WisDOT contract 20251111002 bid tabulation
Madison - Cambridge; CTH W/Oak Park Road Intersection (USH 012, Dane County Madison - Cambridge). Let by Wisconsin DOT on November 11, 2025, Dane. 6 bids received; low bid $2,670,241 by Parisi Construction, LLC.
- Owner
- Wisconsin DOT
- Letting
- 11 NOV 2025
- Pay items
- 147
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Parisi Construction, LLC | $2,670,241 | Low |
| 2 | Musson Bros., Inc. | $2,736,368 | +2.0% |
| 3 | Rock Road Companies, Inc. | $2,777,193 | +4.0% |
| 4 | James Peterson Sons, Inc. | $2,861,740 | +7.0% |
| 5 | Integrity Grading and Excavating, Inc. | $2,999,437 | +12% |
| 6 | R.G. Huston Company, Inc. | $3,182,435 | +19% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Parisi Construction, LLC | 2. Musson Bros., Inc. | 3. Rock Road Companies, Inc. | 4. James Peterson Sons, Inc. | 5. Integrity Grading and Excavating, Inc. | 6. R.G. Huston Company, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing small pipe culverts (203.0100) | EACH | 4 | $500.00 | $820.72 | $762.73 | $500.00 | $1,200.00 | $1,660.00 |
| 2 | Removing concrete pavement (204.0100) | SY | 7,340 | $6.00 | $8.83 | $5.59 | $1.35 | $4.00 | $4.35 |
| 3 | Removing asphaltic surface (204.0110) | SY | 2,600 | $2.00 | $2.08 | $4.89 | $4.05 | $2.92 | $2.80 |
| 4 | Removing curb & gutter (204.0150) | LF | 480 | $7.00 | $5.41 | $7.66 | $2.67 | $9.15 | $5.00 |
| 5 | Excavation common (205.0100) | CY | 16,165 | $10.00 | $12.27 | $12.37 | $12.67 | $18.00 | $15.00 |
| 6 | Borrow (208.0100) | CY | 35 | $10.00 | $64.53 | $31.00 | $32.00 | $50.00 | $45.00 |
| 7 | Finishing roadway (project) 01. 3080-01-78 (213.0100) | EACH | 1 | $1,000.00 | $2,000.00 | $5,389.33 | $2,500.00 | $500.00 | $2,760.00 |
| 8 | Base aggregate dense 3/4-inch (305.0110) | TON | 630 | $21.00 | $26.99 | $38.27 | $26.66 | $32.50 | $27.70 |
| 9 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 11,600 | $14.75 | $14.00 | $13.79 | $16.04 | $16.75 | $17.00 |
| 10 | Breaker run (311.0110) | TON | 550 | $13.75 | $14.00 | $14.46 | $13.57 | $16.75 | $15.00 |
| 11 | Select crushed material (312.0110) | TON | 11,350 | $13.50 | $14.00 | $13.79 | $13.57 | $16.75 | $15.00 |
| 12 | Coloring concrete wisdot red (405.0100) | CY | 184 | $135.00 | $135.00 | $135.00 | $135.00 | $135.00 | $131.31 |
| 13 | Concrete pavement 9-inch (415.0090) | SY | 8,990 | $80.00 | $80.00 | $80.00 | $80.00 | $80.00 | $89.75 |
| 14 | Concrete truck apron 12-inch (415.2010) | SY | 543 | $90.00 | $90.00 | $90.00 | $90.00 | $90.00 | $106.36 |
| 15 | Concrete pavement joint filling (415.4100) | SY | 8,990 | $2.20 | $2.30 | $2.10 | $2.10 | $2.10 | $2.12 |
| 16 | Rout and seal (415.6000.S) | LF | 2,412 | $3.70 | $4.75 | $3.55 | $3.55 | $3.55 | $3.59 |
| 17 | Drilled dowel bars (416.0620) | EACH | 48 | $40.00 | $40.00 | $40.00 | $40.00 | $40.00 | $25.00 |
| 18 | Tack coat (455.0605) | GAL | 155 | $3.10 | $3.00 | $3.63 | $3.00 | $3.00 | $3.03 |
| 19 | Incentive density HMA pavement (460.2000) | DOL | 430 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 20 | HMA pavement 4 MT 58-28 S (460.6224) | TON | 670 | $91.00 | $88.00 | $99.33 | $88.00 | $88.00 | $88.89 |
| 21 | Asphaltic surface driveways and field entrances (465.0120) | TON | 10 | $210.00 | $200.00 | $218.85 | $200.00 | $200.00 | $202.02 |
| 22 | Asphaltic surface temporary (465.0125) | TON | 1,220 | $93.00 | $90.00 | $102.73 | $90.00 | $90.00 | $90.91 |
| 23 | Asphaltic flumes (465.0315) | SY | 45 | $46.25 | $50.00 | $73.53 | $50.00 | $50.00 | $50.51 |
| 24 | Culvert pipe temporary 36-inch (520.2036) | LF | 34 | $10.00 | $143.01 | $375.70 | $150.00 | $109.00 | $106.00 |
| 25 | Culvert pipe class III-A 24-inch (520.3324) | LF | 163 | $96.00 | $88.17 | $90.21 | $113.50 | $55.00 | $57.00 |
| 26 | Concrete collars for pipe (520.8000) | EACH | 1 | $1,400.00 | $834.38 | $794.04 | $800.00 | $870.00 | $1,000.00 |
| 27 | Apron endwalls for culvert pipe sloped side drains steel 24-inch 6 to 1 (521.1524) | EACH | 2 | $1,500.00 | $2,682.12 | $1,354.43 | $2,235.00 | $2,200.00 | $2,100.00 |
| 28 | Culvert pipe reinforced concrete class IV 42-inch (522.0442) | LF | 107 | $230.00 | $289.26 | $354.88 | $297.35 | $230.00 | $207.00 |
| 29 | Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012) | EACH | 4 | $1,800.00 | $1,261.17 | $1,103.32 | $1,070.00 | $1,495.00 | $1,315.00 |
| 30 | Apron endwalls for culvert pipe reinforced concrete 36-inch (522.1036) | EACH | 2 | $2,700.00 | $2,431.95 | $2,197.12 | $2,250.00 | $3,050.00 | $2,320.00 |
| 31 | Apron endwalls for culvert pipe reinforced concrete 42-inch (522.1042) | EACH | 2 | $3,100.00 | $3,466.88 | $3,318.23 | $2,740.00 | $3,370.00 | $2,700.00 |
| 32 | Culvert pipe reinforced concrete horizontal elliptical class HE-III 34X53-inch (522.2334) | LF | 34 | $220.00 | $247.88 | $270.37 | $325.38 | $275.00 | $220.00 |
| 33 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 34X53-inch (522.2634) | EACH | 2 | $3,100.00 | $2,986.72 | $3,363.34 | $2,736.00 | $3,365.00 | $4,740.00 |
| 34 | Culvert pipe salvaged 30-inch (524.0130) | LF | 31 | $66.00 | $86.06 | $81.79 | $165.00 | $67.00 | $130.00 |
| 35 | Apron endwalls for culvert pipe salvaged 30-inch (524.0630) | EACH | 2 | $600.00 | $734.58 | $910.75 | $2,250.00 | $670.00 | $970.00 |
| 36 | Concrete curb integral type D (601.0150) | LF | 29 | $41.00 | $41.00 | $41.00 | $41.00 | $41.00 | $45.45 |
| 37 | Concrete curb & gutter 18-inch type A (601.0405) | LF | 246 | $32.00 | $32.00 | $32.00 | $32.00 | $32.00 | $30.30 |
| 38 | Concrete curb & gutter 30-inch type A (601.0409) | LF | 1,908 | $22.50 | $22.50 | $22.50 | $22.50 | $22.50 | $25.76 |
| 39 | Concrete curb & gutter integral 4- inch sloped 36-inch (601.0501) | LF | 27 | $35.00 | $35.00 | $35.00 | $35.00 | $35.00 | $50.00 |
| 40 | Concrete curb & gutter 4-inch sloped 36-inch type A (601.0551) | LF | 1,839 | $24.50 | $24.50 | $24.50 | $24.50 | $24.50 | $27.37 |
| 41 | Concrete curb & gutter 4-inch sloped 30-inch type R (601.0581) | LF | 337 | $28.00 | $28.00 | $28.00 | $28.00 | $28.00 | $35.35 |
| 42 | Concrete sidewalk 4-inch (602.0405) | SF | 10,930 | $5.75 | $5.75 | $5.75 | $5.75 | $5.75 | $6.97 |
| 43 | Riprap medium (606.0200) | CY | 65 | $100.00 | $158.50 | $138.23 | $125.00 | $170.00 | $176.00 |
| 44 | Storm sewer pipe reinforced concrete class III 12-inch (608.0312) | LF | 139 | $67.00 | $98.82 | $97.27 | $150.35 | $166.00 | $90.00 |
| 45 | Storm sewer pipe reinforced concrete class III 36-inch (608.0336) | LF | 107 | $140.00 | $202.21 | $174.62 | $215.56 | $233.00 | $161.00 |
| 46 | Storm sewer pipe reinforced concrete class IV 12-inch (608.0412) | LF | 135 | $72.00 | $93.48 | $97.27 | $149.15 | $166.00 | $91.00 |
| 47 | Manhole covers type J (611.0530) | EACH | 2 | $810.00 | $751.00 | $959.42 | $560.00 | $745.00 | $825.00 |
| 48 | Inlet covers type HM-S (611.0636) | EACH | 1 | $1,100.00 | $1,163.46 | $1,198.48 | $930.00 | $1,020.00 | $1,080.00 |
| 49 | Inlet covers type H-S (611.0639) | EACH | 10 | $1,100.00 | $1,163.46 | $1,198.48 | $900.00 | $998.00 | $1,080.00 |
| 50 | Inlet covers type T (611.0652) | EACH | 2 | $1,300.00 | $1,332.30 | $1,466.86 | $1,250.00 | $1,265.00 | $1,325.00 |
| 51 | Manholes 5-FT diameter (611.2005) | EACH | 2 | $3,900.00 | $4,578.53 | $3,585.66 | $4,775.00 | $5,165.00 | $3,745.00 |
| 52 | Inlets 2X2.5-FT (611.3225) | EACH | 2 | $1,900.00 | $1,884.12 | $2,265.21 | $2,075.00 | $3,335.00 | $1,250.00 |
| 53 | Inlets 2X3-FT (611.3230) | EACH | 11 | $2,000.00 | $1,671.81 | $2,244.91 | $2,275.00 | $3,425.00 | $1,345.00 |
| 54 | Cover plates temporary (611.8120.S) | EACH | 5 | $500.00 | $318.54 | $350.00 | $300.00 | $364.00 | $290.00 |
| 55 | Pipe grates (size) 01. 36-inch (611.9850.S) | EACH | 2 | $2,700.00 | $2,159.20 | $1,177.13 | $2,986.00 | $2,000.00 | $2,430.00 |
| 56 | Pipe grates (size) 02. 42-inch (611.9850.S) | EACH | 2 | $3,200.00 | $2,656.84 | $1,561.76 | $3,757.00 | $2,300.00 | $3,000.00 |
| 57 | Pipe grates (size) 03. 34X53-inch (611.9850.S) | EACH | 2 | $2,400.00 | $1,927.88 | $2,413.12 | $2,805.00 | $2,400.00 | $2,170.00 |
| 58 | Pipe underdrain 6-inch (612.0106) | LF | 1,230 | $15.25 | $9.18 | $25.74 | $11.90 | $16.00 | $15.00 |
| 59 | Apron endwalls for underdrain reinforced concrete 6-inch (612.0806) | EACH | 4 | $410.00 | $260.59 | $820.54 | $370.00 | $360.00 | $500.00 |
| 60 | Maintenance and repair of haul roads (project) 01. 3080-01-78 (618.0100) | EACH | 1 | $500.00 | $1.00 | $0.01 | $750.00 | $500.00 | $100.00 |
| 61 | Mobilization (619.1000) | EACH | 1 | $275,000 | $250,000 | $308,482 | $348,650 | $267,678 | $560,000 |
| 62 | Concrete median sloped nose (620.0300) | SF | 590 | $10.00 | $10.00 | $10.00 | $10.00 | $17.50 | $13.64 |
| 63 | Water (624.0100) | MGAL | 300 | $5.00 | $0.01 | $0.01 | $50.00 | $53.00 | $0.01 |
| 64 | Topsoil (625.0100) | SY | 21,500 | $2.70 | $1.00 | $0.01 | $1.30 | $4.70 | $0.01 |
| 65 | Mulching (627.0200) | SY | 16,000 | $0.50 | $0.50 | $0.50 | $0.50 | $0.50 | $0.35 |
| 66 | Silt fence (628.1504) | LF | 2,300 | $2.30 | $2.20 | $2.20 | $2.20 | $2.20 | $2.00 |
| 67 | Silt fence maintenance (628.1520) | LF | 2,300 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 68 | Mobilizations erosion control (628.1905) | EACH | 9 | $260.00 | $250.00 | $250.00 | $250.00 | $250.00 | $100.00 |
| 69 | Mobilizations emergency erosion control (628.1910) | EACH | 6 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $100.00 |
| 70 | Erosion mat class I type B (628.2004) | SY | 5,500 | $2.60 | $2.50 | $2.50 | $2.50 | $2.50 | $1.15 |
| 71 | Inlet protection type A (628.7005) | EACH | 13 | $51.00 | $50.00 | $50.00 | $50.00 | $50.00 | $90.00 |
| 72 | Inlet protection type C (628.7015) | EACH | 13 | $150.00 | $150.00 | $150.00 | $150.00 | $150.00 | $65.00 |
| 73 | Temporary ditch checks (628.7504) | LF | 150 | $8.20 | $8.00 | $8.00 | $8.00 | $8.00 | $9.00 |
| 74 | Culvert pipe checks (628.7555) | EACH | 36 | $12.25 | $12.00 | $12.00 | $12.00 | $12.00 | $22.00 |
| 75 | Tracking pads (628.7560) | EACH | 4 | $630.00 | $1,580.73 | $750.00 | $3,000.00 | $1,000.00 | $2,300.00 |
| 76 | Fertilizer type B (629.0210) | CWT | 22 | $130.00 | $125.00 | $125.00 | $125.00 | $125.00 | $90.00 |
| 77 | Seeding mixture no. 20 (630.0120) | LB | 855 | $7.70 | $7.50 | $7.50 | $7.50 | $7.50 | $8.75 |
| 78 | Seeding mixture no. 40 (630.0140) | LB | 25 | $12.25 | $12.00 | $12.00 | $12.00 | $12.00 | $16.00 |
| 79 | Seeding temporary (630.0200) | LB | 685 | $1.50 | $1.50 | $1.50 | $1.50 | $1.50 | $4.00 |
| 80 | Seed water (630.0500) | MGAL | 1,450 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $10.00 |
| 81 | Markers row (633.5100) | EACH | 36 | $100.00 | $100.00 | $70.00 | $100.00 | $100.00 | $70.00 |
| 82 | Markers culvert end (633.5200) | EACH | 12 | $87.00 | $85.00 | $85.00 | $85.00 | $85.00 | $65.00 |
| 83 | Posts wood 4X6-inch X 12-FT (634.0612) | EACH | 4 | $140.00 | $140.00 | $140.00 | $148.00 | $140.00 | $85.00 |
| 84 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 12 | $140.00 | $140.00 | $140.00 | $140.00 | $140.00 | $90.00 |
| 85 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 4 | $150.00 | $150.00 | $150.00 | $150.00 | $150.00 | $95.00 |
| 86 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 10 | $160.00 | $160.00 | $160.00 | $160.00 | $160.00 | $100.00 |
| 87 | Posts tubular steel 2X2-inch X 14- FT (634.0814) | EACH | 13 | $310.00 | $300.00 | $300.00 | $300.00 | $300.00 | $185.00 |
| 88 | Signs type II reflective H (637.2210) | SF | 422.54 | $27.75 | $27.00 | $27.00 | $27.00 | $27.00 | $19.00 |
| 89 | Signs type II reflective F (637.2230) | SF | 75.56 | $29.75 | $29.00 | $29.00 | $29.00 | $29.00 | $20.00 |
| 90 | Moving signs type II (638.2102) | EACH | 9 | $210.00 | $200.00 | $200.00 | $200.00 | $200.00 | $150.00 |
| 91 | Removing signs type II (638.2602) | EACH | 12 | $51.00 | $50.00 | $50.00 | $50.00 | $50.00 | $40.00 |
| 92 | Removing small sign supports (638.3000) | EACH | 14 | $51.00 | $50.00 | $50.00 | $50.00 | $50.00 | $40.00 |
| 93 | Moving small sign supports (638.4000) | EACH | 11 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $100.00 |
| 94 | Field office type C (642.5201) | EACH | 1 | $6,500.00 | $10,000 | $6,250.00 | $12,500 | $15,000 | $13,500 |
| 95 | Traffic control drums (643.0300) | DAY | 8,500 | $0.15 | $0.25 | $0.15 | $0.15 | $0.25 | $0.25 |
| 96 | Traffic control barricades type III (643.0420) | DAY | 1,700 | $0.50 | $1.00 | $0.50 | $0.50 | $1.00 | $1.00 |
| 97 | Traffic control warning lights type A (643.0705) | DAY | 3,400 | $0.15 | $0.10 | $0.15 | $0.15 | $0.10 | $0.10 |
| 98 | Traffic control warning lights type C (643.0715) | DAY | 1,600 | $0.15 | $0.10 | $0.15 | $0.15 | $0.10 | $0.10 |
| 99 | Traffic control signs (643.0900) | DAY | 9,700 | $0.25 | $0.25 | $0.22 | $0.22 | $0.25 | $0.25 |
| 100 | Traffic control covering signs type II (643.0920) | EACH | 1 | $150.00 | $50.00 | $150.00 | $150.00 | $50.00 | $50.00 |
| 101 | Traffic control signs fixed message (643.1000) | SF | 42 | $15.50 | $18.00 | $15.00 | $15.00 | $18.00 | $18.00 |
| 102 | Traffic control signs PCMS (643.1050) | DAY | 60 | $46.25 | $50.00 | $45.00 | $45.00 | $50.00 | $50.00 |
| 103 | Temporary marking line paint 6- inch (643.3165) | LF | 7,200 | $0.25 | $0.30 | $0.25 | $0.25 | $0.30 | $0.30 |
| 104 | Temporary marking line removable tape 6-inch (643.3180) | LF | 12,800 | $2.10 | $1.10 | $2.00 | $2.00 | $1.10 | $1.10 |
| 105 | Traffic control (643.5000) | EACH | 1 | $22,200 | $10,000 | $21,575 | $21,575 | $10,000 | $10,000 |
| 106 | Geotextile type HR (645.0120) | SY | 195 | $2.70 | $2.97 | $1.67 | $4.00 | $1.69 | $3.00 |
| 107 | Geogrid type SR (645.0220) | SY | 15,700 | $1.40 | $2.21 | $1.76 | $0.82 | $0.65 | $1.15 |
| 108 | Marking line epoxy 6-inch (646.2020) | LF | 6,860 | $0.50 | $0.85 | $0.50 | $0.50 | $0.85 | $0.91 |
| 109 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 15,240 | $1.40 | $1.50 | $1.40 | $1.40 | $1.50 | $1.62 |
| 110 | Marking line epoxy 10-inch (646.4020) | LF | 275 | $1.10 | $1.55 | $1.05 | $1.05 | $1.55 | $3.03 |
| 111 | Marking outfall epoxy (646.5520) | EACH | 4 | $51.00 | $160.00 | $49.75 | $49.75 | $160.00 | $353.54 |
| 112 | Marking dotted extension epoxy 18-inch (646.6320) | LF | 65 | $16.50 | $16.00 | $16.00 | $16.00 | $16.00 | $20.20 |
| 113 | Marking diagonal epoxy 12-inch (646.7120) | LF | 355 | $16.00 | $11.00 | $15.60 | $15.60 | $11.00 | $10.40 |
| 114 | Marking curb epoxy (646.8120) | LF | 265 | $8.00 | $12.00 | $7.75 | $7.75 | $12.00 | $8.08 |
| 115 | Marking island nose epoxy (646.8220) | EACH | 4 | $300.00 | $330.00 | $287.25 | $287.25 | $330.00 | $323.23 |
| 116 | Marking removal line 4-inch (646.9000) | LF | 2,460 | $0.50 | $0.45 | $0.50 | $0.50 | $0.45 | $0.45 |
| 117 | Marking removal line 8-inch (646.9100) | LF | 200 | $2.10 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 |
| 118 | Locating no-passing zones (648.0100) | MI | 0.52 | $590.00 | $4,500.00 | $576.92 | $576.92 | $4,500.00 | $1,515.15 |
| 119 | Construction staking storm sewer (650.4000) | EACH | 21 | $1.00 | $200.00 | $15.00 | $200.00 | $200.00 | $200.00 |
| 120 | Construction staking subgrade (650.4500) | LF | 6,432 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 121 | Construction staking base (650.5000) | LF | 4,645 | $0.01 | $1.00 | $0.01 | $1.00 | $1.00 | $1.00 |
| 122 | Construction staking pipe culverts (650.6000) | EACH | 3 | $1.00 | $200.00 | $100.00 | $200.00 | $200.00 | $200.00 |
| 123 | Construction staking concrete pavement (650.7000) | LF | 1,787 | $0.01 | $3.00 | $1.00 | $3.00 | $3.00 | $3.00 |
| 124 | Construction staking electrical installations (project) 01. 3080-01- 78 (650.8501) | EACH | 1 | $1.00 | $3,000.00 | $3,500.00 | $3,000.00 | $3,000.00 | $3,000.00 |
| 125 | Construction staking supplemental control (project) 01. 3080-01-78 (650.9911) | EACH | 1 | $1.00 | $10,000 | $3,500.00 | $10,000 | $10,000 | $10,000 |
| 126 | Construction staking slope stakes (650.9920) | LF | 6,432 | $0.01 | $1.50 | $0.33 | $1.50 | $1.50 | $1.50 |
| 127 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 1,745 | $8.20 | $8.00 | $8.00 | $8.00 | $8.00 | $8.00 |
| 128 | Conduit rigid nonmetallic schedule 40 3-inch (652.0235) | LF | 144 | $10.25 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 |
| 129 | Conduit rigid nonmetallic schedule 80 2-inch (652.0325) | LF | 302 | $9.30 | $9.00 | $9.00 | $9.00 | $9.00 | $9.00 |
| 130 | Pull boxes non-conductive 24X42- inch (653.0164) | EACH | 15 | $2,100.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 |
| 131 | Concrete bases type 5 (654.0105) | EACH | 15 | $1,100.00 | $1,100.00 | $1,100.00 | $1,100.00 | $1,100.00 | $1,100.00 |
| 132 | Concrete control cabinet bases type L30 (654.0230) | EACH | 1 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 133 | Electrical wire lighting 10 AWG (655.0615) | LF | 16,784 | $1.20 | $1.20 | $1.20 | $1.20 | $1.20 | $1.20 |
| 134 | Electrical service meter breaker pedestal (location) 01. sta. 572+15 'WB', 60.5' LT. (656.0201) | EACH | 1 | $2,100.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 |
| 135 | Transformer bases breakaway 11 1/2-inch bolt circle (657.0255) | EACH | 15 | $590.00 | $575.00 | $575.00 | $575.00 | $575.00 | $575.00 |
| 136 | Poles type 5-aluminum (657.0322) | EACH | 15 | $2,000.00 | $1,900.00 | $1,900.00 | $1,900.00 | $1,900.00 | $1,900.00 |
| 137 | Luminaire arms truss type 4 1/2- inch clamp 12-FT (657.0710) | EACH | 15 | $700.00 | $680.00 | $680.00 | $680.00 | $680.00 | $680.00 |
| 138 | Luminaires utility LED B (659.1120) | EACH | 15 | $270.00 | $260.00 | $260.00 | $260.00 | $260.00 | $260.00 |
| 139 | Lighting control cabinets 120/240 30-inch (659.2130) | EACH | 1 | $8,200.00 | $8,000.00 | $8,000.00 | $8,000.00 | $8,000.00 | $8,000.00 |
| 140 | Sawing asphalt (690.0150) | LF | 45 | $1.40 | $8.00 | $1.50 | $1.39 | $1.39 | $1.39 |
| 141 | Sawing concrete (690.0250) | LF | 1,800 | $2.10 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 |
| 142 | Incentive compressive strength concrete pavement (715.0720) | DOL | 2,860 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 143 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,000 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 144 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 1,320 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 145 | Special 01. construction staking roundabout (SPV.0060) | EACH | 1 | $500.00 | $20,000 | $5,000.00 | $20,000 | $20,000 | $20,000 |
| 146 | Special 02. apron endwalls temporary 36-inch (SPV.0060) | EACH | 1 | $100.00 | $1,497.52 | $2,001.92 | $1,500.00 | $2,200.00 | $1,300.00 |
| 147 | Special 03. temporary lighting (SPV.0060) | EACH | 1 | $2,600.00 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of November 11, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.