WisDOT contract 20260210034 bid tabulation

C Antigo, 10th Avenue; Western Avenue to Clermont Street (LOC STR, Langlade County C Antigo, 10th Avenue). Let by Wisconsin DOT on February 10, 2026, Langlade. 4 bids received; low bid $3,230,119 by Integrity Grading and Excavating, Inc..

Owner
Wisconsin DOT
Letting
10 FEB 2026
Pay items
171
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Integrity Grading and Excavating, Inc.$3,230,119Low
2A-1 Excavating LLC$3,636,363+13%
3S & N Incorporated$3,692,909+14%
4Relyco Plus, LLC$4,204,194+30%
WisDOT contract 20260210034: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Integrity Grading and Excavating, Inc.2. A-1 Excavating LLC3. S & N Incorporated4. Relyco Plus, LLC
1Grubbing (201.0220)ID75$40.00$20.00$30.00$20.00
2Removing concrete pavement (204.0100)SY590$3.83$12.00$9.50$10.00
3Removing asphaltic surface (204.0110)SY520$1.10$6.00$8.00$10.00
4Removing curb & gutter (204.0150)LF12,450$4.65$4.00$11.52$10.50
5Removing concrete sidewalk (204.0155)SY795$1.38$12.00$12.50$13.50
6Removing manholes (204.0210)EACH5$616.69$750.00$500.00$565.00
7Removing inlets (204.0220)EACH42$605.59$600.00$400.00$370.00
8Removing storm sewer (size) 01. 8- inch (204.0245)LF739$24.93$15.00$8.00$13.00
9Removing storm sewer (size) 02. 10-inch (204.0245)LF245$23.57$15.00$8.00$12.00
10Removing storm sewer (size) 03. 12-inch (204.0245)LF173$25.95$15.00$10.00$16.00
11Removing storm sewer (size) 04. 15-inch (204.0245)LF294$28.24$17.00$10.00$16.00
12Removing storm sewer (size) 05. 24-inch (204.0245)LF337$25.61$20.00$12.00$18.00
13Removing storm sewer (size) 06. 42-inch (204.0245)LF325$31.57$30.00$15.00$19.00
14Sealing pipes (204.0280)EACH2$1,178.56$1,000.00$500.00$1,015.00
15Excavation common (205.0100)CY3,963$19.12$25.00$22.87$23.09
16Finishing roadway (project) 01. 9835-06-70 (213.0100)EACH1$500.00$1,500.00$500.00$5,000.00
17Base aggregate dense 3/4-inch (305.0110)TON200$49.00$27.00$25.00$34.96
18Base aggregate dense 1 1/4-inch (305.0120)TON4,510$30.10$22.00$19.85$21.17
19Pulverize and relay (325.0100)SY24,620$1.17$3.00$1.65$0.45
20Subbase (350.0104)TON3,140$12.43$14.00$12.35$11.96
21Tack coat (455.0605)GAL3,910$2.00$2.20$2.60$2.00
22Incentive density HMA pavement (460.2000)DOL4,633$1.00$1.00$1.00$1.00
23HMA pavement 3 LT 58-28 S (460.5223)TON3,900$67.90$69.00$74.80$67.90
24HMA pavement 4 LT 58-34 S (460.5244)TON2,750$78.50$80.00$94.30$78.50
25Asphaltic surface driveways and field entrances (465.0120)TON165$121.00$141.00$120.00$121.00
26Concrete collars for pipe (520.8000)EACH12$1,528.54$2,000.00$800.00$995.00
27Apron endwalls for culvert pipe reinforced concrete 42-inch (522.1042)EACH1$5,657.84$3,910.00$3,522.00$3,645.00
28Concrete curb & gutter 18-inch type D (601.0407)LF200$36.00$37.00$36.00$36.00
29Concrete curb & gutter 30-inch type D (601.0411)LF12,515$19.51$25.50$18.45$18.45
30Concrete curb pedestrian (601.0600)LF65$75.00$78.00$75.00$75.00
31Concrete sidewalk 4-inch (602.0405)SF35$9.00$11.00$9.00$9.50
