Crack and damage survey, WisDOT 999.1501.S

Low bidders on WisDOT contracts carried a median of $1,200.00 per EACH for this item, over the 24 months to 10 NOV 2026, across 18 low bids. Half of all 72 bids fell between $900.00 and $2,756.88.

Owner
Wisconsin DOT
Item
999.1501.S
Unit
EACH
Data through
10 NOV 2026

WisDOT prints this item as “Crack and Damage Survey”.

$1,200.00Low bidder's median, per EACH
$1,200.00Median of all bids, per EACH
18Contracts in the window

By year of letting

Crack and damage survey, WisDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
2022109$1,400.0032$1,400.00
202365$4,880.0019$4,880.00
20241312$1,150.0058$1,200.00
202577$1,307.6919$1,350.00
202677$1,000.0032$1,509.22

Bid prices as published, not adjusted for inflation.

By quantity

Quantity (EACH)Low bidsLow-bid median
1 to 14$1,600.00
1 to 25$1,250.00
2 to 124$2,300.00
13 to 695$1,050.00
Crack and damage survey, WisDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

Crack and damage survey, WisDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
10 NOV 202620261110017Walworth69$790.00$900.005James Peterson Sons, Inc.WisDOT
14 JUL 202620260714002Dane1$19,400$5,000.005R.G. Huston Company, Inc.WisDOT
14 APR 202620260414024Trempealeau2$4,000.00$2,763.756Lepke Trucking and Excavating, LLCWisDOT
14 APR 202620260414028Marinette2$1,000.00$2,594.492Peters Concrete CompanyWisDOT
10 FEB 202620260210018Kenosha1$1,200.00$1,259.222Musson Bros., Inc.WisDOT
10 FEB 202620260210047Dane12$900.00$900.007Integrity Grading and Excavating, Inc.WisDOT
13 JAN 202620260113054Oconto1$1,000.00$4,500.005Peters Concrete CompanyWisDOT
09 DEC 202520251209014Milwaukee3$3,600.00$3,600.003Lunda Construction CompanyWisDOT
11 NOV 202520251111018Outagamie2$1,250.00$1,000.002Lunda Construction CompanyWisDOT
08 JUL 202520250708005Calumet1$1,200.00$1,275.002Lunda Construction CompanyWisDOT
08 APR 202520250408023Pepin1$2,000.00$2,560.204James Peterson Sons, Inc.WisDOT
11 MAR 202520250311021Racine1$1,200.00$1,200.001Lunda Construction CompanyWisDOT
11 FEB 202520250211004La Crosse2$1,350.00$1,350.002Pheifer Brothers Construction Co., Inc.WisDOT
11 FEB 202520250211015Milwaukee13$1,307.69$900.005Kraemer North America, LLCWisDOT
10 DEC 202420241210014Outagamie14$1,050.00$1,050.004Michels Road & Stone, Inc.WisDOT
Latest WisDOT contracts carrying Crack and damage survey

Filter this item by your own quantity, county and period, or check your price against it, in the WisDOT explorer.

How these prices were read

WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WisDOT's own: this item is compared with WisDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the WisDOT letting of 10 NOV 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy