WisDOT contract 20260113006 bid tabulation
3997-01-79. Let by Wisconsin DOT on January 13, 2026, Jefferson. 7 bids received; low bid $3,245,906 by Integrity Grading and Excavating, Inc..
- Owner
- Wisconsin DOT
- Letting
- 13 JAN 2026
- Pay items
- 123
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Integrity Grading and Excavating, Inc. | $3,245,906 | Low |
| 2 | Lalonde Contractors Incorporated | $3,269,125 | +1.0% |
| 3 | Forest Landscaping & Construction Inc. | $3,299,169 | +2.0% |
| 4 | Zignego Company, Inc. | $3,369,504 | +4.0% |
| 5 | Rock Road Companies, Inc. | $3,536,222 | +9.0% |
| 6 | James Peterson Sons, Inc. | $3,969,739 | +22% |
| 7 | Parisi Construction, LLC | $4,536,022 | +40% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Integrity Grading and Excavating, Inc. | 2. Lalonde Contractors Incorporated | 3. Forest Landscaping & Construction Inc. | 4. Zignego Company, Inc. | 5. Rock Road Companies, Inc. | 6. James Peterson Sons, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0110) | SY | 64 | $80.00 | $80.00 | $140.00 | $55.55 | $55.55 | $55.55 |
| 2 | Grubbing (201.0210) | SY | 64 | $6.00 | $6.00 | $45.00 | $55.55 | $55.55 | $55.55 |
| 3 | Removing concrete pavement (204.0100) | SY | 8,331 | $3.10 | $7.31 | $7.00 | $10.64 | $7.15 | $8.59 |
| 4 | Removing asphaltic surface (204.0110) | SY | 516 | $0.01 | $6.38 | $5.00 | $10.64 | $6.78 | $2.63 |
| 5 | Removing curb & gutter (204.0150) | LF | 10 | $6.10 | $8.28 | $35.00 | $50.00 | $8.78 | $100.00 |
| 6 | Removing concrete sidewalk (204.0155) | SY | 1,937 | $8.30 | $10.68 | $6.00 | $8.00 | $15.40 | $4.82 |
| 7 | Removing manholes (204.0210) | EACH | 13 | $1,138.90 | $500.00 | $800.00 | $800.00 | $369.33 | $750.00 |
| 8 | Removing inlets (204.0220) | EACH | 15 | $1,138.90 | $300.00 | $600.00 | $600.00 | $369.33 | $750.00 |
| 9 | Removing storm sewer (size) 01. 10-inch (204.0245) | LF | 116 | $22.78 | $16.00 | $15.00 | $15.00 | $10.62 | $38.22 |
| 10 | Removing storm sewer (size) 02. 12-inch (204.0245) | LF | 1,523 | $22.78 | $12.00 | $15.00 | $18.00 | $10.62 | $24.97 |
| 11 | Removing storm sewer (size) 03. 15-inch (204.0245) | LF | 1,404 | $22.78 | $12.00 | $18.00 | $18.00 | $10.62 | $25.32 |
| 12 | Removing storm sewer (size) 04. 18-inch (204.0245) | LF | 735 | $22.78 | $12.00 | $18.00 | $20.00 | $10.62 | $27.33 |
| 13 | Removing storm sewer (size) 05. 24-inch (204.0245) | LF | 141 | $22.78 | $12.00 | $24.00 | $24.00 | $10.62 | $30.10 |
| 14 | Excavation common (205.0100) | CY | 5,173 | $30.00 | $20.41 | $20.00 | $19.00 | $19.14 | $18.10 |
| 15 | Finishing roadway (project) 01. 3997-01-79 (213.0100) | EACH | 1 | $500.00 | $2,610.00 | $2,500.00 | $1,000.00 | $5,023.27 | $10,000 |
