WisDOT contract 20250211015 bid tabulation

2190-10-70. Let by Wisconsin DOT on February 11, 2025, Milwaukee. 5 bids received; low bid $6,896,863 by Kraemer North America, LLC.

Owner
Wisconsin DOT
Letting
11 FEB 2025
Pay items
269
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Kraemer North America, LLC$6,896,863Low
2Lunda Construction Company$7,030,266+2.0%
3Vinton Construction Company$7,216,676+5.0%
4Zignego Company, Inc.$7,389,699+7.0%
5Zenith Tech., Inc. - Waukesha$7,550,858+9.0%
WisDOT contract 20250211015: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Kraemer North America, LLC2. Lunda Construction Company3. Vinton Construction Company4. Zignego Company, Inc.5. Zenith Tech., Inc. - Waukesha
1Grubbing (201.0210)SY1,872$1.29$1.29$1.29$1.29$5.30
2Grubbing (201.0220)ID186$10.99$10.99$10.99$10.99$5.30
3Removing structure over waterway debris capture (structure) 01. P-40- 776 (203.0270)EACH1$250,000$235,000$235,000$235,000$90,170
4Removing concrete pavement (204.0100)SY3,598$5.00$5.00$7.65$5.26$5.00
5Removing asphaltic surface milling (204.0120)SY669$9.50$9.50$9.50$9.50$9.50
6Removing curb & gutter (204.0150)LF639$3.00$3.00$5.20$10.00$3.00
7Removing concrete sidewalk (204.0155)SY555$7.00$7.00$6.00$10.00$7.00
8Removing concrete bases (204.0195)EACH5$500.00$500.00$500.00$500.00$229.00
9Removing manholes (204.0210)EACH3$343.00$343.00$840.00$343.00$343.00
10Removing catch basins (204.0215)EACH7$226.00$226.00$475.00$226.00$226.00
11Removing storm sewer (size) 04. 12-inch (204.0245)LF174$13.00$13.00$23.00$13.00$13.00
12Removing storm sewer (size) 05. 18-inch (204.0245)LF151$13.00$13.00$26.00$13.00$13.00
13Removing storm sewer (size) 06. 24-inch (204.0245)LF101$15.00$15.00$30.00$15.00$15.00
14Sealing pipes (204.0280)EACH1$515.00$515.00$2,650.00$515.00$515.00
15Abandoning sewer (204.0291.S)CY20$702.00$702.00$275.00$702.00$702.00
16Removing (item description) 01. lighting units (204.9060.S)EACH2$679.80$679.80$679.80$679.80$679.80
17Excavation common (205.0100)CY1,832$7.00$7.00$23.19$37.00$7.00
18Excavation for structures bridges (structure) 01. B-40-1033 (206.1001)EACH1$102,458$102,458$127,000$306,000$102,458
19Cofferdams (structure) 01. B-40- 1033 (206.5001)EACH1$29,974$5,000.00$0.01$150,000$37,174
20Borrow (208.0100)CY760$4.00$4.00$0.01$0.01$4.00
21Backfill granular grade 1 (209.1100)CY1,525$37.00$37.00$47.65$40.00$37.00
22Backfill granular grade 2 (209.2100)CY1,487$36.00$36.00$41.00$40.00$36.00
23Backfill structure type A (210.1500)TON1,427$24.00$24.00$28.30$40.00$24.00
24Finishing roadway (project) 01. 2190-10-70 (213.0100)EACH1$2,500.00$500.00$5,000.00$1,000.00$2,771.32
25Base aggregate dense 1 1/4-inch (305.0120)TON3,109$21.00$21.00$22.72$24.50$21.00
26Base aggregate open-graded (310.0110)TON34$26.00$26.00$39.35$100.00$26.00
27Coloring concrete wisdot red (405.0100)CY15$300.00$300.00$167.78$200.00$167.78
28Concrete pavement 8-inch (415.0080)SY1,787$64.50$64.50$66.55$82.00$66.55
29Drilled tie bars (416.0610)EACH146$15.00$15.00$13.73$30.00$13.73
30Drilled dowel bars (416.0620)EACH117$25.00$25.00$17.95$30.00$17.95
31Tack coat (455.0605)GAL507$3.00$3.00$3.00$3.00$3.00
32Incentive density HMA pavement (460.2000)DOL580$1.00$1.00$1.00$1.00$1.00
33HMA pavement 3 MT 58-28 S (460.6223)TON517$87.00$87.00$87.00$87.00$87.00
34HMA pavement 4 MT 58-28 S (460.6224)TON382$94.00$94.00$94.00$94.00$94.00
35Asphaltic surface (465.0105)TON49$225.00$225.00$225.00$225.00$225.00
36Concrete masonry bridges (502.0100)CY1,020$1,100.00$925.00$925.00$925.00$903.58
37Protective surface treatment (502.3200)SY394$3.00$5.00$5.00$5.00$4.25
38Pigmented surface sealer (502.3210)SY73$11.00$11.00$11.00$11.00$12.84
39Bar steel reinforcement HS structures (505.0400)LB37,460$1.30$1.12$1.12$1.12$1.26
40Bar steel reinforcement HS coated structures (505.0600)LB113,460$1.45$1.25$1.25$1.25$1.40
41Railing pipe (513.2001)LF21$450.00$500.00$500.00$500.00$609.33
42Railing steel pedestrian type C2 (513.8011)LF48$450.00$400.00$400.00$400.00$439.02
43Rubberized membrane waterproofing (516.0500)SY68$10.00$35.00$35.00$35.00$66.70
44Sheet membrane waterproofing for buried structures 01. B-40-1033 (516.0610.S)SY370$78.22$135.00$175.00$50.00$46.93
45Concrete collars for pipe (520.8000)EACH1$914.00$914.00$1,430.00$914.00$914.00
46Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012)EACH1$1,081.00$1,081.00$1,080.00$1,081.00$1,081.00
47Apron endwalls for culvert pipe reinforced concrete 18-inch (522.1018)EACH2$1,197.00$1,197.00$1,275.00$1,197.00$1,197.00
48Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024)EACH1$1,505.00$1,505.00$1,580.00$1,505.00$1,505.00
49Apron endwalls for culvert pipe reinforced concrete 30-inch (522.1030)EACH1$1,705.00$1,705.00$2,035.00$1,705.00$1,705.00
50Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 34X53-inch (522.2634)EACH1$2,736.00$2,736.00$3,100.00$2,736.00$2,736.00
51Pre-boring rock or consolidated materials (550.0020)LF4,230$88.00$115.00$115.00$115.00$124.57
52Piling steel HP 12-inch X 53 LB (550.1120)LF4,230$40.00$35.00$35.00$35.00$35.01
53Concrete curb & gutter 19-inch (601.0319)LF25$110.00$110.00$43.17$100.00$43.17
54Concrete curb & gutter 31-inch (601.0331)LF1,281$26.00$26.00$33.63$50.00$31.63
55Concrete sidewalk 5-inch (602.0410)SF4,728$8.00$8.00$8.95$9.50$8.55
56Curb ramp detectable warning field natural patina (602.0515)SF112$55.00$55.00$23.59$50.00$23.59
57Concrete driveway 7-inch (602.0815)SY164$65.00$65.00$76.26$100.00$75.26
58Riprap light (606.0100)CY342$110.00$110.00$129.20$150.00$110.00
59Riprap medium (606.0200)CY43$116.00$116.00$129.20$150.00$116.00
60Riprap heavy (606.0300)CY20$147.00$147.00$129.20$150.00$147.00
61Storm sewer pipe reinforced concrete class III 18-inch (608.0318)LF120$107.00$107.00$126.00$107.00$107.00
62Storm sewer pipe reinforced concrete class III 24-inch (608.0324)LF238$152.00$152.00$188.00$152.00$152.00
63Storm sewer pipe reinforced concrete class III 30-inch (608.0330)LF140$204.00$204.00$242.00$204.00$204.00
64Storm sewer pipe reinforced concrete class III 42-inch (608.0342)LF96$303.00$303.00$391.80$303.00$303.00
65Storm sewer pipe reinforced concrete class V 12-inch (608.0512)LF148$107.00$107.00$115.40$107.00$107.00
66Storm sewer pipe reinforced concrete class V 15-inch (608.0515)LF116$133.00$133.00$132.80$133.00$133.00
67Storm sewer pipe reinforced concrete class V 18-inch (608.0518)LF39$106.00$106.00$153.00$106.00$106.00
68Storm sewer pipe reinforced concrete class V 24-inch (608.0524)LF78$142.00$142.00$189.30$142.00$142.00
69Storm sewer pipe reinforced concrete class V 30-inch (608.0530)LF33$244.00$244.00$276.20$244.00$244.00
70Storm sewer pipe reinforced concrete horizontal elliptical class HE-III 34X53-inch (608.2334)LF26$338.00$338.00$426.60$338.00$338.00
71Inlet covers type B (611.0606)EACH4$1,353.00$1,353.00$776.00$1,353.00$1,353.00
72Inlet covers type C (611.0612)EACH1$1,054.00$1,054.00$537.00$1,054.00$1,054.00
73Inlet covers type MS (611.0642)EACH1$601.00$601.00$525.00$601.00$601.00
74Manholes 4-FT diameter (611.2004)EACH2$3,931.00$3,931.00$5,520.00$3,931.00$3,931.00
75Manholes 5-FT diameter (611.2005)EACH2$6,137.00$6,137.00$7,305.00$6,137.00$6,137.00
76Manholes 6-FT diameter (611.2006)EACH2$10,220$10,220$10,335$10,220$10,220
77Manholes 7-FT diameter (611.2007)EACH1$12,327$12,327$13,625$12,327$12,327
78Inlets 4-FT diameter (611.3004)EACH6$2,941.00$2,941.00$4,825.00$2,941.00$2,941.00
79Inlets 2X2-FT (611.3220)EACH4$1,102.00$1,102.00$2,615.00$1,102.00$1,102.00
80Inlets median 1 grate (611.3901)EACH1$4,298.00$4,298.00$4,565.00$4,298.00$4,298.00
81Pipe underdrain 6-inch (612.0106)LF400$5.00$5.00$20.70$50.00$5.00
82Pipe underdrain unperforated 4- inch (612.0204)LF100$5.00$5.00$10.00$50.00$5.00
83Pipe underdrain unperforated 6- inch (612.0206)LF53$6.00$6.00$10.00$50.00$6.00
84Pipe underdrain wrapped 4-inch (612.0404)LF200$5.00$5.00$17.12$50.00$5.00
85Pipe underdrain wrapped 6-inch (612.0406)LF245$6.00$6.00$6.60$50.00$6.00
86Apron endwalls for underdrain reinforced concrete 4-inch (612.0804)EACH4$295.00$295.00$360.00$100.00$295.00
87Apron endwalls for underdrain reinforced concrete 6-inch (612.0806)EACH2$295.00$295.00$400.00$100.00$295.00
88Fence safety (616.0700.S)LF1,760$3.20$3.24$3.20$3.35$3.25
89Maintenance and repair of haul roads (project) 01. 2190-10-70 (618.0100)EACH1$1,000.00$100.00$0.01$1.00$3,840.85
90Mobilization (619.1000)EACH1$739,900$1,096,114$963,500$677,000$1,632,000
91Dust control surface treatment (623.0200)SY6,063$0.01$0.01$0.01$0.01$0.01
92Water (624.0100)MGAL17$421.00$421.00$40.00$200.00$421.00
93Topsoil (625.0100)SY5,373$6.00$6.30$4.79$4.95$6.00
94Mulching (627.0200)SY5,373$0.60$0.60$0.60$0.40$0.60
95Erosion bales (628.1104)EACH303$14.00$14.00$14.00$11.00$14.00
96Silt fence (628.1504)LF1,694$2.14$2.14$2.14$1.95$2.14
97Silt fence maintenance (628.1520)LF1,694$0.01$0.01$0.01$0.01$0.01
98Mobilizations erosion control (628.1905)EACH6$50.00$50.00$50.00$100.00$50.00
99Mobilizations emergency erosion control (628.1910)EACH16$1.00$1.00$1.00$100.00$1.00
100Erosion mat urban class I type A (628.2006)SY1,090$2.14$2.14$2.14$1.70$2.14
101Erosion mat class II type C (628.2027)SY898$3.90$3.90$3.90$3.95$3.90
102Soil stabilizer type B (628.6510)ACRE1$800.00$800.00$800.00$775.00$800.00
103Inlet protection type B (628.7010)EACH8$700.00$70.00$70.00$50.00$70.00
104Inlet protection type D (628.7020)EACH54$126.00$126.00$126.00$70.00$126.00
105Culvert pipe checks (628.7555)EACH2$30.00$30.00$30.00$18.00$30.00
106Tracking pads (628.7560)EACH4$1,651.00$1,651.00$0.01$1.00$1,651.00
107Fertilizer type B (629.0210)CWT4$80.00$80.00$80.00$80.00$80.00
108Seeding mixture no. 40 (630.0140)LB20$14.00$14.00$14.00$12.00$14.00
109Seeding mixture no. 75 (630.0175)LB7$140.00$140.00$140.00$95.00$140.00
110Seeding temporary (630.0200)LB147$2.90$2.90$2.90$2.95$2.90
111Seeding nurse crop (630.0400)LB8$4.00$4.00$4.00$7.95$4.00
112Seed water (630.0500)MGAL182$5.00$5.00$5.00$12.00$5.00
113Sod water (631.0300)MGAL1,369$5.00$5.00$5.00$0.01$5.00
114Sod lawn (631.1000)SY3,388$6.53$6.53$6.53$6.95$6.53
115Markers culvert end (633.5200)EACH6$70.00$70.00$70.00$60.00$70.00
116Posts tubular steel 2X2-inch X 14- FT (634.0814)EACH2$220.00$220.00$220.00$210.00$220.00
117Signs type II reflective H (637.2210)SF5$28.00$28.00$28.00$23.00$28.00
118Signs type II reflective H folding (637.2215)SF20.72$28.00$28.00$28.00$29.00$28.00
119Signs type II reflective F (637.2230)SF42$24.00$24.00$24.00$23.00$24.00
120Moving signs type II (638.2102)EACH2$80.00$80.00$80.00$80.00$80.00
121Removing signs type II (638.2602)EACH1$15.00$15.00$15.00$35.00$15.00
122Erecting state owned signs type II (638.3620)EACH4$70.00$70.00$70.00$75.00$70.00
123Field office type C (642.5201)EACH1$34,787$8,000.00$20,000$30,000$21,000
124Traffic control drums (643.0300)DAY5,490$0.22$0.22$0.22$0.22$0.22
125Traffic control barricades type III (643.0420)DAY11,310$0.41$0.41$0.41$0.41$0.41
126Traffic control warning lights type A (643.0705)DAY22,620$0.07$0.07$0.07$0.07$0.07
127Traffic control warning lights type C (643.0715)DAY147$0.50$0.50$0.50$0.50$0.50
128Traffic control arrow boards (643.0800)DAY14$41.50$41.50$41.50$41.50$41.50
129Traffic control signs (643.0900)DAY41,108$0.16$0.16$0.16$0.16$0.16
130Traffic control covering signs type II (643.0920)EACH5$50.00$50.00$50.00$50.00$50.00
131Traffic control signs fixed message (643.1000)SF253.50$12.50$12.50$12.50$12.50$12.50
132Traffic control signs PCMS (643.1050)DAY28$35.00$35.00$35.00$35.00$35.00
133Traffic control cones 42-inch (643.1070)DAY794$0.50$0.50$0.50$0.50$0.50
134Temporary marking line removable tape 4-inch (643.3150)LF890$2.65$2.65$2.65$2.65$2.65
135Temporary marking removable mask out tape 12-inch (643.3990)LF360$4.75$4.75$4.75$4.75$4.75
136Traffic control (643.5000)EACH1$2,000.00$2,000.00$2,000.00$2,000.00$2,000.00
137Geotextile type DF schedule A (645.0111)SY1,006$3.00$3.00$4.40$2.00$3.00
138Geotextile type HR (645.0120)SY25$5.00$5.00$10.00$10.00$5.00
139Geotextile type R (645.0130)SY827$2.00$2.00$3.50$5.00$2.00
140Geogrid type SR (645.0220)SY325$2.00$2.00$5.00$5.00$2.00
141Marking line epoxy 4-inch (646.1020)LF4,993$0.97$1.45$0.97$1.28$0.45
142Marking line epoxy 8-inch (646.3020)LF164$6.25$2.80$6.25$1.56$1.14
143Marking arrow epoxy (646.5020)EACH2$200.00$360.00$200.00$325.00$378.57
144Marking stop line epoxy 12-inch (646.6020)LF270$9.35$15.25$9.35$11.10$15.46
145Marking stop line epoxy 18-inch (646.6120)LF95$12.50$18.00$12.50$18.60$16.20
146Marking crosswalk epoxy transverse line 6-inch (646.7420)LF107$10.50$14.00$10.50$8.25$15.00
147Marking crosswalk epoxy block style 24-inch (646.7520)LF224$18.75$20.00$18.75$21.50$26.15
148Marking removal line water blasting 4-inch (646.9010)LF300$1.10$1.10$1.00$1.10$1.10
149Marking removal line water blasting 8-inch (646.9110)LF60$2.70$2.70$1.75$2.70$2.70
150Marking removal line water blasting wide (646.9210)LF22$7.50$7.50$2.50$7.50$7.50
151Marking removal special marking water blasting (646.9310)EACH2$145.00$145.00$175.00$145.00$145.00
152Construction staking storm sewer (650.4000)EACH50$125.00$125.00$125.00$105.00$125.00
153Construction staking base (650.5000)LF815$2.25$2.25$2.25$1.50$2.25
154Construction staking curb gutter and curb & gutter (650.5500)LF954$1.50$1.50$1.50$2.00$1.50
155Construction staking structure layout (structure) 01. B-40-1033 (650.6501)EACH1$3,500.00$3,500.00$3,500.00$3,500.00$3,500.00
156Construction staking concrete pavement (650.7000)LF566$2.00$2.00$2.00$3.00$2.00
157Construction staking resurfacing reference (650.8000)LF338$1.00$0.01$0.01$1.00$0.01
158Construction staking electrical installations (project) 01. 2190-10- 70 (650.8501)EACH1$1,500.00$1,500.00$1,500.00$600.00$1,500.00
159Construction staking curb ramps (650.9000)EACH8$125.00$125.00$125.00$200.00$125.00
160Construction staking sidewalk (project) 01. 2190-10-70 (650.9500)EACH1$1,500.00$1,500.00$1,500.00$750.00$1,500.00
161Construction staking supplemental control (project) 01. 2190-10-70 (650.9911)EACH1$1,000.00$1,000.00$1,000.00$1,500.00$1,000.00
162Construction staking slope stakes (650.9920)LF1,524$0.70$0.70$0.70$0.75$0.70
163Conduit rigid metallic 2-inch (652.0125)LF120$103.38$103.38$103.38$103.38$103.38
164Conduit rigid nonmetallic schedule 40 1 1/4-inch (652.0215)LF374$7.27$7.27$7.27$7.27$7.27
165Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF1,894$8.68$8.68$8.68$8.68$8.68
166Conduit rigid nonmetallic schedule 40 3-inch (652.0235)LF783$11.48$11.48$11.48$11.48$11.48
167Pull boxes steel 24X36-inch (653.0135)EACH5$1,207.50$1,207.50$1,207.50$1,207.50$1,207.50
168Pull boxes steel 24X42-inch (653.0140)EACH10$1,303.40$1,303.40$1,303.40$1,303.40$1,303.40
169Junction boxes 18X12X6-inch (653.0222)EACH8$1,685.00$1,685.00$1,685.00$1,685.00$1,685.00
170Concrete bases type 1 (654.0101)EACH7$987.00$987.00$987.00$987.00$987.00
171Concrete bases type 10 (654.0110)EACH4$6,278.00$6,278.00$6,278.00$6,278.00$6,278.00
172Concrete control cabinet bases type 9 special (654.0217)EACH1$3,038.00$3,038.00$3,038.00$3,038.00$3,038.00
173Cable traffic signal 5-14 AWG (655.0230)LF469$1.56$1.56$1.56$1.56$1.56
174Cable traffic signal 7-14 AWG (655.0240)LF341$2.15$2.15$2.15$2.15$2.15
175Cable traffic signal 12-14 AWG (655.0260)LF1,162$3.24$3.24$3.24$3.24$3.24
176Cable type UF 2-10 AWG grounded (655.0320)LF527$2.44$2.44$2.44$2.44$2.44
177Electrical wire traffic signals 10 AWG (655.0515)LF642$1.29$1.29$1.29$1.29$1.29
178Electrical wire lighting 12 AWG (655.0610)LF804$0.77$0.77$0.77$0.77$0.77
179Electrical wire lighting 10 AWG (655.0615)LF300$1.39$1.39$1.39$1.39$1.39
180Electrical wire lighting 8 AWG (655.0620)LF568$1.64$1.64$1.64$1.64$1.64
181Electrical wire lighting 4 AWG (655.0630)LF4,516$2.58$2.58$2.58$2.58$2.58
182Traffic signal evp detector cable (655.0900)LF577$1.56$1.56$1.56$1.56$1.56
183Electrical service meter breaker pedestal (location) 01. W wisconsin ave & honey creek pkwy (656.0201)EACH1$1,460.00$1,460.00$1,460.00$1,460.00$1,460.00
184Pedestal bases (657.0100)EACH7$261.00$261.00$261.00$261.00$261.00
185Traffic signal standards aluminum 3.5-FT (657.0405)EACH3$230.00$230.00$230.00$230.00$230.00
186Traffic signal standards aluminum 13-FT (657.0420)EACH4$547.50$547.50$547.50$547.50$547.50
187Traffic signal face 3S 12-inch (658.0173)EACH12$822.00$822.00$822.00$822.00$822.00
188Pedestrian signal face 16-inch (658.0416)EACH8$660.00$660.00$660.00$660.00$660.00
189Signal mounting hardware (location) 01. W wisconsin ave & honey creek pkwy (658.5070)EACH1$4,938.00$4,938.00$4,938.00$4,938.00$4,938.00
190Lamp, ballast, LED, switch disposal by contractor (659.5000.S)EACH2$22.00$22.00$22.00$22.00$22.00
191Communication vault type 1 (673.0105)EACH3$3,597.00$3,597.00$3,597.00$3,597.00$3,597.00
192Tracer wire marker posts (673.0200)EACH2$189.00$189.00$189.00$189.00$189.00
193Sawing asphalt (690.0150)LF157$1.75$1.75$1.75$1.75$1.15
194Sawing concrete (690.0250)LF2,133$2.00$2.00$2.00$2.00$2.25
195Incentive strength concrete structures (715.0502)DOL6,120$1.00$1.00$1.00$1.00$1.00
196Incentive compressive strength concrete pavement (715.0720)DOL541$1.00$1.00$1.00$1.00$1.00
197Crack and damage survey (999.1501.S)EACH13$1,307.69$900.00$900.00$900.00$1,630.77
198Special 01. streambed stone (SPV.0035)CY1,509$106.00$106.00$125.00$150.00$106.00
199Special 02. streambed granular fill (SPV.0035)CY378$66.00$66.00$96.00$150.00$66.00
200Special 03. filter gravel (SPV.0035)CY369$63.00$63.00$94.00$150.00$63.00
201Special 04. pea gravel (SPV.0035)CY378$47.00$47.00$100.00$70.00$47.00
202Special 05. reinforced concrete cutoff wall (SPV.0035)CY18$2,200.00$750.00$750.00$750.00$3,142.44
203Special 03. reconstruct MMSD manhole (SPV.0060)EACH4$3,527.00$3,527.00$5,045.00$3,527.00$3,527.00
204Special 04. abandon MMSD pump station BS0401 (SPV.0060)EACH1$58,843$58,843$39,450$58,843$57,393
205Special 05. exposing MMSD mis (SPV.0060)EACH3$1,570.60$4,000.00$3,350.00$20,000$2,500.00
206Special 06. exposing at&T duct package (SPV.0060)EACH3$4,713.38$4,000.00$3,350.00$1,000.00$5,000.00
207Special 07. adjusting sanitary manholes (SPV.0060)EACH2$1,658.00$1,658.00$1,175.00$1,658.00$1,658.00
208Special 08. reconstructing sanitary manholes (SPV.0060)EACH3$3,218.00$3,218.00$4,715.00$3,218.00$3,218.00
209Special 09. concrete base special (SPV.0060)EACH1$3,283.50$3,283.50$3,283.50$3,283.50$3,283.50
210Special 30. outlet structure 63 (SPV.0060)EACH1$25,000$16,000$16,758$16,000$32,546
211Special 31. 24"X72" catch basin (SPV.0060)EACH7$5,275.00$5,275.00$6,675.00$5,275.00$5,275.00
212Special 32. 30"X72" catch basin (SPV.0060)EACH12$8,200.00$8,200.00$8,435.00$8,200.00$8,200.00
213Special 33. 24"X72" riser inlet (SPV.0060)EACH7$11,629$11,629$5,735.00$11,629$11,629
214Special 34. manhole 4-FT riser (SPV.0060)EACH2$1,588.00$1,588.00$5,010.00$1,588.00$1,588.00
215Special 35. inlet cover R-3246-AL (SPV.0060)EACH6$1,692.00$1,692.00$1,045.00$1,692.00$1,692.00
216Special 36. inlet cover R-3293-2 (SPV.0060)EACH12$2,745.00$2,745.00$1,890.00$2,745.00$2,745.00
217Special 37. inlet cover R-3295-2(L) (SPV.0060)EACH14$2,372.00$2,372.00$1,645.00$2,372.00$2,372.00
218Special 38. manhole cover R-1661- B (SPV.0060)EACH8$1,522.00$1,522.00$985.00$1,522.00$1,522.00
219Special 40. hydrant assembly (SPV.0060)EACH2$8,927.00$8,927.00$7,010.00$8,927.00$8,927.00
220Special 41. gate valve & valve box 6-inch (SPV.0060)EACH2$3,014.00$3,014.00$2,670.00$3,014.00$3,014.00
221Special 42. gate valve & valve box 8-inch (SPV.0060)EACH2$4,026.00$4,026.00$3,540.00$4,026.00$4,026.00
222Special 43. butterfly valve & valve box 16-inch (SPV.0060)EACH5$412.00$412.00$2,205.00$412.00$412.00
223Special 44. water testing manhole (SPV.0060)EACH1$12,159$12,159$7,820.00$12,159$12,159
224Special 45. air release valve (SPV.0060)EACH1$2,916.00$2,916.00$2,635.00$2,916.00$2,916.00
225Special 50. remove and salvage existing lighting units (SPV.0060)EACH3$679.80$679.80$679.80$679.80$679.80
226Special 51. luminaire LED medium (SPV.0060)EACH6$322.20$322.20$322.20$322.20$322.20
227Special 52. install concrete pole (SPV.0060)EACH2$1,139.00$1,139.00$1,139.00$1,139.00$1,139.00
228Special 53. install milwaukee county furnished pull box 12X12X12-inch (SPV.0060)EACH2$437.50$437.50$437.50$437.50$437.50
229Special 54. wood pole 60-foot (SPV.0060)EACH4$1,574.00$1,574.00$1,574.00$1,574.00$1,574.00
230Special 55. removing 60-foot wood pole (SPV.0060)EACH4$1,139.00$1,139.00$1,139.00$1,139.00$1,139.00
231Special 61. retroreflective backplate 3S (SPV.0060)EACH12$160.00$160.00$160.00$160.00$160.00
232Special 62. furn & ins traf sig cab & CTRL at WI ave & honey CR pkwy (SPV.0060)EACH1$27,337$27,337$27,337$27,337$27,337
233Special 63. furn & ins access ped push button sys at WI ave & honey CR pkwy (SPV.0060)EACH1$11,195$11,195$11,195$11,195$11,195
234Special 64. furn & ins emerg veh preemption sys at WI ave & honey CR pkwy (SPV.0060)EACH1$8,802.50$8,802.50$8,802.50$8,802.50$8,802.50
235Special 65. battery backup sys for traffic intersection at WI ave & honey CR pkwy (SPV.0060)EACH1$12,457$12,457$12,457$12,457$12,457
236Special 66. non-intrusive vehicle detection system (SPV.0060)EACH1$36,996$36,996$36,996$36,996$36,996
237Special 68. transport & install city furnished poles type 10 (SPV.0060)EACH4$1,374.30$1,374.30$1,374.30$1,374.30$1,374.30
238Special 70. transport & install city furnished monotube arms 20-FT (SPV.0060)EACH3$3,057.80$3,057.80$3,057.80$3,057.80$3,057.80
239Special 71. transport & install city furnished monotube arms 25-FT (SPV.0060)EACH1$3,170.00$3,170.00$3,170.00$3,170.00$3,170.00
240Special 72. transport & install city furnished luminaire arms steel 15- FT (SPV.0060)EACH4$414.00$414.00$414.00$414.00$414.00
241Special 80. junction boxes 18X6X6- inch special watertight (SPV.0060)EACH4$1,764.00$1,764.00$1,764.00$1,764.00$1,764.00
242Special 82. salvaging stone P-40- 776 (SPV.0060)EACH1$40,800$6,000.00$6,000.00$6,000.00$40,800
243Special 01. pavement cleanup project 2190-10-70 (SPV.0075)HRS40$260.00$260.00$260.00$260.00$260.00
244Special 02. boulder obstructions (SPV.0075)HRS8$2,000.00$2,000.00$2,000.00$2,000.00$2,000.00
245Special 01. concrete curb & gutter integral 31-inch (SPV.0090)LF350$31.50$31.50$32.25$60.00$32.25
246Special 02. removing existing utility duct package (SPV.0090)LF415$15.00$19.00$40.00$50.00$19.00
247Special 03. removing existing utility pipe (SPV.0090)LF173$20.00$20.00$40.00$50.00$20.00
248Special 32. storm sewer box pipe 8X5-FT (SPV.0090)LF271$1,609.00$1,609.00$1,445.00$1,609.00$1,609.00
249Special 33. storm sewer box pipe 8X3-FT (SPV.0090)LF26$1,601.00$1,601.00$1,410.00$1,601.00$1,601.00
250Special 34. slotted corrugated metal drain 12-inch (SPV.0090)LF223$239.00$239.00$298.47$239.00$239.00
251Special 35. pipe underdrain exploration (SPV.0090)LF100$8.00$8.00$15.00$30.00$8.00
252Special 36. storm sewer lateral exploration (SPV.0090)LF100$8.00$8.00$15.00$8.00$8.00
253Special 40. PVC hydrant lead 6- inch (SPV.0090)LF42$108.00$108.00$178.15$108.00$108.00
254Special 41. PVC watermain 6-inch (SPV.0090)LF10$381.00$381.00$202.00$381.00$381.00
255Special 42. PVC water main 8-inch (SPV.0090)LF80$364.00$364.00$224.50$364.00$364.00
256Special 43. PVC water main 16- inch (SPV.0090)LF960$262.00$262.00$234.65$262.00$262.00
257Special 44. PVC water main 16- inch within casing pipe (SPV.0090)LF154$169.00$169.00$147.00$169.00$169.00
258Special 45. HDPE water service 1- inch (SPV.0090)LF380$149.00$149.00$212.00$149.00$149.00
259Special 46. 30-inch casing pipe (SPV.0090)LF150$1,196.00$1,196.00$1,975.00$1,196.00$1,196.00
260Special 47. construction staking water main (SPV.0090)LF1,100$1.00$1.00$1.00$2.00$1.00
261Special 50. cable aerial aluminum 4 AWG triplex (SPV.0090)LF575$8.06$8.06$8.06$8.06$8.06
262Special 01. vibration monitoring (SPV.0135)MON8$1,535.00$4,081.25$4,025.00$1,400.00$1,600.00
263Special 01. concrete sidewalk 5- inch special (SPV.0165)SF1,352$12.50$12.50$8.09$9.50$7.69
264Special 01. removing concrete channel (SPV.0180)SY1,596$8.00$8.00$13.30$15.00$8.00
265Special 02. concrete channel lining (SPV.0180)SY70$733.30$300.00$300.00$300.00$280.20
266Special 81. installing salvaged stone facing (SPV.0180)SY88$888.64$975.00$975.00$975.00$2,070.45
267Special 82. stone facing (SPV.0180)SY265$687.55$700.00$700.00$700.00$295.09
268Special 83. anti graffiti coating (SPV.0180)SY470$19.15$31.50$31.50$31.50$19.15
269Special 01. excavation, hauling, and disposal of sediment (SPV.0195)TON1,411$43.00$43.00$72.70$65.00$43.00
WisDOT contract 20250211015: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of February 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy