WisDOT contract 20260512021 bid tabulation
Port Wing - Superior; .48 Miles W of Airport Rd (STH 013, Bayfield County Port Wing - Superior). Let by Wisconsin DOT on May 12, 2026, Bayfield. 2 bids received; low bid $3,975,487 by Northern Interstate Construction, Inc..
- Owner
- Wisconsin DOT
- Letting
- 12 MAY 2026
- Pay items
- 64
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Northern Interstate Construction, Inc. | $3,975,487 | Low |
| 2 | Ritola Inc | $4,560,340 | +15% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Northern Interstate Construction, Inc. | 2. Ritola Inc |
|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 5 | $1,750.00 | $786.06 |
| 2 | Clearing (201.0110) | SY | 1,520 | $5.00 | $16.29 |
| 3 | Grubbing (201.0210) | SY | 1,520 | $5.00 | $12.22 |
| 4 | Removing small pipe culverts (203.0100) | EACH | 2 | $750.00 | $355.14 |
| 5 | Abatement of asbestos containing material (project) 01. 8510-00-76 (203.0216.S) | EACH | 1 | $5,000.00 | $2,135.21 |
| 6 | Removing asphaltic surface (204.0110) | SY | 57 | $20.00 | $4.73 |
| 7 | Removing asphaltic surface butt joints (204.0115) | SY | 45 | $30.00 | $4.73 |
| 8 | Removing concrete sidewalk (204.0155) | SY | 14 | $20.00 | $29.62 |
| 9 | Removing fence (204.0170) | LF | 180 | $10.00 | $2.64 |
| 10 | Removing (item description) 01. guard posts timber (204.9060.S) | EACH | 56 | $30.00 | $66.22 |
| 11 | Excavation common (205.0100) | CY | 5,677 | $36.00 | $41.18 |
| 12 | Finishing roadway (project) 01. 8510-00-76 (213.0100) | EACH | 1 | $5,000.00 | $3,391.93 |
| 13 | Base aggregate dense 3/4-inch (305.0110) | TON | 30 | $185.00 | $42.70 |
| 14 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 84 | $35.00 | $66.20 |
| 15 | Pulverize and relay (325.0100) | SY | 2,520 | $5.00 | $2.82 |
| 16 | Drilled tie bars (416.0610) | EACH | 4 | $16.03 | $29.46 |
| 17 | Asphaltic surface (465.0105) | TON | 443 | $134.20 | $163.74 |
| 18 | Apron endwalls for culvert pipe 12- inch (520.1012) | EACH | 2 | $950.00 | $488.39 |
| 19 | Apron endwalls for culvert pipe 18- inch (520.1018) | EACH | 2 | $1,100.00 | $699.51 |
| 20 | Culvert pipe class III-A 12-inch (520.3312) | LF | 10 | $175.00 | $164.28 |
| 21 | Culvert pipe class III-A 18-inch (520.3318) | LF | 78 | $125.00 | $73.63 |
| 22 | Concrete sidewalk 6-inch (602.0415) | SF | 210 | $30.04 | $36.03 |
| 23 | Curb ramp detectable warning field natural patina (602.0515) | SF | 20 | $60.34 | $86.27 |
| 24 | Guard posts timber (615.0300) | EACH | 56 | $96.00 | $225.80 |
| 25 | Maintenance and repair of haul roads (project) 01. 8510-00-76 (618.0100) | EACH | 1 | $1.00 | $1,648.34 |
| 26 | Mobilization (619.1000) | EACH | 1 | $363,600 | $163,150 |
| 27 | Water (624.0100) | MGAL | 1.20 | $50.00 | $32.18 |
| 28 | Topsoil (625.0100) | SY | 6,070 | $5.00 | $11.97 |
| 29 | Silt fence (628.1504) | LF | 1,330 | $2.20 | $3.38 |
| 30 | Silt fence maintenance (628.1520) | LF | 1,330 | $1.00 | $0.65 |
| 31 | Mobilizations erosion control (628.1905) | EACH | 12 | $275.00 | $210.79 |
| 32 | Mobilizations emergency erosion control (628.1910) | EACH | 2 | $200.00 | $421.59 |
| 33 | Erosion mat urban class I type B (628.2008) | SY | 6,070 | $2.25 | $2.95 |
| 34 | Temporary ditch checks (628.7504) | LF | 20 | $8.95 | $16.73 |
| 35 | Culvert pipe checks (628.7555) | EACH | 2 | $100.00 | $90.84 |
| 36 | Fertilizer type B (629.0210) | CWT | 5 | $125.00 | $186.00 |
| 37 | Seeding mixture no. 40 (630.0140) | LB | 320 | $12.50 | $14.76 |
| 38 | Seeding temporary (630.0200) | LB | 200 | $4.00 | $5.74 |
| 39 | Seed water (630.0500) | MGAL | 120 | $10.00 | $149.46 |
| 40 | Moving signs type II (638.2102) | EACH | 1 | $150.00 | $258.40 |
| 41 | Moving small sign supports (638.4000) | EACH | 1 | $150.00 | $206.34 |
| 42 | Field office type B (642.5001) | EACH | 1 | $15,000 | $9,474.12 |
| 43 | Traffic control barricades type III (643.0420) | DAY | 1,050 | $0.55 | $0.86 |
| 44 | Traffic control warning lights type A (643.0705) | DAY | 2,100 | $0.15 | $0.35 |
| 45 | Traffic control signs (643.0900) | DAY | 790 | $0.30 | $0.54 |
| 46 | Traffic control (643.5000) | EACH | 1 | $11,470 | $14,480 |
| 47 | Geotextile type HR (645.0120) | SY | 6,260 | $3.50 | $4.24 |
| 48 | Marking symbol paint (646.5205) | EACH | 1 | $1,000.00 | $1,220.12 |
| 49 | Marking parking stall paint (646.8305) | LF | 489 | $15.00 | $38.31 |
| 50 | Construction staking base (650.5000) | LF | 861 | $2.00 | $6.99 |
| 51 | Construction staking pipe culverts (650.6000) | EACH | 2 | $300.00 | $352.08 |
| 52 | Construction staking curb ramps (650.9000) | EACH | 2 | $500.00 | $352.08 |
| 53 | Construction staking sidewalk (project) 01. 8510-00-76 (650.9500) | EACH | 1 | $1,500.00 | $704.14 |
| 54 | Construction staking supplemental control (project) 01. 8510-00-76 (650.9911) | EACH | 1 | $5,000.00 | $27,624 |
| 55 | Construction staking slope stakes (650.9920) | LF | 783 | $5.00 | $6.79 |
| 56 | Sawing asphalt (690.0150) | LF | 108 | $6.00 | $3.60 |
| 57 | Sawing concrete (690.0250) | LF | 14 | $9.00 | $9.00 |
| 58 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 800 | $5.00 | $5.00 |
| 59 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 600 | $5.00 | $5.00 |
| 60 | Special 01. excavation common special (SPV.0035) | CY | 8,063 | $45.00 | $50.14 |
| 61 | Special 01. remove and reinstall picnic table (SPV.0060) | EACH | 1 | $900.00 | $1,383.13 |
| 62 | Special 01. armor stone (SPV.0195) | TON | 12,442 | $150.00 | $173.77 |
| 63 | Special 02. underlayer stone (SPV.0195) | TON | 7,460 | $100.00 | $145.27 |
| 64 | Special 03. 6" minus bedding stone (SPV.0195) | TON | 1,420 | $100.00 | $61.48 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of May 12, 2026. Compiled by Mirage Metrics.