32Concrete sidewalk 6-inch (602.0415)SF7,700$7.50$8.50$7.50$8.00
33Curb ramp detectable warning field yellow (602.0505)SF392$30.00$32.00$30.00$30.00
34Curb ramp detectable warning field radial yellow (602.0605)SF31$55.00$58.00$55.00$55.00
35Concrete driveway 6-inch (602.0810)SY735$67.50$74.00$67.50$68.00
36Concrete driveway 8-inch (602.0820)SY120$74.25$80.25$74.25$74.25
37Riprap heavy (606.0300)CY18$212.53$120.00$110.00$250.00
38Storm sewer pipe reinforced concrete class III 24-inch (608.0324)LF130$117.21$275.00$179.24$260.00
39Storm sewer pipe reinforced concrete class III 60-inch (608.0360)LF305$430.16$679.00$685.00$797.00
40Storm sewer pipe reinforced concrete class IV 12-inch (608.0412)LF895$77.82$111.00$95.67$96.70
41Storm sewer pipe reinforced concrete class IV 15-inch (608.0415)LF710$71.86$113.00$101.62$113.90
42Storm sewer pipe reinforced concrete class IV 18-inch (608.0418)LF64$88.14$144.00$106.60$119.00
43Storm sewer pipe reinforced concrete class IV 36-inch (608.0436)LF16$246.39$282.00$261.36$322.20
44Storm sewer pipe reinforced concrete class IV 42-inch (608.0442)LF220$221.49$396.00$341.11$348.30
45Reconstructing manholes (611.0420)EACH15$1,728.52$2,500.00$2,822.00$1,758.00
46Reconstructing inlets (611.0430)EACH1$1,728.52$1,200.00$2,822.00$792.00
47Manhole covers type J (611.0530)EACH1$699.78$1,020.00$942.02$542.00
48Manhole covers type J-special (611.0535)EACH8$696.74$1,020.00$960.04$560.00
49Inlet covers type H (611.0624)EACH16$938.74$1,275.00$1,178.40$778.00
50Inlet covers type H-S (611.0639)EACH35$938.73$1,275.00$1,178.40$778.00
51Inlet covers type MS-A (611.0645)EACH2$743.32$850.00$973.82$574.00
52Catch basins 4-FT diameter (611.1004)EACH7$3,525.10$3,420.00$2,694.06$4,760.00
53Catch basins 5-FT diameter (611.1005)EACH1$4,089.50$5,210.00$3,825.42$6,225.00
54Catch basins 2X3-FT (611.1230)EACH33$3,284.58$2,890.00$2,078.66$3,178.00
55Manholes 4-FT diameter (611.2004)EACH4$3,332.58$3,710.00$3,068.80$4,968.00
56Manholes 5-FT diameter (611.2005)EACH1$3,704.45$5,150.00$4,714.42$6,405.00
57Manholes 6-FT diameter (611.2006)EACH2$6,971.55$8,180.00$7,648.14$7,818.00
58Manholes 8-FT diameter (611.2008)EACH1$21,335$30,600$22,341$33,383
59Manholes 9-FT diameter (611.2009)EACH1$24,930$45,850$32,563$47,055
60Inlets 4-FT diameter (611.3004)EACH2$3,303.56$3,350.00$2,518.77$4,868.00
61Inlets 2X3-FT (611.3230)EACH3$3,153.76$2,960.00$2,138.86$3,230.00
62Inlets median 1 grate (611.3901)EACH2$3,534.60$3,800.00$3,399.52$3,722.00
63Adjusting manhole covers (611.8110)EACH3$726.54$700.00$770.00$550.00
64Adjusting inlet covers (611.8115)EACH5$726.54$700.00$450.00$500.00
65Pipe grates (size) 01. 42-inch (611.9850.S)EACH1$2,271.90$4,550.00$4,101.86$4,476.00
66Mobilization (619.1000)EACH1$394,612$279,214$410,077$559,000
67Water (624.0100)MGAL265$47.19$35.00$48.00$0.01
68Topsoil (625.0100)SY7,710$3.97$8.00$7.50$13.53
69Silt fence (628.1504)LF100$5.00$3.20$5.00$5.00
