | HMA percent within limits (PWL) test strip volumetrics (460.0105.S) | EACH | 3 | $15,000 | $1,500.00 | $15,000 | $5,000.00 | $15,000 |
| 21 | HMA percent within limits (PWL) test strip density (460.0110.S) | EACH | 3 | $15,000 | $1,500.00 | $15,000 | $5,000.00 | $15,000 |
| 22 | Incentive density HMA pavement (460.2000) | DOL | 15,540 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 23 | HMA pavement 4 MT 58-28 S (460.6224) | TON | 14,946 | $75.85 | $80.00 | $75.85 | $75.85 | $75.85 |
| 24 | HMA pavement 4 MT 58-28 H (460.6424) | TON | 9,760 | $85.00 | $85.00 | $85.00 | $85.00 | $85.00 |
| 25 | Asphaltic surface (465.0105) | TON | 896 | $102.00 | $90.00 | $102.00 | $102.00 | $102.00 |
| 26 | Asphaltic surface temporary (465.0125) | TON | 882 | $87.85 | $95.00 | $87.85 | $87.85 | $87.85 |
| 27 | Asphaltic flumes (465.0315) | SY | 36 | $25.00 | $65.00 | $25.00 | $25.00 | $25.00 |
| 28 | Asphaltic rumble strips, shoulder (465.0520) | LF | 25,862 | $0.25 | $0.47 | $0.47 | $0.25 | $0.25 |
| 29 | Asphaltic rumble strips, centerline (465.0560) | LF | 10,406 | $0.44 | $0.66 | $1.02 | $0.44 | $0.44 |
| 30 | Resin binder high friction surface treatment (490.0100.S) | SY | 7,240 | $22.55 | $22.55 | $22.55 | $22.55 | $22.55 |
| 31 | Adhesive anchors no. 4 bar (502.4204) | EACH | 16 | $32.00 | $32.00 | $34.00 | $34.00 | $32.00 |
| 32 | Concrete masonry culverts (504.0100) | CY | 1 | $4,650.00 | $4,650.00 | $4,500.00 | $4,500.00 | $4,650.00 |
| 33 | Bar steel reinforcement HS structures (505.0400) | LB | 20 | $20.00 | $20.00 | $12.80 | $12.80 | $20.00 |
| 34 | Concrete surface repair (509.1500) | SF | 20 | $52.00 | $52.00 | $425.00 | $425.00 | $52.00 |
| 35 | Negative pressure containment and collection of waste materials (structure) 01. B-13-188 (517.4501.S) | EACH | 1 | $24,750 | $25,000 | $24,750 | $24,750 | $24,750 |
| 36 | Portable decontamination facility (517.6001.S) | EACH | 1 | $2,000.00 | $10,000 | $2,000.00 | $2,000.00 | $2,000.00 |
| 37 | Culvert pipe reinforced concrete class III 30-inch (522.0130) | LF | 94 | $182.75 | $182.75 | $272.46 | $248.12 | $250.00 |
| 38 | Culvert pipe reinforced concrete class III 36-inch (522.0136) | LF | 95 | $212.25 | $212.25 | $325.50 | $272.48 | $275.00 |
| 39 | Culvert pipe reinforced concrete class III 42-inch (522.0142) | LF | 99 | $264.75 | $264.75 | $400.74 | $298.34 | $325.00 |
| 40 | Culvert pipe reinforced concrete class IV 24-inch (522.0424) | LF | 100 | $99.75 | $99.75 | $201.39 | $127.49 | $190.00 |
| 41 | Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012) | EACH | 1 | $868.00 | $868.00 | $686.00 | $1,495.23 | $1,500.00 |
| 42 | Apron endwalls for culvert pipe reinforced concrete 15-inch (522.1015) | EACH | 1 | $914.00 | $914.00 | $1,237.12 | $1,541.39 | $1,900.00 |
| 43 | Apron endwalls for culvert pipe reinforced concrete 18-inch (522.1018) | EACH | 1 | $983.00 | $983.00 | $1,358.45 | $1,610.44 | $1,700.00 |
| 44 | Apron endwalls for culvert pipe reinforced concrete 21-inch (522.1021) | EACH | 2 | $1,043.00 | $1,043.00 | $1,421.49 | $1,670.62 | $1,750.00 |
| 45 | Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024) | EACH | 2 | $1,139.00 | $1,139.00 | $1,548.81 | $1,739.66 | $1,800.00 |
| 46 | Apron endwalls for culvert pipe reinforced concrete 27-inch (522.1027) | EACH | 1 | $1,250.00 | $1,250.00 | $1,665.07 | $1,850.63 | $2,000.00 |
| 47 | Apron endwalls for culvert pipe reinforced concrete 30-inch (522.1030) | EACH | 2 | $1,337.00 | $1,337.00 | $1,756.88 | $2,591.17 | $2,100.00 |
| 48 | Apron endwalls for culvert pipe reinforced concrete 36-inch (522.1036) | EACH | 2 | $1,878.00 | $1,878.00 | $2,349.66 | $3,098.82 | $2,700.00 |
| 49 | Apron endwalls for culvert pipe reinforced concrete 42-inch (522.1042) | EACH | 2 | $2,224.00 | $2,224.00 | $2,838.05 | $3,444.75 | $3,600.00 |
| 50 | Culvert pipe reinforced concrete horizontal elliptical class HE-III 53X83-inch (522.2353) | LF | 255 | $612.75 | $612.75 | $761.58 | $548.47 | $750.00 |
| 51 | Culvert pipe reinforced concrete horizontal elliptical class HE-IV 14X23-inch (522.2414) | LF | 22 | $146.75 | $146.75 | $213.57 | $219.99 | $210.00 |
| 52 | Culvert pipe reinforced concrete horizontal elliptical class HE-IV 19X30-inch (522.2419) | LF | 88 | $154.25 | $154.25 | $248.36 | $274.99 | $230.00 |
| 53 | Culvert pipe reinforced concrete horizontal elliptical class HE-IV 34X53-inch (522.2434) | LF | 70 | $280.75 | $280.75 | $410.32 | $380.88 | $405.00 |
| 54 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 14X23-inch (522.2614) | EACH | 2 | $1,015.00 | $1,015.00 | $1,392.48 | $2,278.45 | $1,700.00 |
| 55 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 19X30-inch (522.2619) | EACH | 2 | $1,208.00 | $1,208.00 | $1,621.52 | $3,715.64 | $1,900.00 |
| 56 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 34X53-inch (522.2634) | EACH | 2 | $2,219.00 | $2,219.00 | $2,833.40 | $4,694.02 | $3,600.00 |
| 57 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 53X83-inch (522.2653) | EACH | 6 | $3,815.00 | $3,815.00 | $5,825.52 | $4,858.07 | $5,400.00 |
| 58 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 5,605 | $24.50 | $24.50 | $24.50 | $24.50 | $24.50 |
| 59 | Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557) | LF | 3,382 | $23.75 | $23.75 | $23.75 | $23.75 | $23.75 |
| 60 | Concrete sidewalk 4-inch (602.0405) | SF | 28,652 | $4.75 | $4.75 | $4.75 | $4.75 | $4.75 |
| 61 | Concrete sidewalk 5-inch (602.0410) | SF | 1,885 | $10.50 | $10.50 | $10.50 | $10.50 | $10.50 |
| 62 | Curb ramp detectable warning field yellow (602.0505) | SF | 70 | $40.00 | $40.00 | $70.00 | $40.00 | $40.00 |
| 63 | Riprap light (606.0100) | CY | 43 | $100.00 | $100.00 | $100.00 | $133.59 | $160.00 |
| 64 | Riprap medium (606.0200) | CY | 63 | $80.00 | $80.00 | $100.00 | $133.59 | $160.00 |
| 65 | Riprap heavy (606.0300) | CY | 14 | $105.00 | $105.00 | $200.00 | $133.59 | $180.00 |
| 66 | Storm sewer pipe reinforced concrete class IV 12-inch (608.0412) | LF | 334 | $110.75 | $110.75 | $118.40 | $126.50 | $78.00 |
| 67 | Storm sewer pipe reinforced concrete class IV 15-inch (608.0415) | LF | 520 | $88.50 | $88.50 | $129.02 | $129.27 | $80.00 |
| 68 | Storm sewer pipe reinforced concrete class IV 18-inch (608.0418) | LF | 51 | $153.50 | $153.50 | $125.68 | $134.53 | $84.00 |
| 69 | Storm sewer pipe reinforced concrete class IV 21-inch (608.0421) | LF | 261 | $126.75 | $126.75 | $140.59 | $140.77 | $94.00 |
| 70 | Storm sewer pipe reinforced concrete class IV 24-inch (608.0424) | LF | 74 | $171.00 | $171.00 | $153.26 | $157.93 | $110.00 |
| 71 | Storm sewer pipe reinforced concrete class IV 27-inch (608.0427) | LF | 47 | $203.75 | $203.75 | $174.91 | $175.23 | $152.00 |
| 72 | Manhole covers type J (611.0530) | EACH | 2 | $790.00 | $790.00 | $1,382.72 | $735.58 | $800.00 |
| 73 | Inlet covers type DW (611.0613) | EACH | 2 | $1,065.00 | $1,065.00 | $1,825.12 | $1,079.14 | $1,200.00 |
| 74 | Inlet covers type H (611.0624) | EACH | 16 | $1,050.00 | $1,050.00 | $1,711.72 | $991.09 | $1,100.00 |
| 75 | Inlet covers type H-S (611.0639) | EACH | 12 | $1,050.00 | $1,050.00 | $1,711.72 | $991.09 | $1,100.00 |
| 76 | Catch basins 4-FT diameter (611.1004) | EACH | 1 | $3,723.00 | $3,723.00 | $2,675.71 | $4,019.99 | $3,500.00 |
| 77 | Catch basins 6-FT diameter (611.1006) | EACH | 2 | $6,123.00 | $6,123.00 | $5,487.51 | $6,267.73 | $6,400.00 |
| 78 | Catch basins 2X3-FT (611.1230) | EACH | 2 | $2,537.00 | $2,537.00 | $1,655.20 | $3,517.19 | $2,400.00 |
| 79 | Manholes 4-FT diameter (611.2004) | EACH | 1 | $2,915.00 | $2,915.00 | $2,440.42 | $3,736.19 | $3,200.00 |
| 80 | Manholes 6-FT diameter (611.2006) | EACH | 1 | $5,197.00 | $5,197.00 | $4,987.17 | $5,738.31 | $7,600.00 |
| 81 | Inlets 4-FT diameter (611.3004) | EACH | 14 | $3,049.00 | $3,049.00 | $2,577.76 | $3,756.46 | $3,200.00 |
| 82 | Inlets 2X3-FT (611.3230) | EACH | 11 | $2,342.00 | $2,342.00 | $1,729.47 | $3,425.06 | $2,200.00 |
| 83 | Adjusting manhole covers (611.8110) | EACH | 1 | $1,750.00 | $1,750.00 | $818.52 | $297.45 | $1,100.00 |
| 84 | Pipe underdrain 6-inch (612.0106) | LF | 326 | $28.00 | $28.00 | $12.33 | $13.75 | $24.00 |
| 85 | Maintenance and repair of haul roads (project) 01. 5290-02-71 (618.0100) | EACH | 1 | $1.00 | $100.00 | $1,000.00 | $500.00 | $500.00 |
| 86 | Mobilization (619.1000) | EACH | 1 | $500,000 | $470,000 | $401,151 | $549,230 | $327,480 |
| 87 | Concrete median blunt nose (620.0200) | SF | 182 | $27.00 | $27.00 | $27.00 | $27.00 | $27.00 |
| 88 | Concrete median sloped nose (620.0300) | SF | 573 | $16.00 | $16.00 | $16.00 | $16.00 | $16.00 |
| 89 | Water (624.0100) | MGAL | 528 | $35.00 | $35.00 | $60.00 | $50.50 | $100.00 |
| 90 | Topsoil (625.0100) | SY | 22,061 | $3.00 | $3.00 | $2.75 | $4.70 | $4.50 |
| 91 | Mulching (627.0200) | SY | 172 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 92 | Silt fence (628.1504) | LF | 10,656 | $1.95 | $1.95 | $1.95 | $1.95 | $1.95 |
| 93 | Silt fence maintenance (628.1520) | LF | 10,656 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 94 | Erosion mat urban class I type A (628.2006) | SY | 394 | $1.60 | $1.60 | $1.60 | $1.60 | $1.60 |
| 95 | Erosion mat urban class I type B (628.2008) | SY | 21,847 | $1.60 | $1.60 | $1.60 | $1.60 | $1.60 |
| 96 | Erosion mat class II type B (628.2023) | SY | 2,180 | $1.70 | $1.70 | $1.70 | $1.70 | $1.70 |
| 97 | Turbidity barriers (628.6005) | SY | 38 | $60.00 | $60.00 | $60.00 | $60.00 | $60.00 |
| 98 | Inlet protection type A (628.7005) | EACH | 29 | $75.00 | $75.00 | $75.00 | $75.00 | $75.00 |
| 99 | Inlet protection type C (628.7015) | EACH | 16 | $75.00 | $75.00 | $75.00 | $75.00 | $75.00 |
| 100 | Inlet protection type D (628.7020) | EACH | 13 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 |
| 101 | Temporary ditch checks (628.7504) | LF | 240 | $8.50 | $8.50 | $8.50 | $8.50 | $8.50 |
| 102 | Culvert pipe checks (628.7555) | EACH | 11 | $18.00 | $18.00 | $18.00 | $18.00 | $18.00 |
| 103 | Rock bags (628.7570) | EACH | 187 | $18.00 | $18.00 | $18.00 | $18.00 | $18.00 |
| 104 | Fertilizer type B (629.0210) | CWT | 1,390 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 105 | Seeding mixture no. 30 (630.0130) | LB | 993 | $7.95 | $7.95 | $7.95 | $7.95 | $7.95 |
| 106 | Seed water (630.0500) | MGAL | 4,953 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 107 | Shrubs (species, root, size) 01. prunus americana, 9-inch diameter 6-inch depth, 24-inch (632.0201) | EACH | 25 | $75.00 | $75.00 | $75.00 | $75.00 | $75.00 |
| 108 | Shrubs (species, root, size) 02. viburnum triobum, 9-inch diameter 6-inch depth, 24-inch (632.0201) | EACH | 25 | $75.00 | $75.00 | $75.00 | $75.00 | $75.00 |
| 109 | Markers culvert end (633.5200) | EACH | 21 | $70.00 | $70.00 | $70.00 | $70.00 | $70.00 |
| 110 | Posts wood 4X6-inch X 12-FT (634.0612) | EACH | 2 | $90.00 | $90.00 | $90.00 | $90.00 | $90.00 |
| 111 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 7 | $90.00 | $90.00 | $90.00 | $90.00 | $90.00 |
| 112 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 50 | $95.00 | $95.00 | $95.00 | $95.00 | $95.00 |
| 113 | Signs type II reflective H (637.2210) | SF | 512.50 | $21.00 | $21.00 | $21.00 | $21.00 | $21.00 |
| 114 | Signs type II reflective F (637.2230) | SF | 82.25 | $21.00 | $21.00 | $21.00 | $21.00 | $21.00 |
| 115 | Moving signs type II (638.2102) | EACH | 18 | $150.00 | $150.00 | $150.00 | $150.00 | $150.00 |
| 116 | Removing signs type II (638.2602) | EACH | 70 | $35.00 | $35.00 | $35.00 | $35.00 | $35.00 |
| 117 | Removing small sign supports (638.3000) | EACH | 45 | $35.00 | $35.00 | $35.00 | $35.00 | $35.00 |
| 118 | Field office type B (642.5001) | EACH | 1 | $17,500 | $1,500.00 | $15,000 | $15,750 | $10,000 |
| 119 | Traffic control drums (643.0300) | DAY | 28,125 | $0.25 | $0.25 | $0.35 | $0.35 | $0.25 |
| 120 | Traffic control barricades type III (643.0420) | DAY | 4,665 | $0.75 | $0.75 | $1.28 | $1.25 | $0.75 |
| 121 | Traffic control flexible tubular marker posts (643.0500) | EACH | 299 | $24.00 | $24.00 | $26.24 | $26.24 | $24.00 |
| 122 | Traffic control flexible tubular marker bases (643.0600) | EACH | 299 | $12.00 | $12.00 | $10.80 | $10.80 | $12.00 |
| 123 | Traffic control warning lights type A (643.0705) | DAY | 9,320 | $0.15 | $0.15 | $0.23 | $0.23 | $0.15 |
| 124 | Traffic control warning lights type C (643.0715) | DAY | 4,478 | $0.15 | $0.15 | $0.23 | $0.23 | $0.15 |
| 125 | Traffic control connected arrow boards (643.0810) | DAY | 46 | $20.00 | $20.00 | $26.25 | $26.25 | $20.00 |
| 126 | Traffic control signs (643.0900) | DAY | 13,050 | $0.35 | $0.35 | $0.80 | $0.80 | $0.35 |
| 127 | Traffic control covering signs type II (643.0920) | EACH | 7 | $50.00 | $50.00 | $83.89 | $83.89 | $50.00 |
| 128 | Traffic control signs PCMS (643.1050) | DAY | 135 | $25.00 | $25.00 | $79.85 | $79.85 | $25.00 |
| 129 | Temporary marking line epoxy 6- inch (643.3170) | LF | 110,866 | $0.88 | $0.89 | $0.60 | $0.60 | $0.86 |
| 130 | Temporary marking line epoxy 10- inch (643.3270) | LF | 4,023 | $1.50 | $1.52 | $1.20 | $1.20 | $1.50 |
| 131 | Temporary marking crosswalk epoxy 6-inch (643.3320) | LF | 837 | $0.90 | $0.91 | $17.00 | $17.00 | $0.85 |
| 132 | Temporary marking stop line epoxy 18-inch (643.3820) | LF | 633 | $9.00 | $9.09 | $16.00 | $16.00 | $9.00 |
| 133 | Traffic control (643.5000) | EACH | 1 | $10,000 | $10,000 | $16,277 | $16,277 | $10,000 |
| 134 | Temporary pedestrian surface matting (644.1440) | SF | 1,343 | $6.99 | $6.99 | $14.93 | $14.93 | $6.99 |
| 135 | Temporary pedestrian curb ramp (644.1601) | DAY | 44 | $25.00 | $25.00 | $23.02 | $23.02 | $25.00 |
| 136 | Temporary pedestrian detectable warning field (644.1605) | SF | 40 | $10.00 | $10.00 | $25.74 | $25.74 | $10.00 |
| 137 | Temporary pedestrian barricade (644.1810) | LF | 1,033 | $5.00 | $5.00 | $7.11 | $7.11 | $5.00 |
| 138 | Temporary audible message devices (644.1900.S) | DAY | 700 | $2.22 | $2.22 | $1.67 | $1.67 | $2.22 |
| 139 | Geotextile type HR (645.0120) | SY | 740 | $4.00 | $4.00 | $2.50 | $2.05 | $5.00 |
| 140 | Geotextile type R (645.0130) | SY | 665 | $5.00 | $5.00 | $2.00 | $1.55 | $5.00 |
| 141 | Marking line grooved black epoxy 6-inch (646.2025) | LF | 7,055 | $1.35 | $1.36 | $1.10 | $1.10 | $1.35 |
| 142 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 68,449 | $1.30 | $1.31 | $1.55 | $1.55 | $1.30 |
| 143 | Marking line grooved wet ref epoxy 10-inch (646.4040) | LF | 4,911 | $3.00 | $3.03 | $3.00 | $3.00 | $3.00 |
| 144 | Marking arrow epoxy (646.5020) | EACH | 52 | $225.00 | $227.27 | $340.00 | $340.00 | $225.00 |
| 145 | Marking word epoxy (646.5120) | EACH | 20 | $245.00 | $247.47 | $440.00 | $440.00 | $245.00 |
| 146 | Marking symbol epoxy (646.5220) | EACH | 3 | $300.00 | $303.03 | $330.00 | $330.00 | $300.00 |
| 147 | Marking stop line epoxy 18-inch (646.6120) | LF | 382 | $12.00 | $12.12 | $20.00 | $20.00 | $12.00 |
| 148 | Marking diagonal epoxy 12-inch (646.7120) | LF | 373 | $9.50 | $9.60 | $19.00 | $19.00 | $9.50 |
| 149 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 445 | $10.50 | $10.61 | $18.00 | $18.00 | $10.50 |
| 150 | Marking curb epoxy (646.8120) | LF | 290 | $7.50 | $7.58 | $10.00 | $10.00 | $7.50 |
| 151 | Marking island nose epoxy (646.8220) | EACH | 7 | $275.00 | $277.78 | $330.00 | $330.00 | $275.00 |
| 152 | Marking removal line 4-inch (646.9000) | LF | 10,468 | $0.40 | $0.40 | $0.35 | $0.35 | $0.40 |
| 153 | Marking removal line 8-inch (646.9100) | LF | 492 | $0.45 | $0.45 | $0.75 | $0.75 | $0.45 |
| 154 | Marking removal line 10-inch (646.9102) | LF | 733 | $1.00 | $1.00 | $0.77 | $0.77 | $1.00 |
| 155 | Marking removal line wide (646.9200) | LF | 590 | $1.00 | $1.00 | $1.20 | $1.20 | $1.00 |
| 156 | Marking removal special marking (646.9300) | EACH | 12 | $50.00 | $50.00 | $85.00 | $85.00 | $50.00 |
| 157 | Locating no-passing zones (648.0100) | MI | 0.02 | $50,000 | $50,505 | $100,000 | $100,000 | $50,000 |
| 158 | Construction staking storm sewer (650.4000) | EACH | 33 | $200.00 | $200.00 | $200.00 | $200.00 | $200.00 |
| 159 | Construction staking subgrade (650.4500) | LF | 20,957 | $0.01 | $0.01 | $0.01 | $0.01 | $0.50 |
| 160 | Construction staking base (650.5000) | LF | 20,957 | $0.84 | $0.84 | $0.84 | $0.84 | $0.84 |
| 161 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 9,019 | $0.78 | $0.78 | $0.78 | $0.78 | $0.78 |
| 162 | Construction staking pipe culverts (650.6000) | EACH | 10 | $200.00 | $200.00 | $200.00 | $200.00 | $200.00 |
| 163 | Construction staking resurfacing reference (650.8000) | LF | 13,825 | $0.15 | $0.15 | $0.15 | $0.15 | $0.15 |
| 164 | Construction staking electrical installations (project) 01. 5290-02- 71 (650.8501) | EACH | 1 | $1,800.00 | $1,800.00 | $1,800.00 | $1,800.00 | $1,800.00 |
| 165 | Construction staking curb ramps (650.9000) | EACH | 5 | $200.00 | $200.00 | $200.00 | $200.00 | $200.00 |
| 166 | Construction staking sidewalk (project) 01. 5290-02-71 (650.9500) | EACH | 1 | $900.00 | $900.00 | $900.00 | $900.00 | $900.00 |
| 167 | Construction staking supplemental control (project) 01. 5290-02-71 (650.9911) | EACH | 1 | $1,200.00 | $1,200.00 | $1,200.00 | $1,200.00 | $1,200.00 |
| 168 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 8,882 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 |
| 169 | Conduit rigid nonmetallic schedule 40 3-inch (652.0235) | LF | 2,921 | $12.00 | $12.00 | $12.00 | $12.00 | $12.00 |
| 170 | Conduit special 3-inch (652.0615) | LF | 318 | $60.00 | $60.00 | $60.00 | $60.00 | $60.00 |
| 171 | Conduit loop detector (652.0800) | LF | 4,520 | $8.00 | $8.00 | $8.00 | $8.00 | $8.00 |
| 172 | Pull boxes non-conductive 24X36- inch (653.0154) | EACH | 37 | $1,700.00 | $1,700.00 | $1,700.00 | $1,700.00 | $1,700.00 |
| 173 | Pull boxes non-conductive 24X42- inch (653.0164) | EACH | 27 | $1,800.00 | $1,800.00 | $1,800.00 | $1,800.00 | $1,800.00 |
| 174 | Removing pull boxes (653.0905) | EACH | 25 | $300.00 | $500.00 | $250.00 | $150.00 | $200.00 |
| 175 | Concrete bases type 1 (654.0101) | EACH | 11 | $950.00 | $950.00 | $950.00 | $950.00 | $950.00 |
| 176 | Concrete bases type 10 (654.0110) | EACH | 1 | $8,000.00 | $8,000.00 | $8,000.00 | $8,000.00 | $8,000.00 |
| 177 | Concrete bases type 13 (654.0113) | EACH | 1 | $9,500.00 | $9,500.00 | $9,500.00 | $9,500.00 | $9,500.00 |
| 178 | Concrete bases type 10-special (654.0120) | EACH | 6 | $9,500.00 | $9,500.00 | $9,500.00 | $9,500.00 | $9,500.00 |
| 179 | Concrete control cabinet bases type 9 special (654.0217) | EACH | 2 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 |
| 180 | Cable traffic signal 5-14 AWG (655.0230) | LF | 2,089 | $1.25 | $1.25 | $1.25 | $1.25 | $1.25 |
| 181 | Cable traffic signal 9-14 AWG (655.0250) | LF | 382 | $1.75 | $1.75 | $1.75 | $1.75 | $1.75 |
| 182 | Cable traffic signal 12-14 AWG (655.0260) | LF | 3,094 | $2.50 | $2.50 | $2.50 | $2.50 | $2.50 |
| 183 | Cable type UF 2-12 AWG grounded (655.0305) | LF | 1,430 | $1.50 | $1.50 | $1.50 | $1.50 | $1.50 |
| 184 | Electrical wire traffic signals 10 AWG (655.0515) | LF | 1,384 | $1.10 | $1.10 | $1.10 | $1.10 | $1.10 |
| 185 | Electrical wire lighting 12 AWG (655.0610) | LF | 1,056 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 186 | Loop detector lead in cable (655.0700) | LF | 5,688 | $1.25 | $1.25 | $1.25 | $1.25 | $1.25 |
| 187 | Loop detector wire (655.0800) | LF | 9,668 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 188 | Electrical service meter breaker pedestal (location) 01. STH 19 & division street, STH 19 & raemisch road (656.0201) | EACH | 2 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 |
| 189 | Pedestal bases (657.0100) | EACH | 11 | $260.00 | $260.00 | $260.00 | $260.00 | $260.00 |
| 190 | Poles type 9-special (657.0347) | EACH | 1 | $10,500 | $10,500 | $10,500 | $10,500 | $10,500 |
| 191 | Poles type 10 (657.0350) | EACH | 1 | $10,000 | $10,000 | $10,000 | $10,000 | $10,000 |
| 192 | Poles type 10-special (657.0352) | EACH | 5 | $14,500 | $14,500 | $14,500 | $14,500 | $14,500 |
| 193 | Poles type 13 (657.0360) | EACH | 1 | $18,000 | $18,000 | $18,000 | $18,000 | $18,000 |
| 194 | Traffic signal standards aluminum 15-FT (657.0425) | EACH | 8 | $750.00 | $750.00 | $750.00 | $750.00 | $750.00 |
| 195 | Traffic signal standards aluminum 10-FT (657.0430) | EACH | 3 | $625.00 | $625.00 | $625.00 | $625.00 | $625.00 |
| 196 | Monotube arms 30-FT (657.0530) | EACH | 1 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 |
| 197 | Monotube arms 35-FT-special (657.0536) | EACH | 3 | $4,500.00 | $4,500.00 | $4,500.00 | $4,500.00 | $4,500.00 |
| 198 | Monotube arms 40-FT-special (657.0541) | EACH | 1 | $4,750.00 | $4,750.00 | $4,750.00 | $4,750.00 | $4,750.00 |
| 199 | Monotube arms 45-FT-special (657.0546) | EACH | 2 | $4,875.00 | $4,875.00 | $4,875.00 | $4,875.00 | $4,875.00 |
| 200 | Monotube arms 55-FT (657.0555) | EACH | 1 | $15,500 | $15,500 | $15,500 | $15,500 | $15,500 |
| 201 | Luminaire arms steel 15-FT (657.0815) | EACH | 7 | $840.00 | $840.00 | $840.00 | $840.00 | $840.00 |
| 202 | Traffic signal face 3S 12-inch (658.0173) | EACH | 31 | $725.00 | $725.00 | $725.00 | $725.00 | $725.00 |
| 203 | Traffic signal face 4S 12-inch (658.0174) | EACH | 8 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 204 | Pedestrian signal face 16-inch (658.0416) | EACH | 6 | $500.00 | $500.00 | $500.00 | $500.00 | $500.00 |
| 205 | Pedestrian push buttons (658.0500) | EACH | 6 | $360.00 | $360.00 | $360.00 | $360.00 | $360.00 |
| 206 | Signal mounting hardware (location) 01. STH 19 and division street (658.5070) | EACH | 1 | $7,500.00 | $7,500.00 | $7,500.00 | $7,500.00 | $7,500.00 |
| 207 | Signal mounting hardware (location) 02. STH 19 and raemisch road (658.5070) | EACH | 1 | $6,500.00 | $6,500.00 | $6,500.00 | $6,500.00 | $6,500.00 |
| 208 | Luminaires utility LED C (659.1125) | EACH | 7 | $770.00 | $770.00 | $770.00 | $1,100.00 | $770.00 |
| 209 | Lamp, ballast, LED, switch disposal by contractor (659.5000.S) | EACH | 1 | $400.00 | $400.00 | $400.00 | $400.00 | $400.00 |
| 210 | Temporary traffic signals for intersections (location) 01. STH 19 and division street (661.0201) | EACH | 1 | $60,000 | $60,000 | $60,000 | $60,000 | $60,000 |
| 211 | Temporary traffic signals for intersections (location) 02. STH 19 and schumacher road/raemsich road (661.0201) | EACH | 1 | $60,000 | $60,000 | $60,000 | $60,000 | $60,000 |
| 212 | Install fiber optic cable outdoor plant 12-CT (678.0012) | LF | 2,900 | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 |
| 213 | Fiber optic termination (678.0400) | EACH | 2 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 214 | Sawing asphalt (690.0150) | LF | 6,770 | $1.10 | $1.11 | $1.10 | $1.10 | $1.10 |
| 215 | Sawing concrete (690.0250) | LF | 17 | $2.25 | $2.27 | $2.25 | $2.25 | $2.25 |
| 216 | Incentive iri ride (740.0440) | DOL | 16,720 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 217 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,400 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 218 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 3,200 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 219 | Special 01. utility line opening (ulo) (SPV.0060) | EACH | 3 | $1,000.00 | $1,000.00 | $800.00 | $1,137.28 | $1,500.00 |
| 220 | Special 02. removing traffic signals (STH 19 and division street) (SPV.0060) | EACH | 1 | $3,500.00 | $3,500.00 | $3,500.00 | $3,500.00 | $3,500.00 |
| 221 | Special 03. removing traffic signals (STH 19 and raemisch road) (SPV.0060) | EACH | 1 | $3,500.00 | $3,500.00 | $3,500.00 | $3,500.00 | $3,500.00 |
| 222 | Special 04. railing repainting recycle abrasive, B-13-188 (SPV.0060) | EACH | 1 | $41,250 | $20,000 | $41,250 | $41,250 | $41,250 |
| 223 | Special 05. salvage transformer bases breakaway 11 1/2-inch bolt circle (SPV.0060) | EACH | 7 | $50.00 | $50.00 | $50.00 | $50.00 | $50.00 |
| 224 | Special 06. retroreflective backplate 3S (SPV.0060) | EACH | 12 | $140.00 | $140.00 | $140.00 | $140.00 | $140.00 |
| 225 | Special 07. retroreflective backplate 4S (SPV.0060) | EACH | 8 | $180.00 | $180.00 | $180.00 | $180.00 | $180.00 |
| 226 | Special 08. landmark reference monuments special (SPV.0060) | EACH | 4 | $900.00 | $900.00 | $900.00 | $900.00 | $900.00 |
| 227 | Special 01. install state-supplied non-intrusive detection cable (SPV.0090) | LF | 1,699 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 228 | Special 02. joint and crack plunge milling and patching (SPV.0090) | LF | 395 | $17.02 | $30.00 | $50.00 | $17.02 | $50.00 |
| 229 | Special 03. concrete joint and crack cleaning (SPV.0090) | LF | 395 | $12.34 | $15.00 | $50.00 | $1.00 | $50.00 |
| 230 | Special 01. removing distressed pavement milling (SPV.0180) | SY | 6,262 | $4.42 | $6.00 | $6.00 | $1.96 | $6.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of December 9, 2025. Compiled by Mirage Metrics.