WisDOT contract 20250513026 bid tabulation
6508-00-71. Let by Wisconsin DOT on May 13, 2025, Outagamie. 4 bids received; low bid $2,709,889 by MCC, Inc..
- Owner
- Wisconsin DOT
- Letting
- 13 MAY 2025
- Pay items
- 139
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | MCC, Inc. | $2,709,889 | Low |
| 2 | Vinton Construction Company | $2,731,141 | +1.0% |
| 3 | Northeast Asphalt, Inc | $2,954,774 | +9.0% |
| 4 | James Peterson Sons, Inc. | $3,094,575 | +14% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. MCC, Inc. | 2. Vinton Construction Company | 3. Northeast Asphalt, Inc | 4. James Peterson Sons, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Grubbing (201.0205) | STA | 27 | $459.00 | $273.25 | $372.17 | $273.25 |
| 2 | Grubbing (201.0220) | ID | 46 | $39.00 | $5.28 | $45.95 | $5.28 |
| 3 | Removing small pipe culverts (203.0100) | EACH | 21 | $205.70 | $250.00 | $399.22 | $733.00 |
| 4 | Removing structure (structure) 01. 53X83 CMP (203.0220) | EACH | 2 | $4,800.00 | $2,545.00 | $1,332.16 | $2,344.00 |
| 5 | Removing structure over waterway minimal debris (structure) 01. P-44- 119 (203.0260) | EACH | 1 | $95,000 | $144,000 | $144,000 | $112,800 |
| 6 | Removing concrete pavement (204.0100) | SY | 420 | $5.40 | $5.38 | $10.12 | $7.47 |
| 7 | Removing asphaltic surface (204.0110) | SY | 536 | $5.00 | $4.14 | $7.64 | $4.47 |
| 8 | Removing guardrail (204.0165) | LF | 264 | $7.50 | $2.05 | $7.50 | $7.50 |
| 9 | Removing masonry (204.0185) | CY | 2 | $53.06 | $455.00 | $137.87 | $500.00 |
| 10 | Excavation common (205.0100) | CY | 15,309 | $7.80 | $9.43 | $8.94 | $7.36 |
| 11 | Excavation marsh (205.0400) | CY | 200 | $11.80 | $9.43 | $16.16 | $16.75 |
| 12 | Excavation for structures bridges (structure) 01. B-44-501 (206.1001) | EACH | 1 | $20,000 | $11,500 | $11,500 | $23,000 |
| 13 | Cofferdams (structure) 01. B-44-501 (206.5001) | EACH | 1 | $73,000 | $48,000 | $48,000 | $50,900 |
| 14 | Borrow (208.0100) | CY | 12,141 | $7.50 | $0.01 | $11.57 | $16.58 |
| 15 | Backfill structure type A (210.1500) | TON | 414 | $32.00 | $32.45 | $27.68 | $25.00 |
| 16 | Finishing roadway (project) 01. 6508-00-71 (213.0100) | EACH | 1 | $1,770.00 | $1,000.00 | $866.49 | $5,000.00 |
| 17 | Finishing roadway (project) 02. 6508-01-71 (213.0100) | EACH | 1 | $884.14 | $1,000.00 | $866.49 | $5,000.00 |
| 18 | Base aggregate dense 3/4-inch (305.0110) | TON | 630 | $17.75 | $28.03 | $29.39 | $24.13 |
| 19 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 16,585 | $10.55 | $14.20 | $16.69 | $17.94 |
| 20 | Base aggregate dense 3-inch (305.0130) | TON | 3,460 | $10.85 | $14.20 | $16.85 | $16.75 |
| 21 | Base aggregate open-graded (310.0110) | TON | 10 | $25.00 | $48.70 | $26.44 | $16.56 |
| 22 | Breaker run (311.0110) | TON | 640 | $11.35 | $15.20 | $16.82 | $16.25 |
| 23 | Coloring concrete custom (405.0200) | CY | 2 | $500.00 | $125.00 | $500.00 | $500.00 |
| 24 | Stamping colored concrete (405.1000) | CY | 2 | $1,000.00 | $650.00 | $1,000.00 | $1,000.00 |
| 25 | HMA cold weather paving (450.4000) | TON | 263 | $10.00 | $6.75 | $6.75 | $6.75 |
| 26 | Tack coat (455.0605) | GAL | 1,209 | $4.72 | $3.25 | $3.25 | $3.25 |
| 27 | Incentive density HMA pavement (460.2000) | DOL | 2,830 | $1.00 | $1.00 | $1.00 | $1.00 |
| 28 | HMA pavement 3 LT 58-28 S (460.5223) | TON | 2,480 | $64.58 | $60.10 | $60.10 | $60.10 |
| 29 | HMA pavement 4 LT 58-28 S (460.5224) | TON | 1,930 | $71.30 | $67.10 | $67.10 | $67.10 |
| 30 | Asphaltic surface (465.0105) | TON | 263 | $91.28 | $95.00 | $95.00 | $95.00 |
| 31 | Asphaltic surface driveways and field entrances (465.0120) | TON | 100 | $113.43 | $145.00 | $145.00 | $145.00 |
| 32 | Asphaltic flumes (465.0315) | SY | 28 | $59.08 | $67.00 | $67.00 | $67.00 |
| 33 | Concrete masonry bridges (502.0100) | CY | 252 | $650.00 | $630.00 | $630.00 | $800.00 |
| 34 | Protective surface treatment (502.3200) | SY | 343 | $3.60 | $2.00 | $2.00 | $4.70 |
| 35 | Underwater substructure inspection (structure) 01. B-44-501 (502.9000.S) | EACH | 1 | $500.00 | $5,100.00 | $5,100.00 | $5,100.00 |
| 36 | Concrete masonry endwalls (504.0900) | CY | 20 | $581.00 | $581.00 | $581.00 | $581.00 |
| 37 | Bar steel reinforcement HS structures (505.0400) | LB | 7,230 | $1.20 | $0.91 | $0.91 | $0.96 |
| 38 | Bar steel reinforcement HS coated structures (505.0600) | LB | 36,110 | $1.25 | $1.01 | $1.01 | $1.06 |
| 39 | Railing tubular type M (513.4061) | LF | 150 | $275.00 | $260.00 | $260.00 | $290.00 |
| 40 | Rubberized membrane waterproofing (516.0500) | SY | 14 | $70.00 | $25.00 | $25.00 | $60.00 |
| 41 | Apron endwalls for culvert pipe steel 12-inch (521.1012) | EACH | 16 | $345.00 | $320.00 | $221.22 | $204.00 |
| 42 | Apron endwalls for culvert pipe steel 18-inch (521.1018) | EACH | 12 | $240.00 | $395.00 | $283.50 | $258.00 |
| 43 | Apron endwalls for culvert pipe steel 24-inch (521.1024) | EACH | 12 | $325.00 | $475.00 | $413.15 | $355.00 |
| 44 | Apron endwalls for culvert pipe sloped side drains steel 24-inch 4 to 1 (521.1505) | EACH | 1 | $826.00 | $2,230.00 | $1,492.19 | $2,300.00 |
| 45 | Culvert pipe corrugated steel 18- inch (521.3118) | LF | 314 | $46.75 | $66.35 | $77.97 | $131.00 |
| 46 | Culvert pipe corrugated steel 24- inch (521.3124) | LF | 204 | $52.10 | $80.45 | $92.76 | $189.75 |
| 47 | Culvert pipe reinforced concrete horizontal elliptical class HE-III 19X30-inch (522.2319) | LF | 72 | $215.00 | $155.00 | $185.40 | $257.00 |
| 48 | Culvert pipe reinforced concrete horizontal elliptical class HE-III 24X38-inch (522.2324) | LF | 96 | $270.00 | $182.85 | $253.14 | $296.00 |
| 49 | Culvert pipe reinforced concrete horizontal elliptical class HE-III 53X83-inch (522.2353) | LF | 168 | $735.00 | $590.15 | $644.44 | $991.00 |
| 50 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 19X30-inch (522.2619) | EACH | 4 | $1,735.00 | $1,765.00 | $1,886.81 | $1,641.00 |
| 51 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 24X38-inch (522.2624) | EACH | 4 | $2,350.00 | $2,440.00 | $2,378.80 | $2,092.00 |
| 52 | Pile points (550.0500) | EACH | 27 | $105.00 | $150.00 | $150.00 | $110.00 |
| 53 | Piling steel HP 10-inch X 42 LB (550.1100) | LF | 3,250 | $32.00 | $36.90 | $36.90 | $17.00 |
| 54 | Concrete curb & gutter 6-inch sloped 30-inch type J (601.0415) | LF | 5,465 | $16.10 | $17.65 | $16.10 | $16.10 |
| 55 | Concrete driveway 6-inch (602.0810) | SY | 390 | $64.40 | $72.00 | $64.40 | $64.40 |
| 56 | Riprap light (606.0100) | CY | 685 | $41.15 | $59.95 | $77.10 | $77.75 |
| 57 | Riprap medium (606.0200) | CY | 55 | $65.00 | $76.00 | $81.05 | $90.50 |
| 58 | Riprap heavy (606.0300) | CY | 240 | $85.00 | $67.00 | $88.93 | $90.50 |
| 59 | Storm sewer pipe class III-B 24- inch (608.3624) | LF | 88 | $160.00 | $88.15 | $93.64 | $148.00 |
| 60 | Storm sewer pipe composite 12- inch (608.6012) | LF | 581 | $115.00 | $88.45 | $74.09 | $216.40 |
| 61 | Inlet covers type HM-GJ (611.0630) | EACH | 29 | $730.00 | $657.00 | $855.19 | $880.00 |
| 62 | Inlet covers type MS-A (611.0645) | EACH | 2 | $535.00 | $474.00 | $644.66 | $800.00 |
| 63 | Inlets 2X3-FT (611.3230) | EACH | 29 | $3,600.00 | $2,972.00 | $3,401.64 | $2,758.00 |
| 64 | Inlets median 2 grate (611.3902) | EACH | 1 | $4,750.00 | $4,572.00 | $4,930.18 | $4,867.00 |
| 65 | Pipe underdrain 6-inch (612.0106) | LF | 120 | $36.00 | $21.50 | $20.34 | $31.47 |
| 66 | Pipe underdrain unperforated 6- inch (612.0206) | LF | 30 | $34.00 | $47.40 | $18.44 | $24.26 |
| 67 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 180 | $4.20 | $7.20 | $11.51 | $8.40 |
| 68 | Drain tile exploration (612.0700) | LF | 60 | $36.00 | $15.85 | $25.62 | $15.00 |
| 69 | MGS guardrail 3 (614.2300) | LF | 75 | $32.50 | $32.50 | $32.50 | $32.50 |
| 70 | MGS thrie beam transition (614.2500) | LF | 157.60 | $98.00 | $98.00 | $98.00 | $98.00 |
| 71 | MGS guardrail terminal eat (614.2610) | EACH | 4 | $4,000.00 | $4,000.00 | $4,000.00 | $4,000.00 |
| 72 | Mobilization (619.1000) | EACH | 1 | $299,500 | $425,700 | $175,000 | $230,200 |
| 73 | Landmark reference monuments (621.0100) | EACH | 5 | $50.00 | $50.00 | $150.00 | $50.00 |
| 74 | Water (624.0100) | MGAL | 282.60 | $34.00 | $0.01 | $47.24 | $55.00 |
| 75 | Topsoil (625.0100) | SY | 7,796 | $2.00 | $0.01 | $2.51 | $3.35 |
| 76 | Salvaged topsoil (625.0500) | SY | 30,612 | $0.95 | $2.00 | $4.90 | $1.00 |
| 77 | Mulching (627.0200) | SY | 32,944 | $0.30 | $0.30 | $0.30 | $0.30 |
| 78 | Erosion bales (628.1104) | EACH | 300 | $14.00 | $14.00 | $14.00 | $14.00 |
| 79 | Silt fence (628.1504) | LF | 3,874 | $2.00 | $2.00 | $2.00 | $2.00 |
| 80 | Silt fence maintenance (628.1520) | LF | 3,874 | $0.01 | $0.01 | $0.01 | $0.01 |
| 81 | Mobilizations erosion control (628.1905) | EACH | 9 | $275.00 | $275.00 | $275.00 | $275.00 |
| 82 | Mobilizations emergency erosion control (628.1910) | EACH | 6 | $150.00 | $150.00 | $150.00 | $150.00 |
| 83 | Erosion mat class I type B (628.2004) | SY | 4,207 | $1.42 | $1.42 | $1.42 | $1.42 |
| 84 | Erosion mat urban class I type B (628.2008) | SY | 3,565 | $1.88 | $1.88 | $1.88 | $1.88 |
| 85 | Turbidity barriers (628.6005) | SY | 625 | $48.00 | $48.00 | $48.00 | $48.00 |
| 86 | Inlet protection type A (628.7005) | EACH | 1 | $135.00 | $135.00 | $135.00 | $135.00 |
| 87 | Inlet protection type C (628.7015) | EACH | 40 | $70.00 | $70.00 | $70.00 | $70.00 |
| 88 | Temporary ditch checks (628.7504) | LF | 94 | $8.00 | $8.00 | $8.00 | $8.00 |
| 89 | Culvert pipe checks (628.7555) | EACH | 120 | $14.00 | $14.00 | $14.00 | $14.00 |
| 90 | Tracking pads (628.7560) | EACH | 3 | $1,000.00 | $0.01 | $1,587.14 | $4,500.00 |
| 91 | Rock bags (628.7570) | EACH | 50 | $14.00 | $14.00 | $14.00 | $14.00 |
| 92 | Fertilizer type A (629.0205) | CWT | 26.24 | $100.00 | $100.00 | $100.00 | $100.00 |
| 93 | Seeding mixture no. 20 (630.0120) | LB | 1,457 | $7.25 | $7.25 | $7.25 | $7.25 |
| 94 | Seeding mixture no. 30 (630.0130) | LB | 161 | $8.00 | $8.00 | $8.00 | $8.00 |
| 95 | Seeding mixture no. 40 (630.0140) | LB | 190 | $8.00 | $8.00 | $8.00 | $8.00 |
| 96 | Seeding temporary (630.0200) | LB | 1,083 | $4.00 | $4.00 | $4.00 | $4.00 |
| 97 | Seed water (630.0500) | MGAL | 151 | $1.00 | $1.00 | $1.00 | $1.00 |
| 98 | Markers culvert end (633.5200) | EACH | 6 | $68.00 | $68.00 | $68.00 | $68.00 |
| 99 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 10 | $82.00 | $82.00 | $82.00 | $82.00 |
| 100 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 2 | $86.00 | $86.00 | $86.00 | $86.00 |
| 101 | Signs type II reflective H (637.2210) | SF | 38 | $22.45 | $22.45 | $22.45 | $22.45 |
| 102 | Signs type II reflective F (637.2230) | SF | 12 | $22.75 | $22.75 | $22.75 | $22.75 |
| 103 | Removing signs type II (638.2602) | EACH | 16 | $30.00 | $30.00 | $30.00 | $30.00 |
| 104 | Removing small sign supports (638.3000) | EACH | 16 | $30.00 | $30.00 | $30.00 | $30.00 |
| 105 | Field office type C (642.5201) | EACH | 1 | $12,000 | $9,500.00 | $12,659 | $25,000 |
| 106 | Traffic control drums (643.0300) | DAY | 13,820 | $0.30 | $0.15 | $0.15 | $0.15 |
| 107 | Traffic control barricades type III (643.0420) | DAY | 3,982 | $0.55 | $0.65 | $0.65 | $0.65 |
| 108 | Traffic control warning lights type A (643.0705) | DAY | 6,908 | $0.25 | $0.15 | $0.15 | $0.15 |
| 109 | Traffic control signs (643.0900) | DAY | 4,686 | $0.65 | $0.35 | $0.35 | $0.35 |
| 110 | Traffic control signs PCMS (643.1050) | DAY | 14 | $85.00 | $30.00 | $30.00 | $30.00 |
| 111 | Traffic control (643.5000) | EACH | 1 | $3,500.00 | $12,125 | $12,125 | $12,125 |
| 112 | Geotextile type DF schedule A (645.0111) | SY | 164 | $5.00 | $3.90 | $4.21 | $4.50 |
| 113 | Geotextile type HR (645.0120) | SY | 3,420 | $3.35 | $2.75 | $4.28 | $3.75 |
| 114 | Marking line epoxy 6-inch (646.2020) | LF | 14,098 | $0.67 | $0.67 | $0.67 | $0.67 |
| 115 | Marking stop line epoxy 18-inch (646.6120) | LF | 37 | $18.70 | $18.70 | $19.75 | $18.70 |
| 116 | Locating no-passing zones (648.0100) | MI | 1 | $525.00 | $525.00 | $525.00 | $525.00 |
| 117 | Construction staking storm sewer (650.4000) | EACH | 47 | $90.00 | $90.00 | $90.00 | $90.00 |
| 118 | Construction staking subgrade (650.4500) | LF | 6,011 | $0.01 | $0.01 | $0.01 | $0.01 |
| 119 | Construction staking base (650.5000) | LF | 6,011 | $0.55 | $0.55 | $0.55 | $0.55 |
| 120 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 5,465 | $0.75 | $0.75 | $0.95 | $0.75 |
| 121 | Construction staking pipe culverts (650.6000) | EACH | 19 | $50.00 | $50.00 | $125.00 | $50.00 |
| 122 | Construction staking structure layout (structure) 01. B-44-501 (650.6501) | EACH | 1 | $3,500.00 | $3,500.00 | $3,500.00 | $3,500.00 |
| 123 | Construction staking supplemental control (project) 01. 6508-00-71 (650.9911) | EACH | 1 | $10.00 | $10.00 | $800.00 | $10.00 |
| 124 | Construction staking supplemental control (project) 02. 6508-01-71 (650.9911) | EACH | 1 | $10.00 | $10.00 | $800.00 | $10.00 |
| 125 | Construction staking slope stakes (650.9920) | LF | 6,011 | $0.92 | $0.92 | $0.75 | $0.92 |
| 126 | Sawing asphalt (690.0150) | LF | 209 | $1.95 | $3.00 | $1.95 | $1.25 |
| 127 | Sawing concrete (690.0250) | LF | 111 | $2.35 | $3.00 | $2.35 | $2.25 |
| 128 | Incentive strength concrete structures (715.0502) | DOL | 1,510 | $1.00 | $1.00 | $1.00 | $1.00 |
| 129 | Incentive iri ride (740.0440) | DOL | 4,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 130 | Maintaining bird deterrent system (station) 01. sta 12+30 (999.2005.S) | EACH | 1 | $0.01 | $100.00 | $100.00 | $0.01 |
| 131 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 3,200 | $5.00 | $5.00 | $5.00 | $5.00 |
| 132 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 1,800 | $5.00 | $5.00 | $5.00 | $5.00 |
| 133 | Special 01. town furnished borrow (SPV.0035) | CY | 9,250 | $8.00 | $0.01 | $11.02 | $8.70 |
| 134 | Special 01. temporary water diversion dual 53-inch X 83-inch culvert pipes station 44+25 (SPV.0060) | EACH | 1 | $8,600.00 | $15,205 | $11,090 | $0.01 |
| 135 | Special 01. flashing stainless steel (SPV.0090) | LF | 135 | $64.00 | $50.00 | $50.00 | $82.00 |
| 136 | Special 02. concrete landscaping curb (SPV.0090) | LF | 5 | $150.00 | $150.00 | $150.00 | $150.00 |
| 137 | Special 01. salvage and reset landscaping (SPV.0165) | SF | 90 | $30.00 | $30.00 | $30.00 | $30.00 |
| 138 | Special 01. select crushed material for travel corridor (SPV.0195) | TON | 16 | $74.00 | $55.81 | $72.08 | $50.00 |
| 139 | Special 02. temporary stone ditch checks (SPV.0195) | TON | 230 | $17.50 | $27.50 | $51.11 | $70.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of May 13, 2025. Compiled by Mirage Metrics.