70Silt fence maintenance (628.1520)LF300$0.01$0.01$0.01$0.01
71Mobilizations erosion control (628.1905)EACH6$250.00$650.00$250.00$250.00
72Mobilizations emergency erosion control (628.1910)EACH5$200.00$250.00$200.00$200.00
73Inlet protection type A (628.7005)EACH53$25.00$116.00$25.00$25.00
74Inlet protection type B (628.7010)EACH3$64.00$83.00$64.00$64.00
75Inlet protection type C (628.7015)EACH97$66.00$100.00$66.00$66.00
76Inlet protection type D (628.7020)EACH7$135.00$150.00$135.00$135.00
77Tracking pads (628.7560)EACH2$1,000.00$1.00$500.00$0.01
78Seed water (630.0500)MGAL175$5.00$54.00$5.00$5.00
79Posts wood 4X6-inch X 12-FT (634.0612)EACH2$78.00$135.00$78.00$78.00
80Posts wood 4X6-inch X 14-FT (634.0614)EACH22$82.00$95.00$82.00$82.00
81Posts wood 4X6-inch X 16-FT (634.0616)EACH4$86.00$140.00$86.00$86.00
82Signs type II reflective H (637.2210)SF11$22.15$32.00$22.15$22.15
83Signs type II reflective F (637.2230)SF42$24.50$34.00$24.50$24.50
84Moving signs type II (638.2102)EACH26$75.00$185.00$75.00$75.00
85Removing small sign supports (638.3000)EACH22$50.00$30.00$50.00$50.00
86Field office type C (642.5201)EACH1$17,500$11,998$10,000$12,500
87Traffic control barricades type III (643.0420)DAY5,791$0.45$1.00$0.65$0.65
88Traffic control warning lights type A (643.0705)DAY11,572$0.10$0.25$0.10$0.10
89Traffic control signs (643.0900)DAY7,914$0.32$1.00$0.80$0.80
90Traffic control (643.5000)EACH1$9,000.00$12,491$2,500.00$2,491.00
91Temporary pedestrian surface matting (644.1440)SF1,035$2.75$5.00$4.00$4.00
92Temporary pedestrian curb ramp (644.1601)DAY14$27.00$14.00$4.00$4.00
93Temporary pedestrian detectable warning field (644.1605)SF40$3.50$14.00$4.00$4.00
94Temporary pedestrian barricade (644.1810)LF115$7.50$9.00$4.00$4.00
95Geotextile type HR (645.0120)SY36$11.18$6.00$3.25$10.00
96Marking line epoxy 4-inch (646.1020)LF11,835$0.57$1.10$1.05$0.80
97Marking crosswalk epoxy transverse line 6-inch (646.7420)LF315$25.00$11.00$8.25$19.00
98Construction staking storm sewer (650.4000)EACH74$45.14$56.00$152.00$45.14
99Construction staking subgrade (650.4500)LF598$0.01$1.00$0.77$0.01
100Construction staking base (650.5000)LF598$1.32$2.00$0.77$1.32
101Construction staking curb gutter and curb & gutter (650.5500)LF12,715$0.75$0.80$0.59$0.75
102Construction staking resurfacing reference (650.8000)LF6,252$0.27$0.50$0.13$0.27
103Construction staking curb ramps (650.9000)EACH34$150.00$160.00$155.00$150.00
104Construction staking sidewalk (project) 01. 9835-06-70 (650.9500)EACH1$1,160.25$1,661.00$800.00$1,160.25
105Construction staking supplemental control (project) 01. 9835-06-70 (650.9911)EACH1$460.39$961.00$800.00$460.39
106Construction staking slope stakes (650.9920)LF6,850$1.00$1.10$0.77$1.00
107Sawing asphalt (690.0150)LF3,140$1.49$3.00$2.00$1.50
108Sawing concrete (690.0250)LF505$2.74$6.00$2.75$2.25
109Incentive iri ride (740.0440)DOL4,360$1.00$1.00$1.00$1.00
110On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS2,000$5.00$5.00$5.00$5.00
111On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS1,260$5.00$5.00$5.00$5.00
112Special 01. adjusting sanitary manhole covers (SPV.0060)EACH18$726.54$1,000.00$1,167.50$1,060.00
113Special 02. inlet covers type H-D (SPV.0060)EACH1$1,000.50$1,340.00$1,183.70$784.00
114Special 03. adjusting water valve boxes (SPV.0060)EACH28$778.13$300.00$105.00$320.00
115Special 04. inlets 5-FT diameter (SPV.0060)EACH1$5,537.58$5,210.00$4,164.42$6,404.00
116Special 05. inlets 2X3-FT special (SPV.0060)EACH5$3,330.64$3,080.00$2,459.28$3,435.00
117Special 06. solar powered RRFB system station 18+03 (SPV.0060)EACH1$19,260$21,260$20,260$19,260
118Special 07. sanitary wye, 12-inch X 6-inch (SPV.0060)EACH1$443.97$640.00$970.64$852.00
119Special 08. sanitary wye, 15-inch X 6-inch (SPV.0060)EACH1$717.95$990.00$1,261.08$1,338.00
120Special 09. sanitary sewer tracer wire access box (SPV.0060)EACH2$116.99$230.00$199.02$314.00
121Special 10. sanitary manhole casting (SPV.0060)EACH6$1,142.24$1,800.00$2,007.02$983.00
122Special 11. water valve and box, 6- inch (SPV.0060)EACH1$2,087.87$2,600.00$2,413.28$2,595.00
123Special 12. water valve and box, 8- inch (SPV.0060)EACH4$2,926.82$3,570.00$3,302.62$3,534.00
124Special 13. reducer, 8-inch X 6-inch (SPV.0060)EACH4$376.97$670.00$499.62$832.00
125Special 14. anchoring tee, 8-inch X 6-inch (SPV.0060)EACH1$712.95$1,130.00$955.78$1,330.00
126Special 15. tee, 8-inch X 6-inch (SPV.0060)EACH1$694.95$1,130.00$886.70$1,317.00
127Special 16. tee, 8-inch (SPV.0060)EACH2$792.96$1,245.00$990.58$1,416.00
128Special 17. cross, 8-inch (SPV.0060)EACH1$1,093.94$1,605.00$1,349.04$2,886.00
129Special 18. 11.25 degree bend, 8- inch (SPV.0060)EACH4$415.97$710.00$540.96$729.00
130Special 19. 22.5 degree bend, 8- inch (SPV.0060)EACH1$443.97$740.00$570.64$1,622.00
131Special 20. 45 degree bend, 8-inch (SPV.0060)EACH6$444.97$740.00$571.70$664.00
132Special 21. sleeve, 8-inch (SPV.0060)EACH6$439.97$740.00$566.40$1,042.00
133Special 22. water service corp stop, 1-inch (SPV.0060)EACH2$87.99$400.00$343.28$1,821.00
134Special 23. curb stop and box, 1- inch (SPV.0060)EACH2$345.98$780.00$451.76$1,660.00
135Special 24. reconnect to existing water service (SPV.0060)EACH2$2,391.12$500.00$86.04$628.00
136Special 25. reconnect to existing sanitary lateral (SPV.0060)EACH2$2,371.12$500.00$64.84$412.00
137Special 26. connect to existing sanitary sewer (SPV.0060)EACH5$4,766.21$3,500.00$3,055.12$3,434.00
138Special 27. connect to existing water main (SPV.0060)EACH6$5,088.86$2,500.00$3,397.15$6,004.00
139Special 28. connect to existing sanitary manhole (SPV.0060)EACH1$5,026.20$3,500.00$3,246.00$40,051
140Special 29. construction staking water main - project 9835-06-70 (SPV.0060)EACH1$961.24$1,462.00$900.00$961.24
141Special 30. construction staking sanitary sewer - project 9835-06-70 (SPV.0060)EACH1$1,417.78$1,918.00$900.00$1,417.78
142Special 31. 6-inch cap with flush pipe (SPV.0060)EACH4$77.99$1,600.00$587.53$659.00
143Special 32. 8-inch cap with flush pipe (SPV.0060)EACH2$98.99$1,600.00$842.72$1,256.00
144Special 33. remove, salvage, and reinstall existing hydrant and water valve (SPV.0060)EACH1$4,288.62$3,830.00$8,298.18$4,998.00
145Special 34. remove, salvage, and reinstall existing hydrant (SPV.0060)EACH1$3,613.65$2,600.00$7,582.68$4,299.00
146Special 35. remove, salvage, and reinstall existing 8-inch water valve (SPV.0060)EACH1$2,507.11$1,700.00$2,548.18$3,240.00
147Special 36. 18-inch hydrant barrel extension (SPV.0060)EACH1$1,815.07$2,000.00$1,922.52$2,059.00
148Special 37. solar powered RRFB system station 67+13 (SPV.0060)EACH1$19,260$21,260$20,260$19,260
149Special 38. deconstruct sanitary manhole drop entrance (SPV.0060)EACH1$3,685.65$1,500.00$9,800.00$34,607
150Special 39. temporary water (SPV.0060)EACH1$10,607$3,000.00$6,500.00$13,090
151Special 40. temporary sanitary bypass (SPV.0060)EACH1$15,293$20,000$56,900$59,550
152Special 41. reconstructing storm manhole #14 (SPV.0060)EACH1$4,085.63$7,000.00$9,800.00$24,282
153Special 01. storm sewer laterals 6- inch (SPV.0090)LF25$58.56$92.00$104.09$96.30
154Special 02. storm sewer PVC 10- inch (SPV.0090)LF32$49.69$94.00$105.63$112.25
155Special 03. sanitary sewer pipe PVC 8-inch (SPV.0090)LF100$93.01$121.00$125.06$197.60
156Special 04. sanitary sewer pipe PVC 12-inch (SPV.0090)LF100$115.08$137.00$140.75$374.80
157Special 05. sanitary sewer pipe PVC 15-inch (SPV.0090)LF310$147.75$282.00$450.00$346.10
158Special 06. sanitary sewer pipe PVC 21-inch (SPV.0090)LF15$173.82$298.00$296.25$971.40
159Special 07. sanitary sewer pipe PVC 24-inch (SPV.0090)LF90$172.49$314.00$381.27$816.80
160Special 08. sanitary lateral pipe PVC, 6-inch (SPV.0090)LF55$110.64$88.00$92.65$159.80
161Special 09. abandon-in-place existing sanitary sewer, 12-inch (SPV.0090)LF345$33.67$30.00$8.70$37.95
162Special 10. water main pipe ductile iron class 52, 6-inch (SPV.0090)LF45$131.04$105.00$229.70$147.40
163Special 11. water main pipe ductile iron class 52, 8-inch (SPV.0090)LF600$94.60$118.00$178.37$142.60
164Special 12. water service pipe, 1- inch (SPV.0090)LF90$94.23$94.00$101.60$84.90
165Special 01. preparing topsoil for lawn type turf (SPV.0180)SY7,710$0.40$1.30$0.40$0.40
166Special 02. removing excess pulverized material (SPV.0180)SY24,620$0.58$2.00$2.05$3.60
167Special 03. hydroseeding (SPV.0180)SY7,710$1.80$2.40$1.80$1.80
168Special 02. excavation, hauling and disposal of contaminated soil and MGT of groundwater (SPV.0195)TON685$104.60$70.00$90.00$98.00
169Special 01. sanitary manhole 4-FT diameter (SPV.0200)VF73.40$1,044.22$715.00$656.57$1,340.50
170Special 02. sanitary reduction manhole (SPV.0200)VF20.80$1,038.83$775.00$773.17$1,895.75
171Special 03. sanitary manhole outside drop (SPV.0200)VF42.60$294.64$600.00$612.96$1,309.80
WisDOT contract 20260210034: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of February 10, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy