WisDOT contract 20260414028 bid tabulation

C Marinette, Madison Avenue; Hall Avenue to Lewis Street (LOC STR, Marinette County C Marinette, Madison Avenue). Let by Wisconsin DOT on April 14, 2026, Marinette. 2 bids received; low bid $2,273,927 by Peters Concrete Company.

Owner
Wisconsin DOT
Letting
14 APR 2026
Pay items
148
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Peters Concrete Company$2,273,927Low
2Degroot, Inc.$2,326,688+2.0%
WisDOT contract 20260414028: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Peters Concrete Company2. Degroot, Inc.
1Grubbing (201.0220)ID14$205.00$42.42
2Removing small pipe culverts (203.0100)EACH1$300.00$353.50
3Removing concrete pavement (204.0100)SY538$8.00$7.64
4Removing curb (204.0130)LF128$6.00$5.30
5Removing curb & gutter (204.0150)LF3,171$3.95$4.83
6Removing concrete sidewalk (204.0155)SY1,535$12.75$6.69
7Removing fence (204.0170)LF87$10.00$5.30
8Removing masonry (204.0185)CY1.20$650.00$318.15
9Removing surface drains (204.0190)EACH1$300.00$404.00
10Removing manholes (204.0210)EACH6$500.00$505.00
11Removing inlets (204.0220)EACH15$300.00$454.50
12Removing storm sewer (size) 01. 8- inch (204.0245)LF173$20.00$15.15
13Removing storm sewer (size) 02. 12-inch (204.0245)LF673$20.00$17.17
14Removing storm sewer (size) 03. 15-inch (204.0245)LF46$20.00$18.18
15Removing storm sewer (size) 04. 18-inch (204.0245)LF40$20.00$20.20
16Excavation common (205.0100)CY4,750$22.50$26.80
17Finishing roadway (project) 01. 9995-05-73 (213.0100)EACH1$3,000.00$9,595.00
18Base aggregate dense 1 1/4-inch (305.0120)TON6,200$15.95$55.98
19Drilled tie bars (416.0610)EACH4$25.00$26.51
20Tack coat (455.0605)GAL554$4.20$4.45
21Incentive density HMA pavement (460.2000)DOL1,320$1.00$1.00
22HMA pavement 3 LT 58-28 S (460.5223)TON1,139$132.40$104.35
23HMA pavement 4 LT 58-34 S (460.5244)TON910$114.80$121.75
24Asphaltic surface driveways and field entrances (465.0120)TON29$296.00$313.91
25Concrete collars for pipe (520.8000)EACH10$400.00$2,121.00
26Concrete curb & gutter 18-inch type A (601.0405)LF12$88.00$93.32
27Concrete curb & gutter 30-inch type D (601.0411)LF3,472$18.90$20.05
28Concrete curb pedestrian (601.0600)LF10$75.00$79.54
29Concrete sidewalk 4-inch (602.0405)SF13,807$6.40$6.79
30Curb ramp detectable warning field yellow (602.0505)SF280$35.00$37.12
31Concrete driveway 6-inch (602.0810)SY466$65.00$68.93
32Storm sewer pipe reinforced concrete class III 12-inch (608.0312)LF289$109.25$67.55
33Storm sewer pipe reinforced concrete class III 15-inch (608.0315)LF30$153.55$72.61
34Storm sewer pipe reinforced concrete class III 18-inch (608.0318)LF401$103.55$85.32
35Storm sewer pipe reinforced concrete class IV 12-inch (608.0412)LF203$95.95$73.56
36Storm sewer pipe reinforced concrete class IV 18-inch (608.0418)LF381$85.00$81.21
37Reconstructing manholes (611.0420)EACH1$3,075.00$2,777.50
38Manhole covers type J (611.0530)EACH11$475.00$524.30
39Manhole covers type J-special (611.0535)EACH5$475.00$542.58
40Inlet covers type A-S (611.0603)EACH22$700.00$740.50
41Inlet covers type HM-S (611.0636)EACH1$750.00$764.17
42Catch basins 3-FT diameter (611.1003)EACH17$2,700.00$2,412.15
43Catch basins 4-FT diameter (611.1004)EACH4$3,490.00$3,627.44
44Catch basins 5-FT diameter (611.1005)EACH2$5,625.00$5,048.14
45Manholes 4-FT diameter (611.2004)EACH8$4,885.00$4,158.11
46Manholes 5-FT diameter (611.2005)EACH3$6,465.00$6,616.52
47Adjusting manhole covers (611.8110)EACH2$650.00$808.00
48Adjusting inlet covers (611.8115)EACH2$750.00$858.50
49Maintenance and repair of haul roads (project) 01. 9995-05-73 (618.0100)EACH1$100.00$18,685
50Mobilization (619.1000)EACH1$193,570$151,087
51Water (624.0100)MGAL59$45.00$42.42
52Topsoil (625.0100)SY2,208$14.60$5.30
53Silt fence (628.1504)LF156$3.00$3.18
54Silt fence maintenance (628.1520)LF156$0.01$1.01
55Mobilizations erosion control (628.1905)EACH16$1.00$50.50
56Mobilizations emergency erosion control (628.1910)EACH4$1.00$25.25
57Inlet protection type A (628.7005)EACH22$97.00$50.50
58Inlet protection type B (628.7010)EACH1$100.00$50.50
59Inlet protection type C (628.7015)EACH37$100.00$50.50
60Seed water (630.0500)MGAL48$1.00$1.01
61Posts wood 4X6-inch X 14-FT (634.0614)EACH13$150.00$95.45
62Posts wood 4X6-inch X 16-FT (634.0616)EACH1$185.00$116.66
63Signs type II reflective H (637.2210)SF62.52$28.00$33.94
64Signs type II reflective F (637.2230)SF34.07$28.00$33.94
65Removing signs type II (638.2602)EACH15$50.00$26.51
66Removing small sign supports (638.3000)EACH12$100.00$47.72
67Field office type C (642.5201)EACH1$8,000.00$12,625
68Traffic control drums (643.0300)DAY11,091$0.15$0.16
69Traffic control barricades type III (643.0420)DAY6,304$0.45$0.47
70Traffic control warning lights type A (643.0705)DAY7,678$0.12$0.13
71Traffic control warning lights type C (643.0715)DAY1,440$0.12$0.13
72Traffic control signs (643.0900)DAY5,803$0.50$0.54
73Traffic control signs PCMS (643.1050)DAY28$25.00$26.51
74Temporary marking line paint 6- inch (643.3165)LF3,410$0.70$0.75
75Temporary marking crosswalk paint 6-inch (643.3305)LF663$4.80$5.09
76Temporary marking stop line paint 18-inch (643.3805)LF44$6.05$6.11
77Traffic control (643.5000)EACH1$34,155$36,221
78Temporary pedestrian surface matting (644.1440)SF1,187$2.80$2.97
79Temporary pedestrian curb ramp (644.1601)DAY14$200.00$212.10
80Temporary pedestrian detectable warning field (644.1605)SF160$5.45$5.78
81Temporary pedestrian barricade (644.1810)LF6,041$5.90$6.26
82Marking line epoxy 4-inch (646.1020)LF170$1.00$3.13
83Marking line epoxy 6-inch (646.2020)LF4,468$1.15$3.50
84Marking line epoxy 10-inch (646.4020)LF75$1.38$4.35
85Marking arrow epoxy (646.5020)EACH3$492.69$371.18
86Marking railroad crossing epoxy (646.5320)EACH1$4,833.96$1,166.55
87Marking stop line epoxy 18-inch (646.6120)LF115$20.66$17.77
88Marking crosswalk epoxy transverse line 6-inch (646.7420)LF882$19.59$12.20
89Construction staking storm sewer (650.4000)EACH34$50.14$53.18
90Construction staking subgrade (650.4500)LF1,945$1.00$1.01
91Construction staking base (650.5000)LF1,945$0.51$0.55
92Construction staking curb gutter and curb & gutter (650.5500)LF3,494$0.72$0.77
93Construction staking curb ramps (650.9000)EACH28$125.65$128.27
94Construction staking sidewalk (project) 01. 9995-05-73 (650.9500)EACH1$1,988.21$2,108.27
95Construction staking supplemental control (project) 01. 9995-05-73 (650.9911)EACH1$660.39$699.93
96Construction staking slope stakes (650.9920)LF1,966$0.95$1.01
97Sawing asphalt (690.0150)LF681$1.95$4.04
98Sawing concrete (690.0250)LF445$2.55$5.05
99Crack and damage survey (999.1501.S)EACH2$1,000.00$4,188.98
100On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS2,000$5.00$5.00
101On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS1,320$5.00$5.00
102Special 01. trench undercut (SPV.0035)CY345$8.00$9.09
103Special 02. trench undercut backfill (SPV.0035)CY345$15.00$14.14
104Special 01. abandoning water main (SPV.0060)EACH45$50.00$126.25
105Special 02. abandoning water laterals (SPV.0060)EACH3$150.00$252.50
106Special 03. removing water valve boxes (SPV.0060)EACH14$100.00$202.00
107Special 04. removing hydrants (SPV.0060)EACH3$1,000.00$858.50
108Special 05. salvaging hydrants (SPV.0060)EACH2$1,200.00$1,212.00
109Special 06. 6-inch hydrant 7'-6" bury (SPV.0060)EACH2$7,385.00$7,402.71
110Special 07. 6-inch hydrant 8' bury (SPV.0060)EACH1$7,415.00$7,618.80
111Special 08. 6-inch hydrant 8'-6" bury (SPV.0060)EACH2$7,550.00$7,785.47
112Special 09. 6-inch hydrant 10' bury (SPV.0060)EACH1$8,900.00$8,231.76
113Special 10. curb stop and box 1- inch (SPV.0060)EACH15$355.00$839.53
114Special 11. curb stop and box 2- inch (SPV.0060)EACH2$875.00$1,396.61
115Special 12. gate valve and box 6- inch (SPV.0060)EACH6$2,400.00$2,657.49
116Special 13. gate valve and box 8- inch (SPV.0060)EACH17$3,350.00$3,548.26
117Special 14. service tap 1-inch (SPV.0060)EACH16$1,350.00$591.05
118Special 15. service tap 2-inch (SPV.0060)EACH2$1,950.00$1,224.50
119Special 16. water main tie in 6-inch (SPV.0060)EACH2$2,960.00$2,892.87
120Special 17. water main tie in 8-inch (SPV.0060)EACH5$4,510.00$2,998.29
121Special 18. adjusting sanitary manhole covers (SPV.0060)EACH4$600.00$858.50
122Special 19. abandoning sanitary sewer laterals (SPV.0060)EACH6$485.00$479.75
123Special 20. removing sanitary manholes (SPV.0060)EACH3$615.00$505.00
124Special 21. sanitary sewer wye (SPV.0060)EACH9$420.00$926.49
125Special 22. mini storm sewer wye 6"X4" (SPV.0060)EACH13$75.00$399.76
126Special 23. core and seal 4-inch (SPV.0060)EACH4$300.00$656.50
127Special 24. core and seal 6-inch (SPV.0060)EACH4$300.00$757.50
128Special 25. reconnecting storm sewer lateral sta 23+37 (SPV.0060)EACH1$1,815.00$1,355.42
129Special 26. adjusting water valve boxes (SPV.0060)EACH1$300.00$303.00
130Special 01. water main class 52 ductile iron pipe with polywrap 6- inch (SPV.0090)LF71$147.50$88.73
131Special 02. water main class 52 ductile iron pipe with polywrap 8- inch (SPV.0090)LF1,615$148.15$112.20
132Special 03. water lateral 1-inch (SPV.0090)LF493$106.00$61.01
133Special 04. water lateral 2-inch (SPV.0090)LF83$149.50$92.58
134Special 05. removing sanitary sewer 8-inch (SPV.0090)LF454$27.60$18.18
135Special 06. removing sanitary sewer 10-inch (SPV.0090)LF141$28.00$18.18
136Special 07. sanitary sewer PVC SDR-35 8-inch (SPV.0090)LF20$229.00$79.77
137Special 08. sanitary sewer PVC SDR-35 10-inch (SPV.0090)LF579$127.85$117.26
138Special 09. sanitary sewer lateral PVC schedule 40 (SPV.0090)LF335$114.25$58.44
139Special 10. mini storm sewer lateral 4-inch (SPV.0090)LF132$68.00$65.55
140Special 11. mini storm sewer trunk 6-inch (SPV.0090)LF638$52.60$42.66
141Special 12. salvaging and resetting landscape timbers (SPV.0090)LF44$50.00$32.88
142Special 13. concrete curb type D special (SPV.0090)LF38$88.00$93.32
143Special 14. water main class 52 ductile iron pipe 8-in, casing pipe 16-in, jack and bore (SPV.0090)LF55$1,533.00$925.25
144Special 01. resetting existing brick pavers (SPV.0165)SF22$35.00$106.05
145Special 01. hydroseeding (SPV.0180)SY2,208$2.00$2.12
146Special 01. water main fittings (SPV.0195)TON1.01$1.00$7,070.00
147Special 01. sanitary sewer manholes 4-FT diameter (SPV.0200)VF33.30$740.00$588.81
148Special 02. sanitary sewer manholes 4-FT diameter with outside drop (SPV.0200)VF8.60$1,020.00$780.53
WisDOT contract 20260414028: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of April 14, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy