| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Peters Concrete Company | $2,273,927 | Low |
| 2 | Degroot, Inc. | $2,326,688 | +2.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Peters Concrete Company | 2. Degroot, Inc. |
|---|---|---|---|---|---|
| 1 | Grubbing (201.0220) | ID | 14 | $205.00 | $42.42 |
| 2 | Removing small pipe culverts (203.0100) | EACH | 1 | $300.00 | $353.50 |
| 3 | Removing concrete pavement (204.0100) | SY | 538 | $8.00 | $7.64 |
| 4 | Removing curb (204.0130) | LF | 128 | $6.00 | $5.30 |
| 5 | Removing curb & gutter (204.0150) | LF | 3,171 | $3.95 | $4.83 |
| 6 | Removing concrete sidewalk (204.0155) | SY | 1,535 | $12.75 | $6.69 |
| 7 | Removing fence (204.0170) | LF | 87 | $10.00 | $5.30 |
| 8 | Removing masonry (204.0185) | CY | 1.20 | $650.00 | $318.15 |
| 9 | Removing surface drains (204.0190) | EACH | 1 | $300.00 | $404.00 |
| 10 | Removing manholes (204.0210) | EACH | 6 | $500.00 | $505.00 |
| 11 | Removing inlets (204.0220) | EACH | 15 | $300.00 | $454.50 |
| 12 | Removing storm sewer (size) 01. 8- inch (204.0245) | LF | 173 | $20.00 | $15.15 |
| 13 | Removing storm sewer (size) 02. 12-inch (204.0245) | LF | 673 | $20.00 | $17.17 |
| 14 | Removing storm sewer (size) 03. 15-inch (204.0245) | LF | 46 | $20.00 | $18.18 |
| 15 | Removing storm sewer (size) 04. 18-inch (204.0245) | LF | 40 | $20.00 | $20.20 |
| 16 | Excavation common (205.0100) | CY | 4,750 | $22.50 | $26.80 |
| 17 | Finishing roadway (project) 01. 9995-05-73 (213.0100) | EACH | 1 | $3,000.00 | $9,595.00 |
| 18 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 6,200 | $15.95 | $55.98 |
| 19 | Drilled tie bars (416.0610) | EACH | 4 | $25.00 | $26.51 |
| 20 | Tack coat (455.0605) | GAL | 554 | $4.20 | $4.45 |
| 21 | Incentive density HMA pavement (460.2000) | DOL | 1,320 | $1.00 | $1.00 |
| 22 | HMA pavement 3 LT 58-28 S (460.5223) | TON | 1,139 | $132.40 | $104.35 |
| 23 | HMA pavement 4 LT 58-34 S (460.5244) | TON | 910 | $114.80 | $121.75 |
| 24 | Asphaltic surface driveways and field entrances (465.0120) | TON | 29 | $296.00 | $313.91 |
| 25 | Concrete collars for pipe (520.8000) | EACH | 10 | $400.00 | $2,121.00 |
| 26 | Concrete curb & gutter 18-inch type A (601.0405) | LF | 12 | $88.00 | $93.32 |
| 27 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 3,472 | $18.90 | $20.05 |
| 28 | Concrete curb pedestrian (601.0600) | LF | 10 | $75.00 | $79.54 |
| 29 | Concrete sidewalk 4-inch (602.0405) | SF | 13,807 | $6.40 | $6.79 |
| 30 | Curb ramp detectable warning field yellow (602.0505) | SF | 280 | $35.00 | $37.12 |
| 31 | Concrete driveway 6-inch (602.0810) | SY | 466 | $65.00 | $68.93 |
| 32 | Storm sewer pipe reinforced concrete class III 12-inch (608.0312) | LF | 289 | $109.25 | $67.55 |
| 33 | Storm sewer pipe reinforced concrete class III 15-inch (608.0315) | LF | 30 | $153.55 | $72.61 |
| 34 | Storm sewer pipe reinforced concrete class III 18-inch (608.0318) | LF | 401 | $103.55 | $85.32 |
| 35 | Storm sewer pipe reinforced concrete class IV 12-inch (608.0412) | LF | 203 | $95.95 | $73.56 |
| 36 | Storm sewer pipe reinforced concrete class IV 18-inch (608.0418) | LF | 381 | $85.00 | $81.21 |
| 37 | Reconstructing manholes (611.0420) | EACH | 1 | $3,075.00 | $2,777.50 |
| 38 | Manhole covers type J (611.0530) | EACH | 11 | $475.00 | $524.30 |
| 39 | Manhole covers type J-special (611.0535) | EACH | 5 | $475.00 | $542.58 |
| 40 | Inlet covers type A-S (611.0603) | EACH | 22 | $700.00 | $740.50 |
| 41 | Inlet covers type HM-S (611.0636) | EACH | 1 | $750.00 | $764.17 |
| 42 | Catch basins 3-FT diameter (611.1003) | EACH | 17 | $2,700.00 | $2,412.15 |
| 43 | Catch basins 4-FT diameter (611.1004) | EACH | 4 | $3,490.00 | $3,627.44 |
| 44 | Catch basins 5-FT diameter (611.1005) | EACH | 2 | $5,625.00 | $5,048.14 |
| 45 | Manholes 4-FT diameter (611.2004) | EACH | 8 | $4,885.00 | $4,158.11 |
| 46 | Manholes 5-FT diameter (611.2005) | EACH | 3 | $6,465.00 | $6,616.52 |
| 47 | Adjusting manhole covers (611.8110) | EACH | 2 | $650.00 | $808.00 |
| 48 | Adjusting inlet covers (611.8115) | EACH | 2 | $750.00 | $858.50 |
| 49 | Maintenance and repair of haul roads (project) 01. 9995-05-73 (618.0100) | EACH | 1 | $100.00 | $18,685 |
| 50 | Mobilization (619.1000) | EACH | 1 | $193,570 | $151,087 |
| 51 | Water (624.0100) | MGAL | 59 | $45.00 | $42.42 |
| 52 | Topsoil (625.0100) | SY | 2,208 | $14.60 | $5.30 |
| 53 | Silt fence (628.1504) | LF | 156 | $3.00 | $3.18 |
| 54 | Silt fence maintenance (628.1520) | LF | 156 | $0.01 | $1.01 |
| 55 | Mobilizations erosion control (628.1905) | EACH | 16 | $1.00 | $50.50 |
| 56 | Mobilizations emergency erosion control (628.1910) | EACH | 4 | $1.00 | $25.25 |
| 57 | Inlet protection type A (628.7005) | EACH | 22 | $97.00 | $50.50 |
| 58 | Inlet protection type B (628.7010) | EACH | 1 | $100.00 | $50.50 |
| 59 | Inlet protection type C (628.7015) | EACH | 37 | $100.00 | $50.50 |
| 60 | Seed water (630.0500) | MGAL | 48 | $1.00 | $1.01 |
| 61 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 13 | $150.00 | $95.45 |
| 62 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 1 | $185.00 | $116.66 |
| 63 | Signs type II reflective H (637.2210) | SF | 62.52 | $28.00 | $33.94 |
| 64 | Signs type II reflective F (637.2230) | SF | 34.07 | $28.00 | $33.94 |
| 65 | Removing signs type II (638.2602) | EACH | 15 | $50.00 | $26.51 |
| 66 | Removing small sign supports (638.3000) | EACH | 12 | $100.00 | $47.72 |
| 67 | Field office type C (642.5201) | EACH | 1 | $8,000.00 | $12,625 |
| 68 | Traffic control drums (643.0300) | DAY | 11,091 | $0.15 | $0.16 |
| 69 | Traffic control barricades type III (643.0420) | DAY | 6,304 | $0.45 | $0.47 |
| 70 | Traffic control warning lights type A (643.0705) | DAY | 7,678 | $0.12 | $0.13 |
| 71 | Traffic control warning lights type C (643.0715) | DAY | 1,440 | $0.12 | $0.13 |
| 72 | Traffic control signs (643.0900) | DAY | 5,803 | $0.50 | $0.54 |
| 73 | Traffic control signs PCMS (643.1050) | DAY | 28 | $25.00 | $26.51 |
| 74 | Temporary marking line paint 6- inch (643.3165) | LF | 3,410 | $0.70 | $0.75 |
| 75 | Temporary marking crosswalk paint 6-inch (643.3305) | LF | 663 | $4.80 | $5.09 |
| 76 | Temporary marking stop line paint 18-inch (643.3805) | LF | 44 | $6.05 | $6.11 |
| 77 | Traffic control (643.5000) | EACH | 1 | $34,155 | $36,221 |
| 78 | Temporary pedestrian surface matting (644.1440) | SF | 1,187 | $2.80 | $2.97 |
| 79 | Temporary pedestrian curb ramp (644.1601) | DAY | 14 | $200.00 | $212.10 |
| 80 | Temporary pedestrian detectable warning field (644.1605) | SF | 160 | $5.45 | $5.78 |
| 81 | Temporary pedestrian barricade (644.1810) | LF | 6,041 | $5.90 | $6.26 |
| 82 | Marking line epoxy 4-inch (646.1020) | LF | 170 | $1.00 | $3.13 |
| 83 | Marking line epoxy 6-inch (646.2020) | LF | 4,468 | $1.15 | $3.50 |
| 84 | Marking line epoxy 10-inch (646.4020) | LF | 75 | $1.38 | $4.35 |
| 85 | Marking arrow epoxy (646.5020) | EACH | 3 | $492.69 | $371.18 |
| 86 | Marking railroad crossing epoxy (646.5320) | EACH | 1 | $4,833.96 | $1,166.55 |
| 87 | Marking stop line epoxy 18-inch (646.6120) | LF | 115 | $20.66 | $17.77 |
| 88 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 882 | $19.59 | $12.20 |
| 89 | Construction staking storm sewer (650.4000) | EACH | 34 | $50.14 | $53.18 |
| 90 | Construction staking subgrade (650.4500) | LF | 1,945 | $1.00 | $1.01 |
| 91 | Construction staking base (650.5000) | LF | 1,945 | $0.51 | $0.55 |
| 92 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 3,494 | $0.72 | $0.77 |
| 93 | Construction staking curb ramps (650.9000) | EACH | 28 | $125.65 | $128.27 |
| 94 | Construction staking sidewalk (project) 01. 9995-05-73 (650.9500) | EACH | 1 | $1,988.21 | $2,108.27 |
| 95 | Construction staking supplemental control (project) 01. 9995-05-73 (650.9911) | EACH | 1 | $660.39 | $699.93 |
| 96 | Construction staking slope stakes (650.9920) | LF | 1,966 | $0.95 | $1.01 |
| 97 | Sawing asphalt (690.0150) | LF | 681 | $1.95 | $4.04 |
| 98 | Sawing concrete (690.0250) | LF | 445 | $2.55 | $5.05 |
| 99 | Crack and damage survey (999.1501.S) | EACH | 2 | $1,000.00 | $4,188.98 |
| 100 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,000 | $5.00 | $5.00 |
| 101 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 1,320 | $5.00 | $5.00 |
| 102 | Special 01. trench undercut (SPV.0035) | CY | 345 | $8.00 | $9.09 |
| 103 | Special 02. trench undercut backfill (SPV.0035) | CY | 345 | $15.00 | $14.14 |
| 104 | Special 01. abandoning water main (SPV.0060) | EACH | 45 | $50.00 | $126.25 |
| 105 | Special 02. abandoning water laterals (SPV.0060) | EACH | 3 | $150.00 | $252.50 |
| 106 | Special 03. removing water valve boxes (SPV.0060) | EACH | 14 | $100.00 | $202.00 |
| 107 | Special 04. removing hydrants (SPV.0060) | EACH | 3 | $1,000.00 | $858.50 |
| 108 | Special 05. salvaging hydrants (SPV.0060) | EACH | 2 | $1,200.00 | $1,212.00 |
| 109 | Special 06. 6-inch hydrant 7'-6" bury (SPV.0060) | EACH | 2 | $7,385.00 | $7,402.71 |
| 110 | Special 07. 6-inch hydrant 8' bury (SPV.0060) | EACH | 1 | $7,415.00 | $7,618.80 |
| 111 | Special 08. 6-inch hydrant 8'-6" bury (SPV.0060) | EACH | 2 | $7,550.00 | $7,785.47 |
| 112 | Special 09. 6-inch hydrant 10' bury (SPV.0060) | EACH | 1 | $8,900.00 | $8,231.76 |
| 113 | Special 10. curb stop and box 1- inch (SPV.0060) | EACH | 15 | $355.00 | $839.53 |
| 114 | Special 11. curb stop and box 2- inch (SPV.0060) | EACH | 2 | $875.00 | $1,396.61 |
| 115 | Special 12. gate valve and box 6- inch (SPV.0060) | EACH | 6 | $2,400.00 | $2,657.49 |
| 116 | Special 13. gate valve and box 8- inch (SPV.0060) | EACH | 17 | $3,350.00 | $3,548.26 |
| 117 | Special 14. service tap 1-inch (SPV.0060) | EACH | 16 | $1,350.00 | $591.05 |
| 118 | Special 15. service tap 2-inch (SPV.0060) | EACH | 2 | $1,950.00 | $1,224.50 |
| 119 | Special 16. water main tie in 6-inch (SPV.0060) | EACH | 2 | $2,960.00 | $2,892.87 |
| 120 | Special 17. water main tie in 8-inch (SPV.0060) | EACH | 5 | $4,510.00 | $2,998.29 |
| 121 | Special 18. adjusting sanitary manhole covers (SPV.0060) | EACH | 4 | $600.00 | $858.50 |
| 122 | Special 19. abandoning sanitary sewer laterals (SPV.0060) | EACH | 6 | $485.00 | $479.75 |
| 123 | Special 20. removing sanitary manholes (SPV.0060) | EACH | 3 | $615.00 | $505.00 |
| 124 | Special 21. sanitary sewer wye (SPV.0060) | EACH | 9 | $420.00 | $926.49 |
| 125 | Special 22. mini storm sewer wye 6"X4" (SPV.0060) | EACH | 13 | $75.00 | $399.76 |
| 126 | Special 23. core and seal 4-inch (SPV.0060) | EACH | 4 | $300.00 | $656.50 |
| 127 | Special 24. core and seal 6-inch (SPV.0060) | EACH | 4 | $300.00 | $757.50 |
| 128 | Special 25. reconnecting storm sewer lateral sta 23+37 (SPV.0060) | EACH | 1 | $1,815.00 | $1,355.42 |
| 129 | Special 26. adjusting water valve boxes (SPV.0060) | EACH | 1 | $300.00 | $303.00 |
| 130 | Special 01. water main class 52 ductile iron pipe with polywrap 6- inch (SPV.0090) | LF | 71 | $147.50 | $88.73 |
| 131 | Special 02. water main class 52 ductile iron pipe with polywrap 8- inch (SPV.0090) | LF | 1,615 | $148.15 | $112.20 |
| 132 | Special 03. water lateral 1-inch (SPV.0090) | LF | 493 | $106.00 | $61.01 |
| 133 | Special 04. water lateral 2-inch (SPV.0090) | LF | 83 | $149.50 | $92.58 |
| 134 | Special 05. removing sanitary sewer 8-inch (SPV.0090) | LF | 454 | $27.60 | $18.18 |
| 135 | Special 06. removing sanitary sewer 10-inch (SPV.0090) | LF | 141 | $28.00 | $18.18 |
| 136 | Special 07. sanitary sewer PVC SDR-35 8-inch (SPV.0090) | LF | 20 | $229.00 | $79.77 |
| 137 | Special 08. sanitary sewer PVC SDR-35 10-inch (SPV.0090) | LF | 579 | $127.85 | $117.26 |
| 138 | Special 09. sanitary sewer lateral PVC schedule 40 (SPV.0090) | LF | 335 | $114.25 | $58.44 |
| 139 | Special 10. mini storm sewer lateral 4-inch (SPV.0090) | LF | 132 | $68.00 | $65.55 |
| 140 | Special 11. mini storm sewer trunk 6-inch (SPV.0090) | LF | 638 | $52.60 | $42.66 |
| 141 | Special 12. salvaging and resetting landscape timbers (SPV.0090) | LF | 44 | $50.00 | $32.88 |
| 142 | Special 13. concrete curb type D special (SPV.0090) | LF | 38 | $88.00 | $93.32 |
| 143 | Special 14. water main class 52 ductile iron pipe 8-in, casing pipe 16-in, jack and bore (SPV.0090) | LF | 55 | $1,533.00 | $925.25 |
| 144 | Special 01. resetting existing brick pavers (SPV.0165) | SF | 22 | $35.00 | $106.05 |
| 145 | Special 01. hydroseeding (SPV.0180) | SY | 2,208 | $2.00 | $2.12 |
| 146 | Special 01. water main fittings (SPV.0195) | TON | 1.01 | $1.00 | $7,070.00 |
| 147 | Special 01. sanitary sewer manholes 4-FT diameter (SPV.0200) | VF | 33.30 | $740.00 | $588.81 |
| 148 | Special 02. sanitary sewer manholes 4-FT diameter with outside drop (SPV.0200) | VF | 8.60 | $1,020.00 | $780.53 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of April 14, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.