| 1 | Removing small pipe culverts (203.0100) | EACH | 5 | $1,500.00 |
| 2 | Removing asphaltic surface butt joints (204.0115) | SY | 2,923 | $9.80 |
| 3 | Removing guardrail (204.0165) | LF | 75 | $3.00 |
| 4 | Excavation common (205.0100) | CY | 4,340 | $15.00 |
| 5 | Borrow (208.0100) | CY | 946 | $17.00 |
| 6 | Backfill granular grade 2 (209.2500) | TON | 426 | $28.00 |
| 7 | Prepare foundation for asphaltic paving (project) 01. 5316-00-71 (211.0101) | EACH | 1 | $21,625 |
| 8 | Finishing roadway (project) 01. 5316-00-71 (213.0100) | EACH | 1 | $500.00 |
| 9 | Base aggregate dense 3/4-inch (305.0110) | TON | 6,800 | $29.35 |
| 10 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 6,440 | $23.00 |
| 11 | Select crushed material (312.0110) | TON | 3,350 | $23.00 |
| 12 | Pulverize and relay (325.0100) | SY | 142,126 | $1.96 |
| 13 | QMP pulverize and relay compaction (374.1020.S) | SY | 142,126 | $0.22 |
| 14 | Tack coat (455.0605) | GAL | 16,852 | $3.36 |
| 15 | HMA percent within limits (PWL) test strip volumetrics (460.0105.S) | EACH | 2 | $3,800.00 |
| 16 | HMA percent within limits (PWL) test strip density (460.0110.S) | EACH | 1 | $2,250.00 |
| 17 | Incentive density PWL HMA pavement (460.2005) | DOL | 8,500 | $1.00 |
| 18 | Incentive density HMA pavement longitudinal joints (460.2007) | DOL | 18,000 | $1.00 |
| 19 | Incentive air voids HMA pavement (460.2010) | DOL | 38,000 | $1.00 |
| 20 | HMA pavement 3 LT 58-28 S (460.5223) | TON | 19,652 | $87.29 |
| 21 | HMA pavement 4 LT 58-28 S (460.5224) | TON | 19,652 | $88.41 |
| 22 | Asphaltic surface driveways and field entrances (465.0120) | TON | 56 | $120.26 |
| 23 | Asphaltic rumble strips, centerline (465.0560) | LF | 30,922 | $0.21 |
| 24 | Apron endwalls for culvert pipe steel 18-inch (521.1018) | EACH | 2 | $400.00 |
| 25 | Apron endwalls for culvert pipe steel 24-inch (521.1024) | EACH | 4 | $575.00 |
| 26 | Culvert pipe corrugated steel 18- inch (521.3118) | LF | 70 | $110.00 |
| 27 | Culvert pipe corrugated steel 24- inch (521.3124) | LF | 104 | $140.00 |
| 28 | Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024) | EACH | 2 | $2,800.00 |
| 29 | Concrete curb & gutter 4-inch sloped 30-inch type J (601.0576) | LF | 2,777 | $24.00 |
| 30 | Concrete surface drains (602.3010) | CY | 32 | $500.00 |
| 31 | Riprap medium (606.0200) | CY | 39 | $45.00 |
| 32 | Storm sewer pipe reinforced concrete class III 24-inch (608.0324) | LF | 174 | $135.00 |
| 33 | Inlet covers type HM-GJ (611.0630) | EACH | 2 | $1,500.00 |
| 34 | Inlet covers type MS (611.0642) | EACH | 2 | $1,025.00 |
| 35 | Catch basins 6-FT diameter (611.1006) | EACH | 2 | $7,000.00 |
| 36 | Inlets median 2 grate (611.3902) | EACH | 1 | $3,500.00 |
| 37 | MGS guardrail 3 K (614.2330) | LF | 926 | $45.00 |
| 38 | MGS guardrail terminal eat (614.2610) | EACH | 4 | $3,250.00 |
| 39 | Maintenance and repair of haul roads (project) 01. 5316-00-71 (618.0100) | EACH | 1 | $1.00 |
| 40 | Mobilization (619.1000) | EACH | 1 | $324,210 |
| 41 | Water (624.0100) | MGAL | 230 | $59.10 |
| 42 | Salvaged topsoil (625.0500) | SY | 8,444 | $4.00 |
| 43 | Mulching (627.0200) | SY | 2,500 | $0.35 |
| 44 | Silt fence (628.1504) | LF | 3,641 | $2.25 |
| 45 | Silt fence maintenance (628.1520) | LF | 7,282 | $0.01 |
| 46 | Mobilizations erosion control (628.1905) | EACH | 3 | $200.00 |
| 47 | Mobilizations emergency erosion control (628.1910) | EACH | 2 | $300.00 |
| 48 | Erosion mat class I type B (628.2004) | SY | 12,944 | $1.05 |
| 49 | Inlet protection type A (628.7005) | EACH | 1 | $100.00 |
| 50 | Inlet protection type B (628.7010) | EACH | 2 | $60.00 |
| 51 | Temporary ditch checks (628.7504) | LF | 190 | $8.75 |
| 52 | Culvert pipe checks (628.7555) | EACH | 15 | $20.00 |
| 53 | Tracking pads (628.7560) | EACH | 1 | $1.00 |
| 54 | Fertilizer type B (629.0210) | CWT | 9.60 | $65.00 |
| 55 | Seeding mixture no. 20 (630.0120) | LB | 279 | $7.90 |
| 56 | Seeding temporary (630.0200) | LB | 279 | $2.50 |
| 57 | Seeding borrow pit (630.0300) | LB | 125 | $7.90 |
| 58 | Seed water (630.0500) | MGAL | 64 | $20.00 |
| 59 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 30 | $100.00 |
| 60 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 13 | $107.00 |
| 61 | Signs type II reflective H (637.2210) | SF | 230.94 | $21.00 |
| 62 | Signs type II reflective F (637.2230) | SF | 85.60 | $26.00 |
| 63 | Removing signs type II (638.2602) | EACH | 44 | $35.00 |
| 64 | Removing small sign supports (638.3000) | EACH | 33 | $35.00 |
| 65 | Field office type B (642.5001) | EACH | 1 | $19,055 |
| 66 | Traffic control drums (643.0300) | DAY | 5,920 | $0.15 |
| 67 | Traffic control signs (643.0900) | DAY | 8,375 | $0.25 |
| 68 | Traffic control signs PCMS (643.1050) | DAY | 14 | $20.00 |
| 69 | Temporary marking line paint 6- inch (643.3165) | LF | 148,688 | $0.23 |
| 70 | Traffic control (643.5000) | EACH | 1 | $20,100 |
| 71 | Geotextile type HR (645.0120) | SY | 136 | $9.00 |
| 72 | Marking line epoxy 6-inch (646.2020) | LF | 120,710 | $0.53 |
| 73 | Marking line epoxy 8-inch (646.3020) | LF | 400 | $1.50 |
| 74 | Marking arrow epoxy (646.5020) | EACH | 4 | $226.50 |
| 75 | Marking word epoxy (646.5120) | EACH | 4 | $302.25 |
| 76 | Locating no-passing zones (648.0100) | MI | 7.10 | $589.50 |
| 77 | Construction staking storm sewer (650.4000) | EACH | 5 | $215.00 |
| 78 | Construction staking subgrade (650.4500) | LF | 2,866 | $0.01 |
| 79 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 2,777 | $2.00 |
| 80 | Construction staking pipe culverts (650.6000) | EACH | 4 | $300.00 |
| 81 | Construction staking resurfacing reference (650.8000) | LF | 37,172 | $0.21 |
| 82 | Construction staking supplemental control (project) 01. 5316-00-71 (650.9911) | EACH | 1 | $1,200.00 |
| 83 | Construction staking slope stakes (650.9920) | LF | 2,676 | $2.25 |
| 84 | Sawing asphalt (690.0150) | LF | 542 | $1.96 |
| 85 | Incentive iri ride (740.0440) | DOL | 11,100 | $1.00 |
| 86 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,500 | $5.00 |
| 87 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 3,250 | $5.00 |
| 88 | Special 01. incentive density PWL, HMA pavement (SPV.0055) | DOL | 8,500 | $1.00 |
| 89 | Special 02. incentive density PWL, HMA pavement longitudinal joints (SPV.0055) | DOL | 18,000 | $1.00 |
| 90 | Special 01. landmark reference monuments special (SPV.0060) | EACH | 5 | $550.00 |