WisDOT contract 20250513026 bid tabulation

6508-00-71. Let by Wisconsin DOT on May 13, 2025, Outagamie. 4 bids received; low bid $2,709,889 by MCC, Inc..

Owner
Wisconsin DOT
Letting
13 MAY 2025
Pay items
139
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1MCC, Inc.$2,709,889Low
2Vinton Construction Company$2,731,141+1.0%
3Northeast Asphalt, Inc$2,954,774+9.0%
4James Peterson Sons, Inc.$3,094,575+14%
WisDOT contract 20250513026: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. MCC, Inc.2. Vinton Construction Company3. Northeast Asphalt, Inc4. James Peterson Sons, Inc.
1Grubbing (201.0205)STA27$459.00$273.25$372.17$273.25
2Grubbing (201.0220)ID46$39.00$5.28$45.95$5.28
3Removing small pipe culverts (203.0100)EACH21$205.70$250.00$399.22$733.00
4Removing structure (structure) 01. 53X83 CMP (203.0220)EACH2$4,800.00$2,545.00$1,332.16$2,344.00
5Removing structure over waterway minimal debris (structure) 01. P-44- 119 (203.0260)EACH1$95,000$144,000$144,000$112,800
6Removing concrete pavement (204.0100)SY420$5.40$5.38$10.12$7.47
7Removing asphaltic surface (204.0110)SY536$5.00$4.14$7.64$4.47
8Removing guardrail (204.0165)LF264$7.50$2.05$7.50$7.50
9Removing masonry (204.0185)CY2$53.06$455.00$137.87$500.00
10Excavation common (205.0100)CY15,309$7.80$9.43$8.94$7.36
11Excavation marsh (205.0400)CY200$11.80$9.43$16.16$16.75
12Excavation for structures bridges (structure) 01. B-44-501 (206.1001)EACH1$20,000$11,500$11,500$23,000
13Cofferdams (structure) 01. B-44-501 (206.5001)EACH1$73,000$48,000$48,000$50,900
14Borrow (208.0100)CY12,141$7.50$0.01$11.57$16.58
15Backfill structure type A (210.1500)TON414$32.00$32.45$27.68$25.00
16Finishing roadway (project) 01. 6508-00-71 (213.0100)EACH1$1,770.00$1,000.00$866.49$5,000.00
17Finishing roadway (project) 02. 6508-01-71 (213.0100)EACH1$884.14$1,000.00$866.49$5,000.00
18Base aggregate dense 3/4-inch (305.0110)TON630$17.75$28.03$29.39$24.13
19Base aggregate dense 1 1/4-inch (305.0120)TON16,585$10.55$14.20$16.69$17.94
20Base aggregate dense 3-inch (305.0130)TON3,460$10.85$14.20$16.85$16.75
21Base aggregate open-graded (310.0110)TON10$25.00$48.70$26.44$16.56
22Breaker run (311.0110)TON640$11.35$15.20$16.82$16.25
23Coloring concrete custom (405.0200)CY2$500.00$125.00$500.00$500.00
24Stamping colored concrete (405.1000)CY2$1,000.00$650.00$1,000.00$1,000.00
25HMA cold weather paving (450.4000)TON263$10.00$6.75$6.75$6.75
26Tack coat (455.0605)GAL1,209$4.72$3.25$3.25$3.25
27Incentive density HMA pavement (460.2000)DOL2,830$1.00$1.00$1.00$1.00
28HMA pavement 3 LT 58-28 S (460.5223)TON2,480$64.58$60.10$60.10$60.10
29HMA pavement 4 LT 58-28 S (460.5224)TON1,930$71.30$67.10$67.10$67.10
30Asphaltic surface (465.0105)TON263$91.28$95.00$95.00$95.00
31Asphaltic surface driveways and field entrances (465.0120)TON100$113.43$145.00$145.00$145.00
32Asphaltic flumes (465.0315)SY28$59.08$67.00$67.00$67.00
33Concrete masonry bridges (502.0100)CY252$650.00$630.00$630.00$800.00
34Protective surface treatment (502.3200)SY343$3.60$2.00$2.00$4.70
35Underwater substructure inspection (structure) 01. B-44-501 (502.9000.S)EACH1$500.00$5,100.00$5,100.00$5,100.00
36Concrete masonry endwalls (504.0900)CY20$581.00$581.00$581.00$581.00
37Bar steel reinforcement HS structures (505.0400)LB7,230$1.20$0.91$0.91$0.96
38Bar steel reinforcement HS coated structures (505.0600)LB36,110$1.25$1.01$1.01$1.06
39Railing tubular type M (513.4061)LF150$275.00$260.00$260.00$290.00
40Rubberized membrane waterproofing (516.0500)SY14$70.00$25.00$25.00$60.00
41Apron endwalls for culvert pipe steel 12-inch (521.1012)EACH16$345.00$320.00$221.22$204.00
42Apron endwalls for culvert pipe steel 18-inch (521.1018)EACH12$240.00$395.00$283.50$258.00
43Apron endwalls for culvert pipe steel 24-inch (521.1024)EACH12$325.00$475.00$413.15$355.00
44Apron endwalls for culvert pipe sloped side drains steel 24-inch 4 to 1 (521.1505)EACH1$826.00$2,230.00$1,492.19$2,300.00
45Culvert pipe corrugated steel 18- inch (521.3118)LF314$46.75$66.35$77.97$131.00
46Culvert pipe corrugated steel 24- inch (521.3124)LF204$52.10$80.45$92.76$189.75
47Culvert pipe reinforced concrete horizontal elliptical class HE-III 19X30-inch (522.2319)LF72$215.00$155.00$185.40$257.00
48Culvert pipe reinforced concrete horizontal elliptical class HE-III 24X38-inch (522.2324)LF96$270.00$182.85$253.14$296.00
49Culvert pipe reinforced concrete horizontal elliptical class HE-III 53X83-inch (522.2353)LF168$735.00$590.15$644.44$991.00
50Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 19X30-inch (522.2619)EACH4$1,735.00$1,765.00$1,886.81$1,641.00
51Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 24X38-inch (522.2624)EACH4$2,350.00$2,440.00$2,378.80$2,092.00
52Pile points (550.0500)EACH27$105.00$150.00$150.00$110.00
53Piling steel HP 10-inch X 42 LB (550.1100)LF3,250$32.00$36.90$36.90$17.00
54Concrete curb & gutter 6-inch sloped 30-inch type J (601.0415)LF5,465$16.10$17.65$16.10$16.10
55Concrete driveway 6-inch (602.0810)SY390$64.40$72.00$64.40$64.40
56Riprap light (606.0100)CY685$41.15$59.95$77.10$77.75
57Riprap medium (606.0200)CY55$65.00$76.00$81.05$90.50
58Riprap heavy (606.0300)CY240$85.00$67.00$88.93$90.50
59Storm sewer pipe class III-B 24- inch (608.3624)LF88$160.00$88.15$93.64$148.00
60Storm sewer pipe composite 12- inch (608.6012)LF581$115.00$88.45$74.09$216.40
61Inlet covers type HM-GJ (611.0630)EACH29$730.00$657.00$855.19$880.00
62Inlet covers type MS-A (611.0645)EACH2$535.00$474.00$644.66$800.00
63Inlets 2X3-FT (611.3230)EACH29$3,600.00$2,972.00$3,401.64$2,758.00
64Inlets median 2 grate (611.3902)EACH1$4,750.00$4,572.00$4,930.18$4,867.00
65Pipe underdrain 6-inch (612.0106)LF120$36.00$21.50$20.34$31.47
66Pipe underdrain unperforated 6- inch (612.0206)LF30$34.00$47.40$18.44$24.26
67Pipe underdrain wrapped 6-inch (612.0406)LF180$4.20$7.20$11.51$8.40
68Drain tile exploration (612.0700)LF60$36.00$15.85$25.62$15.00
69MGS guardrail 3 (614.2300)LF75$32.50$32.50$32.50$32.50
70MGS thrie beam transition (614.2500)LF157.60$98.00$98.00$98.00$98.00
71MGS guardrail terminal eat (614.2610)EACH4$4,000.00$4,000.00$4,000.00$4,000.00
72Mobilization (619.1000)EACH1$299,500$425,700$175,000$230,200
73Landmark reference monuments (621.0100)EACH5$50.00$50.00$150.00$50.00
74Water (624.0100)MGAL282.60$34.00$0.01$47.24$55.00
75Topsoil (625.0100)SY7,796$2.00$0.01$2.51$3.35
76Salvaged topsoil (625.0500)SY30,612$0.95$2.00$4.90$1.00
77Mulching (627.0200)SY32,944$0.30$0.30$0.30$0.30
78Erosion bales (628.1104)EACH300$14.00$14.00$14.00$14.00
79Silt fence (628.1504)LF3,874$2.00$2.00$2.00$2.00
80Silt fence maintenance (628.1520)LF3,874$0.01$0.01$0.01$0.01
81Mobilizations erosion control (628.1905)EACH9$275.00$275.00$275.00$275.00
82Mobilizations emergency erosion control (628.1910)EACH6$150.00$150.00$150.00$150.00
83Erosion mat class I type B (628.2004)SY4,207$1.42$1.42$1.42$1.42
84Erosion mat urban class I type B (628.2008)SY3,565$1.88$1.88$1.88$1.88
85Turbidity barriers (628.6005)SY625$48.00$48.00$48.00$48.00
86Inlet protection type A (628.7005)EACH1$135.00$135.00$135.00$135.00
87Inlet protection type C (628.7015)EACH40$70.00$70.00$70.00$70.00
88Temporary ditch checks (628.7504)LF94$8.00$8.00$8.00$8.00
89Culvert pipe checks (628.7555)EACH120$14.00$14.00$14.00$14.00
90Tracking pads (628.7560)EACH3$1,000.00$0.01$1,587.14$4,500.00
91Rock bags (628.7570)EACH50$14.00$14.00$14.00$14.00
92Fertilizer type A (629.0205)CWT26.24$100.00$100.00$100.00$100.00
93Seeding mixture no. 20 (630.0120)LB1,457$7.25$7.25$7.25$7.25
94Seeding mixture no. 30 (630.0130)LB161$8.00$8.00$8.00$8.00
95Seeding mixture no. 40 (630.0140)LB190$8.00$8.00$8.00$8.00
96Seeding temporary (630.0200)LB1,083$4.00$4.00$4.00$4.00
97Seed water (630.0500)MGAL151$1.00$1.00$1.00$1.00
98Markers culvert end (633.5200)EACH6$68.00$68.00$68.00$68.00
99Posts wood 4X6-inch X 14-FT (634.0614)EACH10$82.00$82.00$82.00$82.00
100Posts wood 4X6-inch X 16-FT (634.0616)EACH2$86.00$86.00$86.00$86.00
101Signs type II reflective H (637.2210)SF38$22.45$22.45$22.45$22.45
102Signs type II reflective F (637.2230)SF12$22.75$22.75$22.75$22.75
103Removing signs type II (638.2602)EACH16$30.00$30.00$30.00$30.00
104Removing small sign supports (638.3000)EACH16$30.00$30.00$30.00$30.00
105Field office type C (642.5201)EACH1$12,000$9,500.00$12,659$25,000
106Traffic control drums (643.0300)DAY13,820$0.30$0.15$0.15$0.15
107Traffic control barricades type III (643.0420)DAY3,982$0.55$0.65$0.65$0.65
108Traffic control warning lights type A (643.0705)DAY6,908$0.25$0.15$0.15$0.15
109Traffic control signs (643.0900)DAY4,686$0.65$0.35$0.35$0.35
110Traffic control signs PCMS (643.1050)DAY14$85.00$30.00$30.00$30.00
111Traffic control (643.5000)EACH1$3,500.00$12,125$12,125$12,125
112Geotextile type DF schedule A (645.0111)SY164$5.00$3.90$4.21$4.50
113Geotextile type HR (645.0120)SY3,420$3.35$2.75$4.28$3.75
114Marking line epoxy 6-inch (646.2020)LF14,098$0.67$0.67$0.67$0.67
115Marking stop line epoxy 18-inch (646.6120)LF37$18.70$18.70$19.75$18.70
116Locating no-passing zones (648.0100)MI1$525.00$525.00$525.00$525.00
117Construction staking storm sewer (650.4000)EACH47$90.00$90.00$90.00$90.00
118Construction staking subgrade (650.4500)LF6,011$0.01$0.01$0.01$0.01
119Construction staking base (650.5000)LF6,011$0.55$0.55$0.55$0.55
120Construction staking curb gutter and curb & gutter (650.5500)LF5,465$0.75$0.75$0.95$0.75
121Construction staking pipe culverts (650.6000)EACH19$50.00$50.00$125.00$50.00
122Construction staking structure layout (structure) 01. B-44-501 (650.6501)EACH1$3,500.00$3,500.00$3,500.00$3,500.00
123Construction staking supplemental control (project) 01. 6508-00-71 (650.9911)EACH1$10.00$10.00$800.00$10.00
124Construction staking supplemental control (project) 02. 6508-01-71 (650.9911)EACH1$10.00$10.00$800.00$10.00
125Construction staking slope stakes (650.9920)LF6,011$0.92$0.92$0.75$0.92
126Sawing asphalt (690.0150)LF209$1.95$3.00$1.95$1.25
127Sawing concrete (690.0250)LF111$2.35$3.00$2.35$2.25
128Incentive strength concrete structures (715.0502)DOL1,510$1.00$1.00$1.00$1.00
129Incentive iri ride (740.0440)DOL4,000$1.00$1.00$1.00$1.00
130Maintaining bird deterrent system (station) 01. sta 12+30 (999.2005.S)EACH1$0.01$100.00$100.00$0.01
131On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS3,200$5.00$5.00$5.00$5.00
132On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS1,800$5.00$5.00$5.00$5.00
133Special 01. town furnished borrow (SPV.0035)CY9,250$8.00$0.01$11.02$8.70
134Special 01. temporary water diversion dual 53-inch X 83-inch culvert pipes station 44+25 (SPV.0060)EACH1$8,600.00$15,205$11,090$0.01
135Special 01. flashing stainless steel (SPV.0090)LF135$64.00$50.00$50.00$82.00
136Special 02. concrete landscaping curb (SPV.0090)LF5$150.00$150.00$150.00$150.00
137Special 01. salvage and reset landscaping (SPV.0165)SF90$30.00$30.00$30.00$30.00
138Special 01. select crushed material for travel corridor (SPV.0195)TON16$74.00$55.81$72.08$50.00
139Special 02. temporary stone ditch checks (SPV.0195)TON230$17.50$27.50$51.11$70.00
WisDOT contract 20250513026: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of May 13, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy