WisDOT contract 20251111018 bid tabulation
C Appleton, Olde Oneida Street; South Mill Race Bridge (LOC STR, Outagamie County C. Appleton, Olde Oneida Street). Let by Wisconsin DOT on November 11, 2025, Outagamie. 2 bids received; low bid $4,294,712 by Lunda Construction Company.
- Owner
- Wisconsin DOT
- Letting
- 11 NOV 2025
- Pay items
- 108
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Lunda Construction Company | $4,294,712 | Low |
| 2 | Zenith Tech., Inc. - Waukesha | $4,864,589 | +13% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Lunda Construction Company | 2. Zenith Tech., Inc. - Waukesha |
|---|---|---|---|---|---|
| 1 | Removing structure over waterway minimal debris (structure) 01. P-44- 723 (203.0260) | EACH | 1 | $105,000 | $665,000 |
| 2 | Removing concrete pavement (204.0100) | SY | 651 | $9.55 | $9.55 |
| 3 | Removing concrete surface partial depth (204.0109.S) | SF | 107 | $17.00 | $47.82 |
| 4 | Removing concrete sidewalk (204.0155) | SY | 290 | $4.05 | $4.05 |
| 5 | Removing guardrail (204.0165) | LF | 91 | $5.00 | $5.00 |
| 6 | Removing fence (204.0170) | LF | 45 | $5.00 | $5.00 |
| 7 | Removing concrete bases (204.0195) | EACH | 4 | $140.00 | $140.00 |
| 8 | Removing inlets (204.0220) | EACH | 4 | $300.00 | $300.00 |
| 9 | Removing storm sewer (size) 01. 10-inch (204.0245) | LF | 28 | $10.00 | $10.00 |
| 10 | Removing storm sewer (size) 02. 12-inch (204.0245) | LF | 48 | $10.00 | $10.00 |
| 11 | Removing (item description) 01. removing bollard (204.9060.S) | EACH | 2 | $140.00 | $140.00 |
| 12 | Excavation common (205.0100) | CY | 768 | $34.85 | $34.85 |
| 13 | Excavation, hauling, and disposal of petroleum contaminated soil (205.0501.S) | TON | 144 | $90.00 | $100.00 |
| 14 | Excavation for structures bridges (structure) 01. B-44-0502 (206.1001) | EACH | 1 | $50,000 | $160,000 |
| 15 | Cofferdams (structure) 01. B-44- 0502 (206.5001) | EACH | 2 | $5,000.00 | $180,000 |
| 16 | Backfill structure type A (210.1500) | TON | 614 | $31.25 | $31.25 |
| 17 | Finishing roadway (project) 01. 4984-01-79 (213.0100) | EACH | 1 | $1,500.00 | $1.00 |
| 18 | Base aggregate dense 3/4-inch (305.0110) | TON | 77 | $26.00 | $26.00 |
| 19 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 470 | $26.00 | $26.00 |
| 20 | Concrete pavement 9-inch (415.0090) | SY | 417 | $94.90 | $104.00 |
| 21 | Concrete pavement approach slab (415.0410) | SY | 125 | $285.00 | $273.00 |
| 22 | Concrete pavement joint filling (415.4100) | SY | 557 | $5.00 | $2.50 |
| 23 | Drilled dowel bars (416.0620) | EACH | 40 | $18.00 | $20.00 |
| 24 | Asphaltic surface driveways and field entrances (465.0120) | TON | 13 | $290.00 | $290.00 |
| 25 | Concrete masonry bridges (502.0100) | CY | 584 | $750.00 | $1,250.00 |
| 26 | Protective surface treatment (502.3200) | SY | 1,044 | $2.00 | $4.00 |
| 27 | Adhesive anchors no. 4 bar (502.4204) | EACH | 24 | $25.00 | $27.00 |
| 28 | Adhesive anchors no. 5 bar (502.4205) | EACH | 302 | $30.00 | $30.00 |
| 29 | Underwater substructure inspection (structure) 01. B-44-0502 (502.9000.S) | EACH | 2 | $2,500.00 | $5,400.00 |
| 30 | Bar steel reinforcement HS structures (505.0400) | LB | 17,360 | $1.09 | $1.30 |
| 31 | Bar steel reinforcement HS coated structures (505.0600) | LB | 77,830 | $1.19 | $1.53 |
| 32 | Structural steel HS (506.0605) | LB | 182,200 | $5.00 | $4.25 |
| 33 | Bearing pads elastomeric non- laminated (506.2605) | EACH | 18 | $150.00 | $130.00 |
| 34 | Welded stud shear connectors 7/8X5-inch (506.3010) | EACH | 7,128 | $3.75 | $6.00 |
| 35 | Bearing assemblies fixed (structure) 01. B-44-0502 (506.5000) | EACH | 18 | $2,000.00 | $1,800.00 |
| 36 | Railing pipe (513.2001) | LF | 29 | $235.00 | $270.00 |
| 37 | Railing steel type C3 (513.7016) | LF | 304 | $250.00 | $225.00 |
| 38 | Rubberized membrane waterproofing (516.0500) | SY | 24 | $25.00 | $60.00 |
| 39 | Anchor assemblies poles on structures (531.8990) | EACH | 3 | $1,500.00 | $2,800.00 |
| 40 | Pre-boring rock or consolidated materials (550.0020) | LF | 776 | $296.14 | $350.00 |
| 41 | Piling steel HP 10-inch X 42 LB (550.1100) | LF | 1,185 | $34.40 | $52.00 |
| 42 | Concrete curb & gutter integral 36- inch (601.0344) | LF | 247 | $33.00 | $30.00 |
| 43 | Concrete curb & gutter integral 4- inch sloped 36-inch (601.0501) | LF | 16 | $33.00 | $30.00 |
| 44 | Concrete sidewalk 5-inch (602.0410) | SF | 506 | $7.75 | $7.50 |
| 45 | Concrete sidewalk 7-inch (602.0420) | SF | 1,054 | $8.40 | $8.50 |
| 46 | Curb ramp detectable warning field natural patina (602.0515) | SF | 40 | $38.00 | $40.00 |
| 47 | Concrete driveway 7-inch (602.0815) | SY | 32 | $75.60 | $76.50 |
| 48 | Slope paving concrete (604.0400) | SY | 52 | $210.00 | $300.00 |
| 49 | Storm sewer pipe reinforced concrete class III 12-inch (608.0312) | LF | 30 | $84.73 | $84.73 |
| 50 | Storm sewer pipe reinforced concrete class IV 12-inch (608.0412) | LF | 100 | $99.14 | $99.14 |
| 51 | Reconstructing manholes (611.0420) | EACH | 1 | $2,500.00 | $2,500.00 |
| 52 | Manhole covers type J (611.0530) | EACH | 1 | $990.00 | $990.00 |
| 53 | Inlet covers type F (611.0615) | EACH | 1 | $2,925.00 | $2,925.00 |
| 54 | Inlet covers type H-S (611.0639) | EACH | 3 | $1,555.00 | $1,555.00 |
| 55 | Manholes 3-FT diameter (611.2003) | EACH | 1 | $2,422.00 | $2,422.00 |
| 56 | Inlets 2X3-FT (611.3230) | EACH | 3 | $3,564.00 | $3,564.00 |
| 57 | Inlets 2.5X3-FT (611.3253) | EACH | 1 | $1,984.00 | $1,984.00 |
| 58 | Fence safety (616.0700.S) | LF | 465 | $6.00 | $6.00 |
| 59 | Mobilization (619.1000) | EACH | 1 | $1,830,104 | $1,100,000 |
| 60 | Water (624.0100) | MGAL | 11 | $90.00 | $90.00 |
| 61 | Topsoil (625.0100) | SY | 138 | $12.50 | $12.50 |
| 62 | Silt fence (628.1504) | LF | 100 | $5.00 | $5.00 |
| 63 | Silt fence maintenance (628.1520) | LF | 100 | $0.01 | $0.01 |
| 64 | Mobilizations erosion control (628.1905) | EACH | 7 | $200.00 | $200.00 |
| 65 | Mobilizations emergency erosion control (628.1910) | EACH | 6 | $200.00 | $200.00 |
| 66 | Erosion mat urban class I type B (628.2008) | SY | 138 | $5.00 | $5.00 |
| 67 | Inlet protection type C (628.7015) | EACH | 5 | $75.00 | $75.00 |
| 68 | Fertilizer type B (629.0210) | CWT | 1 | $150.00 | $150.00 |
| 69 | Seeding mixture no. 40 (630.0140) | LB | 3 | $35.00 | $35.00 |
| 70 | Seed water (630.0500) | MGAL | 1.20 | $100.00 | $100.00 |
| 71 | Field office type B (642.5001) | EACH | 1 | $5,000.00 | $12,000 |
| 72 | Traffic control barricades type III (643.0420) | DAY | 1,116 | $0.61 | $0.61 |
| 73 | Traffic control warning lights type A (643.0705) | DAY | 1,488 | $0.22 | $0.22 |
| 74 | Traffic control signs (643.0900) | DAY | 4,092 | $0.31 | $0.31 |
| 75 | Traffic control signs fixed message (643.1000) | SF | 248 | $12.40 | $12.40 |
| 76 | Traffic control signs PCMS (643.1050) | DAY | 14 | $60.70 | $60.70 |
| 77 | Traffic control (643.5000) | EACH | 1 | $5,000.00 | $5,000.00 |
| 78 | Geotextile type DF schedule A (645.0111) | SY | 106 | $8.00 | $8.00 |
| 79 | Marking line epoxy 4-inch (646.1020) | LF | 1,180 | $2.50 | $2.50 |
| 80 | Marking arrow epoxy (646.5020) | EACH | 4 | $170.00 | $170.00 |
| 81 | Marking symbol epoxy (646.5220) | EACH | 4 | $170.00 | $170.00 |
| 82 | Construction staking storm sewer (650.4000) | EACH | 5 | $150.00 | $150.00 |
| 83 | Construction staking structure layout (structure) 01. B-44-0502 (650.6501) | EACH | 1 | $7,000.00 | $7,000.00 |
| 84 | Construction staking concrete pavement (650.7000) | LF | 147 | $3.00 | $3.00 |
| 85 | Construction staking curb ramps (650.9000) | EACH | 2 | $300.00 | $300.00 |
| 86 | Construction staking sidewalk (project) 01. 4984-01-79 (650.9500) | EACH | 1 | $100.00 | $100.00 |
| 87 | Construction staking supplemental control (project) 01. 4984-01-79 (650.9911) | EACH | 1 | $10.00 | $10.00 |
| 88 | Construction staking slope stakes (650.9920) | LF | 295 | $3.00 | $3.00 |
| 89 | Conduit rigid metallic 2-inch (652.0125) | LF | 50 | $95.00 | $95.00 |
| 90 | Conduit rigid nonmetallic schedule 80 2-inch (652.0325) | LF | 676 | $14.00 | $14.00 |
| 91 | Pull boxes non-conductive 24X42- inch (653.0164) | EACH | 3 | $2,150.00 | $2,150.00 |
| 92 | Junction boxes 18X12X6-inch (653.0222) | EACH | 3 | $2,400.00 | $2,400.00 |
| 93 | Concrete bases type 2 (654.0102) | EACH | 2 | $1,410.00 | $1,410.00 |
| 94 | Concrete bases type 5 (654.0105) | EACH | 1 | $1,510.00 | $1,510.00 |
| 95 | Concrete control cabinet bases type 6 (654.0200) | EACH | 1 | $1,600.00 | $1,600.00 |
| 96 | Sawing asphalt (690.0150) | LF | 90 | $2.35 | $2.50 |
| 97 | Sawing concrete (690.0250) | LF | 180 | $2.35 | $3.50 |
| 98 | Incentive strength concrete structures (715.0502) | DOL | 3,498 | $1.00 | $1.00 |
| 99 | Incentive compressive strength concrete pavement (715.0720) | DOL | 500 | $1.00 | $1.00 |
| 100 | Crack and damage survey (999.1501.S) | EACH | 2 | $1,250.00 | $750.00 |
| 101 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 500 | $5.00 | $5.00 |
| 102 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 2,000 | $5.00 | $5.00 |
| 103 | Special 02. remove, salvage, and reinstall electrical service meter breaker pedestal (SPV.0060) | EACH | 1 | $2,200.00 | $2,300.00 |
| 104 | Special 01. railing steel pedestrian type C3 (SPV.0090) | LF | 89 | $375.00 | $350.00 |
| 105 | Special 02. marking crosswalk epoxy block style 18-inch (SPV.0090) | LF | 90 | $25.00 | $25.00 |
| 106 | Special 03. petroleum absorbent boom (SPV.0090) | LF | 400 | $15.00 | $15.00 |
| 107 | Special 04. contaminated boom disposal (SPV.0090) | LF | 400 | $5.00 | $5.00 |
| 108 | Special 01. concrete sidewalk 7- inch special (SPV.0165) | SF | 1,125 | $11.75 | $13.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of November 11, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.