| 16 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 4,500 | $19.49 | $21.04 | $21.00 | $30.00 | $22.52 | $21.33 |
| 17 | Tack coat (455.0605) | GAL | 40 | $4.00 | $2.50 | $4.00 | $4.00 | $4.00 | $4.00 |
| 18 | Incentive density HMA pavement (460.2000) | DOL | 70 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 19 | HMA pavement 3 MT 58-28 S (460.6223) | TON | 60 | $135.00 | $249.00 | $140.00 | $135.00 | $135.00 | $135.00 |
| 20 | HMA pavement 4 MT 58-28 S (460.6224) | TON | 40 | $180.00 | $249.00 | $185.00 | $180.00 | $180.00 | $180.00 |
| 21 | Asphaltic surface driveways and field entrances (465.0120) | TON | 30 | $195.00 | $315.00 | $200.00 | $195.00 | $195.00 | $195.00 |
| 22 | Concrete collars for pipe (520.8000) | EACH | 4 | $735.17 | $500.00 | $1,200.00 | $1,500.00 | $847.27 | $641.25 |
| 23 | Apron endwalls for culvert pipe reinforced concrete 36-inch (522.1036) | EACH | 1 | $2,949.47 | $3,000.00 | $3,500.00 | $3,000.00 | $2,596.27 | $2,131.15 |
| 24 | Concrete curb & gutter 18-inch type D (601.0407) | LF | 10 | $71.49 | $53.82 | $75.00 | $50.00 | $71.49 | $71.49 |
| 25 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 14 | $72.22 | $49.17 | $75.00 | $50.00 | $72.22 | $72.22 |
| 26 | Concrete curb pedestrian (601.0600) | LF | 66 | $65.14 | $53.77 | $66.00 | $50.00 | $65.14 | $65.14 |
| 27 | Concrete sidewalk 5-inch (602.0410) | SF | 17,950 | $6.02 | $7.94 | $6.15 | $7.05 | $6.02 | $6.02 |
| 28 | Curb ramp detectable warning field natural patina (602.0515) | SF | 290 | $47.73 | $42.20 | $48.00 | $40.00 | $47.73 | $47.73 |
| 29 | Concrete driveway hes 6-inch (602.0860) | SY | 1,360 | $62.54 | $87.73 | $63.00 | $71.55 | $62.54 | $62.54 |
| 30 | Concrete steps (602.1500) | SF | 200 | $84.89 | $84.73 | $85.00 | $80.00 | $84.89 | $84.89 |
| 31 | Riprap medium (606.0200) | CY | 3 | $229.05 | $100.00 | $150.00 | $150.00 | $207.15 | $92.58 |
| 32 | Storm sewer pipe reinforced concrete class III 15-inch (608.0315) | LF | 186 | $102.28 | $122.00 | $80.00 | $80.00 | $154.09 | $261.66 |
| 33 | Storm sewer pipe reinforced concrete class III 18-inch (608.0318) | LF | 208 | $102.50 | $124.00 | $85.00 | $85.00 | $134.57 | $127.42 |
| 34 | Storm sewer pipe reinforced concrete class III 36-inch (608.0336) | LF | 647 | $169.35 | $182.00 | $160.00 | $160.00 | $176.32 | $202.54 |
| 35 | Storm sewer pipe reinforced concrete class IV 15-inch (608.0415) | LF | 60 | $106.08 | $121.00 | $80.00 | $80.00 | $154.09 | $255.07 |
| 36 | Storm sewer pipe reinforced concrete class IV 24-inch (608.0424) | LF | 780 | $112.18 | $140.00 | $105.00 | $105.00 | $126.75 | $148.42 |
| 37 | Storm sewer pipe reinforced concrete class IV 36-inch (608.0436) | LF | 502 | $185.95 | $200.00 | $175.00 | $175.00 | $181.55 | $202.69 |
| 38 | Storm sewer pipe reinforced concrete horizontal elliptical class HE-IV 29X45-inch (608.2429) | LF | 147 | $110.25 | $292.00 | $230.00 | $230.00 | $253.00 | $298.28 |
| 39 | Manhole covers type J-special (611.0535) | EACH | 9 | $735.57 | $490.00 | $900.00 | $900.00 | $1,329.33 | $1,257.04 |
| 40 | Inlet covers type H (611.0624) | EACH | 16 | $908.56 | $673.00 | $1,200.00 | $1,200.00 | $1,392.44 | $1,715.39 |
| 41 | Catch basins 4-FT diameter (611.1004) | EACH | 2 | $4,222.03 | $673.00 | $3,400.00 | $3,400.00 | $3,658.08 | $3,066.46 |
| 42 | Catch basins 2X3-FT (611.1230) | EACH | 14 | $3,837.24 | $2,850.00 | $2,800.00 | $2,800.00 | $3,136.91 | $2,656.54 |
| 43 | Manholes 4-FT diameter (611.2004) | EACH | 4 | $3,708.52 | $3,000.00 | $3,300.00 | $3,400.00 | $3,398.31 | $2,130.14 |
| 44 | Manholes 5-FT diameter (611.2005) | EACH | 3 | $5,158.13 | $4,400.00 | $4,000.00 | $4,000.00 | $4,849.22 | $3,931.08 |
| 45 | Manholes 6-FT diameter (611.2006) | EACH | 1 | $7,770.51 | $7,000.00 | $5,000.00 | $5,000.00 | $6,433.33 | $6,565.93 |
| 46 | Manholes 7-FT diameter (611.2007) | EACH | 1 | $9,568.47 | $8,400.00 | $6,000.00 | $6,300.00 | $6,653.33 | $7,172.34 |
| 47 | Adjusting manhole covers (611.8110) | EACH | 2 | $817.57 | $600.00 | $1,500.00 | $1,500.00 | $1,545.65 | $712.44 |
| 48 | Fence chain link salvaged 4-FT (616.0404) | LF | 10 | $100.00 | $90.00 | $50.00 | $90.00 | $100.00 | $100.00 |
| 49 | Maintenance and repair of haul roads (project) 01. 3997-01-80 (618.0100) | EACH | 1 | $500.00 | $1.00 | $1,000.00 | $1.00 | $0.01 | $1.00 |
| 50 | Mobilization (619.1000) | EACH | 1 | $286,000 | $123,937 | $135,000 | $167,000 | $272,000 | $331,295 |
| 51 | Water (624.0100) | MGAL | 45 | $45.34 | $56.20 | $40.00 | $200.00 | $0.01 | $50.00 |
| 52 | Salvaged topsoil (625.0500) | SY | 3,300 | $13.51 | $4.01 | $6.50 | $10.00 | $3.70 | $11.14 |
| 53 | Silt fence (628.1504) | LF | 50 | $10.00 | $5.00 | $10.00 | $5.00 | $10.00 | $10.00 |
| 54 | Silt fence maintenance (628.1520) | LF | 50 | $1.00 | $0.01 | $5.00 | $0.01 | $1.00 | $1.00 |
| 55 | Mobilizations erosion control (628.1905) | EACH | 3 | $1.00 | $150.00 | $200.00 | $150.00 | $1.00 | $1.00 |
| 56 | Mobilizations emergency erosion control (628.1910) | EACH | 3 | $1.00 | $150.00 | $250.00 | $150.00 | $1.00 | $1.00 |
| 57 | Erosion mat urban class I type A (628.2006) | SY | 3,300 | $5.00 | $1.85 | $2.00 | $1.85 | $5.00 | $5.00 |
| 58 | Inlet protection type D (628.7020) | EACH | 37 | $125.00 | $90.00 | $100.00 | $90.00 | $125.00 | $125.00 |
| 59 | Fertilizer type A (629.0205) | CWT | 210 | $0.01 | $0.01 | $0.10 | $1.00 | $0.01 | $0.01 |
| 60 | Seeding mixture no. 40 (630.0140) | LB | 60 | $25.00 | $12.95 | $15.00 | $12.95 | $25.00 | $25.00 |
| 61 | Seeding temporary (630.0200) | LB | 90 | $2.00 | $5.00 | $6.00 | $5.00 | $2.00 | $2.00 |
| 62 | Seed water (630.0500) | MGAL | 19 | $100.00 | $25.00 | $30.00 | $25.00 | $100.00 | $100.00 |
| 63 | Posts tubular steel 2X2-inch X 12- FT (634.0812) | EACH | 17 | $300.00 | $220.00 | $225.00 | $220.00 | $300.00 | $300.00 |
| 64 | Signs type II reflective F (637.2230) | SF | 66.26 | $32.00 | $25.00 | $30.00 | $25.00 | $32.00 | $32.00 |
| 65 | Removing signs type II (638.2602) | EACH | 17 | $50.00 | $30.00 | $35.00 | $30.00 | $50.00 | $50.00 |
| 66 | Removing small sign supports (638.3000) | EACH | 17 | $50.00 | $30.00 | $35.00 | $30.00 | $50.00 | $50.00 |
| 67 | Field office type B (642.5001) | EACH | 1 | $15,750 | $11,108 | $10,000 | $10,000 | $12,150 | $16,000 |
| 68 | Traffic control drums (643.0300) | DAY | 1,175 | $1.00 | $1.00 | $1.10 | $1.00 | $1.00 | $0.15 |
| 69 | Traffic control barricades type III (643.0420) | DAY | 1,880 | $1.00 | $1.00 | $1.10 | $1.00 | $1.00 | $0.45 |
| 70 | Traffic control warning lights type A (643.0705) | DAY | 5,085 | $0.10 | $0.10 | $0.20 | $0.10 | $0.10 | $0.10 |
| 71 | Traffic control signs (643.0900) | DAY | 8,590 | $0.20 | $0.20 | $0.30 | $0.20 | $0.20 | $0.25 |
| 72 | Traffic control signs PCMS (643.1050) | DAY | 14 | $80.00 | $80.00 | $100.00 | $80.00 | $80.00 | $45.00 |
| 73 | Traffic control (643.5000) | EACH | 1 | $8,300.00 | $8,300.00 | $8,500.00 | $8,300.00 | $8,300.00 | $32,850 |
| 74 | Temporary pedestrian surface asphalt (644.1410) | SF | 3,200 | $3.75 | $0.01 | $4.00 | $3.75 | $2.50 | $3.75 |
| 75 | Temporary pedestrian curb ramp (644.1601) | DAY | 3,000 | $5.00 | $0.01 | $5.25 | $5.00 | $5.00 | $5.75 |
| 76 | Temporary pedestrian barricade (644.1810) | LF | 396 | $5.00 | $5.00 | $6.00 | $5.00 | $5.00 | $8.00 |
| 77 | Geotextile type HR (645.0120) | SY | 12 | $37.58 | $8.00 | $10.00 | $6.00 | $2.54 | $93.42 |
| 78 | Marking line epoxy 6-inch (646.2020) | LF | 4,890 | $0.95 | $0.95 | $53.00 | $0.95 | $0.51 | $0.51 |
| 79 | Marking stop line epoxy 18-inch (646.6120) | LF | 41 | $11.30 | $11.30 | $17.00 | $11.30 | $16.92 | $16.92 |
| 80 | Marking crosswalk epoxy block style 24-inch (646.7520) | LF | 666 | $15.10 | $15.10 | $28.00 | $15.10 | $27.76 | $27.76 |
| 81 | Marking curb epoxy (646.8120) | LF | 781 | $12.75 | $12.75 | $9.00 | $12.75 | $8.09 | $8.09 |
| 82 | Construction staking storm sewer (650.4000) | EACH | 26 | $200.00 | $200.00 | $300.00 | $200.00 | $200.00 | $200.00 |
| 83 | Construction staking subgrade (650.4500) | LF | 1,997 | $0.01 | $0.01 | $1.00 | $0.01 | $0.01 | $0.01 |
| 84 | Construction staking base (650.5000) | LF | 1,997 | $2.00 | $2.50 | $2.10 | $2.00 | $2.00 | $2.00 |
| 85 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 4,274 | $2.00 | $2.50 | $2.10 | $2.00 | $2.00 | $2.00 |
| 86 | Construction staking concrete pavement (650.7000) | LF | 1,997 | $3.00 | $2.50 | $3.10 | $3.00 | $3.00 | $3.00 |
| 87 | Construction staking curb ramps (650.9000) | EACH | 18 | $300.00 | $150.00 | $315.00 | $300.00 | $300.00 | $300.00 |
| 88 | Construction staking sidewalk (project) 01. 3997-01-79 (650.9500) | EACH | 1 | $4,000.00 | $5,000.00 | $4,100.00 | $4,000.00 | $4,000.00 | $4,000.00 |
| 89 | Construction staking supplemental control (project) 01. 3997-01-79 (650.9911) | EACH | 1 | $5,000.00 | $4,000.00 | $5,100.00 | $5,000.00 | $5,000.00 | $5,000.00 |
| 90 | Sawing asphalt (690.0150) | LF | 451 | $2.25 | $1.25 | $5.00 | $1.25 | $1.89 | $1.45 |
| 91 | Sawing concrete (690.0250) | LF | 916 | $2.25 | $2.35 | $5.00 | $2.35 | $2.15 | $2.45 |
| 92 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,000 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 93 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 1,320 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 94 | Special 01. 8-inch gate valve & box (SPV.0060) | EACH | 18 | $2,597.89 | $3,000.00 | $3,200.00 | $3,000.00 | $3,260.03 | $3,324.22 |
| 95 | Special 02. 6-inch gate valve & box (SPV.0060) | EACH | 6 | $1,829.92 | $2,200.00 | $3,000.00 | $3,000.00 | $2,226.37 | $2,445.80 |
| 96 | Special 03. fire hyrdrant (SPV.0060) | EACH | 6 | $6,665.05 | $7,200.00 | $8,000.00 | $9,400.00 | $6,610.81 | $6,567.77 |
| 97 | Special 04. temporary water service, project (SPV.0060) | EACH | 1 | $50,000 | $25,000 | $65,000 | $75,000 | $170,769 | $37,500 |
| 98 | Special 05. watermain offset (SPV.0060) | EACH | 8 | $8,405.33 | $6,800.00 | $4,500.00 | $4,900.00 | $5,716.57 | $5,434.88 |
| 99 | Special 06. 6-inch watermain tie in, station 10+26 (SPV.0060) | EACH | 1 | $6,523.52 | $5,000.00 | $4,000.00 | $4,000.00 | $4,673.03 | $3,489.60 |
| 100 | Special 07. 6-inch watermain tie in, station 100+98 (SPV.0060) | EACH | 1 | $5,155.55 | $2,800.00 | $4,200.00 | $4,500.00 | $4,327.78 | $2,215.80 |
| 101 | Special 08. 6-inch watermain tie in, station 201+52 (SPV.0060) | EACH | 1 | $5,787.55 | $3,400.00 | $4,200.00 | $4,200.00 | $4,327.78 | $2,215.80 |
| 102 | Special 09. 6-inch watermain tie in, station 202+67 (SPV.0060) | EACH | 1 | $5,787.55 | $4,275.00 | $4,500.00 | $4,800.00 | $4,327.78 | $2,215.80 |
| 103 | Special 10. 6-inch watermain tie in, station 301+64 (SPV.0060) | EACH | 1 | $5,977.54 | $4,400.00 | $4,100.00 | $4,100.00 | $4,327.78 | $2,215.80 |
| 104 | Special 11. 6-inch watermain tie in, station 400+94 (SPV.0060) | EACH | 1 | $5,977.54 | $4,451.00 | $4,000.00 | $4,000.00 | $4,327.78 | $2,215.80 |
| 105 | Special 12. 6-inch watermain tie in, station 500+75 (SPV.0060) | EACH | 1 | $5,191.57 | $2,900.00 | $4,300.00 | $4,300.00 | $4,327.78 | $2,215.80 |
| 106 | Special 13. 8-inch watermain tie in, station 501+48 (SPV.0060) | EACH | 1 | $4,945.56 | $2,600.00 | $5,000.00 | $5,000.00 | $4,425.03 | $2,313.45 |
| 107 | Special 14. mini storm cleanout (SPV.0060) | EACH | 44 | $372.98 | $925.00 | $550.00 | $650.00 | $932.48 | $670.58 |
| 108 | Special 15. remove, salvage, and reinstall sign (SPV.0060) | EACH | 12 | $350.00 | $120.00 | $130.00 | $120.00 | $350.00 | $350.00 |
| 109 | Special 01. 6-inch watermain (SPV.0090) | LF | 50 | $170.48 | $75.00 | $140.00 | $150.00 | $137.55 | $201.74 |
| 110 | Special 02. 8-inch watermain (SPV.0090) | LF | 2,350 | $103.67 | $120.00 | $110.00 | $120.00 | $108.66 | $125.40 |
| 111 | Special 03. 6-inch watermain, hydrant lead (SPV.0090) | LF | 42 | $143.41 | $100.00 | $140.00 | $150.00 | $65.10 | $137.13 |
| 112 | Special 04. copper water service 1- inch (SPV.0090) | LF | 588 | $71.59 | $95.00 | $85.00 | $90.00 | $129.50 | $149.95 |
| 113 | Special 05. mini storm sewer 6-inch (SPV.0090) | LF | 2,920 | $39.57 | $52.00 | $45.00 | $50.00 | $53.23 | $106.51 |
| 114 | Special 06. mini storm sewer lateral, 6-inch (SPV.0090) | LF | 380 | $84.78 | $92.00 | $45.00 | $50.00 | $110.19 | $265.86 |
| 115 | Special 07. sanitary sewer 8-inch PVC (SPV.0090) | LF | 971 | $93.86 | $140.00 | $105.00 | $110.00 | $118.69 | $157.99 |
| 116 | Special 08. sanitary sewer 10-inch PVC (SPV.0090) | LF | 284 | $98.38 | $155.00 | $110.00 | $120.00 | $125.85 | $229.57 |
| 117 | Special 09. sanitary sewer 12-inch PVC (SPV.0090) | LF | 684 | $103.17 | $165.00 | $120.00 | $130.00 | $155.70 | $226.32 |
| 118 | Special 10. sanitary sewer 6-inch lateral (SPV.0090) | LF | 1,520 | $102.40 | $87.00 | $95.00 | $100.00 | $143.44 | $121.23 |
| 119 | Special 11. concrete curb & gutter hes 30-inch type A (SPV.0090) | LF | 2,133 | $22.84 | $32.39 | $23.00 | $24.65 | $22.84 | $22.84 |
| 120 | Special 12. concrete curb & gutter integral hes 30-inch type D (SPV.0090) | LF | 2,117 | $12.76 | $19.57 | $13.00 | $35.50 | $12.76 | $12.76 |
| 121 | Special 01. concrete pavement hes 7-inch (SPV.0180) | SY | 6,860 | $56.13 | $62.08 | $57.00 | $65.50 | $56.13 | $56.13 |
| 122 | Special 01. sanitary manhole 48- inch (SPV.0200) | VF | 54 | $661.07 | $450.00 | $450.00 | $500.00 | $630.58 | $624.98 |
| 123 | Special 02. sanitary manhole 48- inch outside drop (SPV.0200) | VF | 11 | $740.51 | $730.00 | $825.00 | $850.00 | $890.68 | $1,015.15 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of January 13, 2026. Compiled by Mirage Metrics.