WisDOT contract 20260310022 bid tabulation

4516-11-73. Let by Wisconsin DOT on March 10, 2026, Brown. 4 bids received; low bid $2,963,668 by MCC, Inc..

Owner
Wisconsin DOT
Letting
10 MAR 2026
Pay items
140
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1MCC, Inc.$2,963,668Low
2Vinton Construction Company$2,971,9330.0%
3Peters Concrete Company$3,110,716+5.0%
4James Peterson Sons, Inc.$3,406,460+15%
WisDOT contract 20260310022: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. MCC, Inc.2. Vinton Construction Company3. Peters Concrete Company4. James Peterson Sons, Inc.
1Clearing (201.0120)ID30$30.00$30.00$30.00$80.00
2Grubbing (201.0220)ID30$30.00$30.00$30.00$40.00
3Removing small pipe culverts (203.0100)EACH1$455.00$490.00$400.00$750.00
4Removing concrete pavement (204.0100)SY1,305$4.60$8.31$6.95$12.00
5Removing asphaltic surface (204.0110)SY992$5.25$5.39$4.50$4.50
6Removing asphaltic surface milling (204.0120)SY10,915$5.65$0.01$4.60$4.60
7Removing curb & gutter (204.0150)LF7,891$2.70$6.96$8.10$12.00
8Removing concrete sidewalk (204.0155)SY835$5.80$9.00$8.30$10.00
9Removing surface drains (204.0190)EACH8$455.00$100.00$150.00$750.00
10Removing manholes (204.0210)EACH4$400.00$504.25$400.00$465.00
11Removing storm sewer (size) 01. 12-inch (204.0245)LF308$20.00$13.94$29.15$20.00
12Removing storm sewer (size) 02. 15-inch (204.0245)LF376$20.00$17.65$30.85$20.00
13Excavation common (205.0100)CY15,712$12.50$17.75$15.00$28.40
14Finishing roadway (project) 01. 4516-11-73 (213.0100)EACH1$3,500.00$2,500.00$3,000.00$2,000.00
15Finishing roadway (project) 02. 4516-12-75 (213.0100)EACH1$3,500.00$2,500.00$1,500.00$2,000.00
16Base aggregate dense 1 1/4-inch (305.0120)TON10,903$15.10$0.01$15.60$20.39
17Base aggregate dense 3-inch (305.0130)TON13,910$14.35$15.90$18.35$17.00
18Drilled tie bars (416.0610)EACH278$6.00$6.00$6.00$6.00
19HMA cold weather paving (450.4000)TON2,450$0.01$2.00$2.00$2.00
20Tack coat (455.0605)GAL2,010$4.05$3.00$3.00$3.00
21Incentive density HMA pavement (460.2000)DOL9,786$1.00$1.00$1.00$1.00
22HMA pavement 3 LT 58-28 S (460.5223)TON1,838$82.90$68.20$68.20$68.20
23HMA pavement 4 LT 58-28 S (460.5224)TON1,226$78.85$74.20$74.20$74.20
24HMA pavement 3 MT 58-28 S (460.6223)TON4,979$81.15$70.30$70.30$70.30
25HMA pavement 4 MT 58-28 S (460.6224)TON1,743$80.75$77.20$77.20$77.20
26Asphaltic surface driveways and field entrances (465.0120)TON117$200.00$165.00$165.00$165.00
27Bar steel reinforcement HS structures (505.0400)LB985$2.45$2.45$2.45$2.45
28Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012)EACH1$1,300.00$1,502.05$1,950.00$1,350.00
29Concrete curb & gutter 18-inch type A (601.0405)LF106$52.50$52.50$52.50$52.50
30Concrete curb & gutter 18-inch type D (601.0407)LF161$51.50$51.50$51.50$51.50
31Concrete curb & gutter 30-inch type D (601.0411)LF85$53.00$53.00$53.00$53.00
32Concrete curb pedestrian (601.0600)LF21$50.00$50.00$50.00$50.00
33Concrete sidewalk 4-inch (602.0405)SF52,776$6.10$6.10$6.10$6.10
34Concrete sidewalk 6-inch (602.0415)SF3,749$7.85$7.85$7.85$7.85
35Curb ramp detectable warning field yellow (602.0505)SF434$34.00$34.00$34.00$34.00
36Curb ramp detectable warning field radial yellow (602.0605)SF51$60.00$60.00$60.00$60.00
37Concrete driveway 6-inch (602.0810)SY917$68.75$68.75$68.75$68.75
38Concrete driveway 8-inch (602.0820)SY579$79.25$79.25$79.25$79.25
39Relaid storm sewer 15-inch (608.0115)LF50$86.00$88.49$102.00$95.00
40Storm sewer pipe reinforced concrete class III 12-inch (608.0312)LF238$70.00$85.05$101.00$105.00
41Storm sewer pipe reinforced concrete class III 18-inch (608.0318)LF45$102.00$132.50$139.00$195.00
42Storm sewer pipe reinforced concrete class III 24-inch (608.0324)LF20$169.00$181.07$190.00$315.00
43Storm sewer pipe reinforced concrete class IV 12-inch (608.0412)LF220$71.00$83.36$98.75$95.00
44Storm sewer pipe reinforced concrete class IV 15-inch (608.0415)LF359$92.00$98.27$86.25$95.00
45Reconstructing catch basins (611.0410)EACH11$1,000.00$1,024.91$800.00$1,500.00
46Reconstructing manholes (611.0420)EACH23$1,000.00$1,338.63$750.00$1,450.00
47Reconstructing inlets (611.0430)EACH13$1,000.00$1,047.29$800.00$1,500.00
48Inlet covers type C (611.0612)EACH7$591.00$564.20$550.00$600.00
49Inlet covers type H-S (611.0639)EACH8$831.00$777.31$800.00$800.00
50Manholes 4-FT diameter (611.2004)EACH3$4,487.00$6,967.96$5,450.00$5,150.00
51Manholes 6X6-FT (611.2066)EACH1$14,978$18,337$11,750$14,500
52Inlets 3-FT diameter (611.3003)EACH7$2,705.00$2,302.10$2,750.00$2,850.00
53Inlets 2X3-FT (611.3230)EACH7$2,976.00$2,821.46$2,830.00$3,350.00
54Pipe underdrain wrapped 6-inch (612.0406)LF1,389$12.50$13.97$26.00$15.00
55Maintenance and repair of haul roads (project) 01. 4516-11-73 (618.0100)EACH1$500.00$0.01$1.00$500.00
56Maintenance and repair of haul roads (project) 02. 4516-12-75 (618.0100)EACH1$500.00$0.01$1.00$500.00
57Mobilization (619.1000)EACH1$140,300$360,000$261,000$189,160
58Water (624.0100)MGAL349$32.23$0.01$1.00$45.00
59Topsoil (625.0100)SY17,915$6.35$5.00$6.34$6.75
60Silt fence (628.1504)LF3,499$1.95$1.80$1.80$1.80
61Silt fence maintenance (628.1520)LF3,499$0.01$0.01$0.01$0.01
62Mobilizations erosion control (628.1905)EACH6$150.00$0.01$0.01$0.01
63Mobilizations emergency erosion control (628.1910)EACH6$100.00$0.01$0.01$0.01
64Erosion mat urban class I type B (628.2008)SY20,603$1.85$0.01$0.01$0.01
65Inlet protection type A (628.7005)EACH15$5.00$20.00$20.00$20.00
66Inlet protection type B (628.7010)EACH11$65.00$20.00$20.00$20.00
67Inlet protection type C (628.7015)EACH32$68.00$20.00$20.00$20.00
68Temporary ditch checks (628.7504)LF180$7.50$6.25$6.25$6.25
69Culvert pipe checks (628.7555)EACH6$15.00$16.00$16.00$16.00
70Tracking pads (628.7560)EACH2$1,380.02$0.01$500.00$3,500.00
71Rock bags (628.7570)EACH43$15.00$16.00$16.00$16.00
72Fertilizer type B (629.0210)CWT10$95.00$340.00$340.00$340.00
73Seeding mixture no. 40 (630.0140)LB402$7.50$75.00$75.00$75.00
74Seeding temporary (630.0200)LB482$4.00$18.00$18.00$18.00
75Seed water (630.0500)MGAL203$1.00$0.01$0.01$0.01
76Posts wood 4X6-inch X 12-FT (634.0612)EACH6$74.00$110.00$110.00$110.00
77Posts wood 4X6-inch X 14-FT (634.0614)EACH21$76.00$113.00$113.00$113.00
78Posts wood 4X6-inch X 16-FT (634.0616)EACH50$80.00$118.00$118.00$118.00
79Posts wood 4X6-inch X 18-FT (634.0618)EACH3$88.00$118.00$118.00$118.00
80Signs type II reflective H (637.2210)SF252.72$22.15$19.00$19.00$19.00
81Signs type II reflective F (637.2230)SF475.33$22.80$19.00$19.00$19.00
82Moving signs type II (638.2102)EACH13$65.00$35.00$35.00$35.00
83Removing signs type II (638.2602)EACH21$30.00$10.00$10.00$10.00
84Removing small sign supports (638.3000)EACH15$30.00$10.00$10.00$10.00
85Field office type B (642.5001)EACH1$14,500$10,000$9,500.00$18,000
86Traffic control drums (643.0300)DAY2,950$0.30$0.15$0.15$0.15
87Traffic control barricades type III (643.0420)DAY2,589$0.45$0.45$0.45$0.45
88Traffic control warning lights type A (643.0705)DAY5,178$0.10$0.10$0.10$0.10
89Traffic control warning lights type C (643.0715)DAY110$0.60$0.60$0.60$0.60
90Traffic control connected arrow boards (643.0810)DAY5$9.00$9.00$9.00$9.00
91Traffic control signs (643.0900)DAY4,073$0.20$0.20$0.20$0.20
92Traffic control signs fixed message (643.1000)SF25$14.00$14.00$14.00$14.00
93Traffic control signs PCMS (643.1050)DAY28$11.00$11.00$11.00$11.00
94Temporary marking crosswalk removable tape 6-inch (643.3350)LF52$2.20$2.20$2.20$2.20
95Temporary marking stop line removable tape 18-inch (643.3850)LF13$7.00$7.00$7.00$7.00
96Traffic control (643.5000)EACH1$11,750$11,750$11,750$16,360
97Temporary pedestrian surface plate (644.1430)SF48$10.00$10.00$10.00$10.00
98Temporary pedestrian surface matting (644.1440)SF400$2.50$2.50$2.50$2.50
99Temporary pedestrian detectable warning field (644.1605)SF16$3.50$3.50$3.50$3.50
100Temporary pedestrian barricade (644.1810)LF301$6.75$6.75$6.75$6.75
101Marking line epoxy 6-inch (646.2020)LF20,799$0.49$0.49$0.65$0.49
102Marking line epoxy 10-inch (646.4020)LF287$1.07$1.07$0.80$1.07
103Marking arrow epoxy (646.5020)EACH51$193.48$193.48$175.00$193.48
104Marking word epoxy (646.5120)EACH3$378.89$378.89$225.00$378.89
105Marking symbol epoxy (646.5220)EACH49$182.05$182.05$255.00$182.05
106Marking stop line epoxy 18-inch (646.6120)LF155$15.72$15.72$15.25$15.72
107Marking diagonal epoxy 12-inch (646.7120)LF9$15.30$15.30$10.20$15.30
108Marking crosswalk epoxy transverse line 6-inch (646.7420)LF1,838$14.88$14.88$8.50$14.88
109Marking crosswalk epoxy block style 24-inch (646.7520)LF70$25.77$25.77$18.75$25.77
110Marking removal line water blasting 6-inch (646.9012)LF172$2.20$2.20$2.20$2.20
111Marking removal line water blasting wide (646.9210)LF50$9.85$9.85$9.85$9.85
112Marking removal special marking water blasting (646.9310)EACH2$475.00$475.00$475.00$475.00
113Construction staking storm sewer (650.4000)EACH19$250.00$250.00$250.00$250.00
114Construction staking subgrade (650.4500)LF3,967$0.01$0.01$0.01$0.01
115Construction staking base (650.5000)LF6,545$0.30$0.30$0.30$0.30
116Construction staking curb gutter and curb & gutter (650.5500)LF7,959$0.45$0.45$0.45$0.45
117Construction staking curb ramps (650.9000)EACH46$75.00$75.00$75.00$75.00
118Construction staking sidewalk (project) 01. 4516-11-73 (650.9500)EACH1$100.00$100.00$100.00$100.00
119Construction staking sidewalk (project) 02. 4516-12-75 (650.9500)EACH1$100.00$100.00$100.00$100.00
120Construction staking supplemental control (project) 01. 4516-11-73 (650.9911)EACH1$10.00$10.00$10.00$10.00
121Construction staking supplemental control (project) 02. 4516-12-75 (650.9911)EACH1$10.00$10.00$10.00$10.00
122Construction staking slope stakes (650.9920)LF6,545$1.35$1.35$1.35$1.35
123Sawing asphalt (690.0150)LF1,041$1.75$3.00$1.75$1.48
124Sawing concrete (690.0250)LF781$2.35$3.00$2.35$3.03
125Incentive iri ride (740.0440)DOL10,000$1.00$1.00$1.00$1.00
126Installing and maintaining climbing turtle exclusion fence (999.2100.S)LF640$6.50$4.00$4.00$4.00
127On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS2,000$5.00$5.00$5.00$5.00
128On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS1,320$5.00$5.00$5.00$5.00
129Special 01. adjust water valves (SPV.0060)EACH20$350.00$329.13$225.00$350.00
130Special 02. adjust water service valves (SPV.0060)EACH22$350.00$125.48$225.00$275.00
131Special 03. manhole covers type 1 (SPV.0060)EACH4$645.00$593.74$775.00$650.00
132Special 04. inlet covers type E (SPV.0060)EACH1$1,149.00$1,041.06$1,500.00$1,250.00
133Special 05. internal/external frame and chimeny seal (SPV.0060)EACH2$720.00$575.00$575.00$800.00
134Special 05. internal/external frame and chimney seal (SPV.0060)EACH5$720.00$575.00$575.00$800.00
135Special 06. storm sewer pipe PVC 12-inch connection (SPV.0060)EACH1$800.00$1,860.56$2,400.00$1,500.00
136Special 07. temporary mailbox accommodations project 4516-11- 73 (SPV.0060)EACH1$1,200.00$1,000.00$1,000.00$1,000.00
137Special 08. temporary mailbox accommodations project 4516-12- 75 (SPV.0060)EACH1$1,500.00$1,000.00$1,000.00$1,000.00
138Special 01. concrete curb and gutter 24-inch type A (SPV.0090)LF106$48.55$48.55$48.55$48.55
139Special 02. concrete curb and gutter 24-inch type D (SPV.0090)LF7,480$22.95$22.95$22.95$22.95
140Special 03. concrete valley gutter 36-inch type D (SPV.0090)LF116$54.00$54.00$54.00$54.00
WisDOT contract 20260310022: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of March 10, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy