WisDOT contract 20250513024 bid tabulation

Oshkosh - Greenville; Larsen Rd Intersection (STH 076, Winnebago County Oshkosh - Greenville). Let by Wisconsin DOT on May 13, 2025, Winnebago. 5 bids received; low bid $1,740,854 by Northeast Asphalt, Inc.

Owner
Wisconsin DOT
Letting
13 MAY 2025
Pay items
142
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Northeast Asphalt, Inc$1,740,854Low
2Relyco Plus, LLC$1,805,102+4.0%
3MCC, Inc.$1,809,402+4.0%
4Michels Road & Stone, Inc.$1,859,928+7.0%
5James Peterson Sons, Inc.$2,269,661+30%
WisDOT contract 20250513024: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Northeast Asphalt, Inc2. Relyco Plus, LLC3. MCC, Inc.4. Michels Road & Stone, Inc.5. James Peterson Sons, Inc.
1Grubbing (201.0205)STA4$522.33$400.00$499.00$499.00$400.00
2Grubbing (201.0220)ID36$22.71$20.00$29.99$29.99$20.00
3Removing small pipe culverts (203.0100)EACH9$224.47$399.00$175.00$400.00$698.00
4Removing concrete pavement (204.0100)SY67$8.04$6.30$12.75$5.00$25.00
5Removing curb & gutter (204.0150)LF565$5.06$6.00$3.00$5.00$2.50
6Removing fence (204.0170)LF62$5.00$5.00$5.00$5.00$5.00
7Removing inlets (204.0220)EACH3$423.84$294.00$325.00$325.00$750.00
8Removing storm sewer (size) 01. 18-inch (204.0245)LF223$11.52$12.00$15.00$15.00$20.00
9Removing storm sewer (size) 02. 6- inch (204.0245)LF50$3.02$10.00$10.00$10.00$20.00
10Removing storm sewer (size) 03. 4- inch (204.0245)LF16$11.11$10.00$8.00$8.00$20.00
11Excavation common (205.0100)CY17,500$9.98$16.49$10.15$11.50$21.06
12Finishing roadway (project) 01. 6430-24-71 (213.0100)EACH1$1,624.31$2,500.00$3,000.00$4,500.00$5,000.00
13Base aggregate dense 3/4-inch (305.0110)TON990$23.22$25.72$23.65$22.80$30.95
14Base aggregate dense 1 1/4-inch (305.0120)TON5,900$15.40$7.53$13.80$14.30$21.96
15Base aggregate open-graded (310.0115)CY85$31.54$28.00$54.75$70.00$56.73
16Select crushed material (312.0110)TON11,300$15.23$11.45$11.85$11.30$16.69
17Coloring concrete wisdot red (405.0100)CY241$78.40$77.00$78.40$78.40$78.40
18Concrete truck apron 12-inch (415.2010)SY480$83.45$84.62$83.45$83.45$83.45
19Tack coat (455.0605)GAL950$3.25$3.25$4.20$3.25$3.25
20Incentive density HMA pavement (460.2000)DOL3,100$1.00$1.00$1.00$1.00$1.00
21HMA pavement 3 HT 58-28 S (460.7223)TON3,920$65.15$65.15$81.00$65.15$65.15
22HMA pavement 4 HT 58-28 H (460.7424)TON920$86.70$86.70$92.00$86.70$86.70
23Asphaltic surface driveways and field entrances (465.0120)TON22$175.00$175.00$158.00$175.00$175.00
24Asphaltic flumes (465.0315)SY26$60.00$60.00$52.00$60.00$60.00
25Apron endwalls for culvert pipe 30- inch (520.1030)EACH1$709.09$949.00$702.00$702.00$775.00
26Culvert pipe class III-A 18-inch (520.3318)LF82$50.51$68.75$50.00$50.00$71.00
27Apron endwalls for culvert pipe sloped side drains steel 18-inch 6 to 1 (521.1518)EACH4$1,350.51$1,359.00$1,337.00$1,337.00$1,210.00
28Apron endwalls for culvert pipe sloped side drains steel 30-inch 6 to 1 (521.1530)EACH1$3,934.34$3,772.00$3,895.00$3,895.00$3,800.00
29Culvert pipe reinforced concrete class IV 24-inch (522.0424)LF72$140.40$106.00$139.00$139.00$114.00
30Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012)EACH2$1,220.20$1,215.00$1,208.00$1,208.00$1,233.00
31Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024)EACH3$1,676.77$1,608.00$1,660.00$1,660.00$1,642.00
32Concrete curb & gutter 18-inch type A (601.0405)LF230$19.60$22.50$19.60$19.60$19.60
33Concrete curb pedestrian (601.0600)LF104$55.00$40.00$55.00$55.00$55.00
34Concrete sidewalk 4-inch (602.0405)SF13,390$6.45$6.85$6.45$6.45$6.45
35Curb ramp detectable warning field natural patina (602.0515)SF320$30.00$34.00$30.00$30.00$30.00
36Concrete driveway 6-inch (602.0810)SY165$64.35$68.00$64.35$64.35$64.35
37Riprap medium (606.0200)CY30$73.37$95.00$61.00$150.00$89.00
38Storm sewer pipe reinforced concrete class IV 12-inch (608.0412)LF459$78.79$73.75$79.00$79.00$202.92
39Storm sewer pipe reinforced concrete class IV 15-inch (608.0415)LF207$80.81$81.00$82.00$82.00$209.45
40Storm sewer pipe reinforced concrete class IV 24-inch (608.0424)LF176$116.16$119.25$115.00$115.00$226.59
41Storm sewer pipe class III-A 30- inch (608.3030)LF108$102.02$108.00$101.00$101.00$277.60
42Manhole covers type J (611.0530)EACH6$536.36$467.00$531.00$531.00$584.00
43Inlet covers type H (611.0624)EACH9$786.87$691.00$779.00$779.00$898.00
44Inlet covers type HM (611.0627)EACH1$786.87$691.00$779.00$779.00$898.00
45Inlet covers type HM-S (611.0636)EACH1$786.87$691.00$779.00$779.00$898.00
46Inlet covers type H-S (611.0639)EACH3$786.87$691.00$779.00$779.00$898.00
47Inlet covers type MS (611.0642)EACH2$548.49$478.00$543.00$543.00$599.00
48Inlet covers type MS-A (611.0645)EACH1$570.71$498.00$565.00$565.00$999.00
49Inlet covers type T (611.0652)EACH2$1,068.69$943.00$1,058.00$1,058.00$1,251.00
50Manholes 4-FT diameter (611.2004)EACH2$3,545.46$3,779.00$3,510.00$3,510.00$3,642.00
51Manholes 5-FT diameter (611.2005)EACH4$5,645.46$5,401.00$5,589.00$5,589.00$5,655.00
52Inlets 4-FT diameter (611.3004)EACH5$3,485.86$3,451.00$3,451.00$3,451.00$3,052.00
53Inlets 2X3-FT (611.3230)EACH9$2,738.38$2,712.00$2,711.00$2,711.00$2,293.00
54Inlets median 1 grate (611.3901)EACH3$3,191.92$3,109.00$3,160.00$3,160.00$3,145.00
55Pipe underdrain 4-inch (612.0104)LF120$10.47$22.00$20.00$32.00$20.00
56Pipe underdrain 6-inch (612.0106)LF1,825$6.34$18.50$23.00$13.60$12.44
57Apron endwalls for underdrain reinforced concrete 6-inch (612.0806)EACH2$259.60$323.00$257.00$257.00$400.00
58Maintenance and repair of haul roads (project) 01. 6430-24-71 (618.0100)EACH1$546.37$0.01$1.00$0.01$100.00
59Mobilization (619.1000)EACH1$78,000$110,500$103,500$196,779$193,020
60Concrete median sloped nose (620.0300)SF370$12.00$14.00$12.00$12.00$12.00
61Water (624.0100)MGAL350$35.89$0.01$35.95$30.00$45.00
62Topsoil (625.0100)SY8,000$4.43$3.81$3.30$3.80$5.12
63Mulching (627.0200)SY500$0.55$0.55$0.55$0.55$0.55
64Silt fence (628.1504)LF1,500$2.00$2.00$2.00$2.00$2.00
65Silt fence maintenance (628.1520)LF1,500$0.01$0.01$0.01$0.01$0.01
66Mobilizations erosion control (628.1905)EACH6$250.00$250.00$250.00$250.00$250.00
67Mobilizations emergency erosion control (628.1910)EACH4$150.00$150.00$150.00$150.00$150.00
68Erosion mat urban class I type B (628.2008)SY8,000$1.78$1.78$1.78$1.78$1.78
69Inlet protection type A (628.7005)EACH21$25.00$25.00$25.00$25.00$25.00
70Inlet protection type C (628.7015)EACH16$68.00$68.00$68.00$68.00$68.00
71Temporary ditch checks (628.7504)LF120$8.25$8.25$8.25$8.25$8.25
72Culvert pipe checks (628.7555)EACH12$15.00$15.00$15.00$15.00$15.00
73Tracking pads (628.7560)EACH3$1,128.14$0.01$1,055.00$100.00$3,000.00
74Rock bags (628.7570)EACH20$15.00$15.00$15.00$15.00$15.00
75Fertilizer type B (629.0210)CWT5$110.00$110.00$110.00$110.00$110.00
76Seeding mixture no. 40 (630.0140)LB350$8.25$8.25$8.25$8.25$8.25
77Seeding temporary (630.0200)LB50$4.00$4.00$4.00$4.00$4.00
78Seed water (630.0500)MGAL450$5.00$5.00$5.00$5.00$5.00
79Markers culvert end (633.5200)EACH2$70.00$70.00$70.00$70.00$70.00
80Posts wood 4X6-inch X 12-FT (634.0612)EACH8$82.00$82.00$82.00$82.00$82.00
81Posts wood 4X6-inch X 14-FT (634.0614)EACH27$86.00$86.00$86.00$86.00$86.00
82Posts wood 4X6-inch X 18-FT (634.0618)EACH12$90.00$90.00$90.00$90.00$90.00
83Posts tubular steel 2X2-inch X 14- FT (634.0814)EACH2$210.00$210.00$210.00$210.00$210.00
84Signs type II reflective H (637.2210)SF287.54$21.95$21.95$21.95$21.95$21.95
85Signs type II reflective F (637.2230)SF65.24$22.80$22.80$22.80$22.80$22.80
86Removing signs type II (638.2602)EACH7$35.00$35.00$35.00$35.00$35.00
87Removing small sign supports (638.3000)EACH11$35.00$35.00$35.00$35.00$35.00
88Field office type C (642.5201)EACH1$11,539$9,500.00$12,000$15,000$10,000
89Traffic control drums (643.0300)DAY200$1.00$1.00$1.00$1.00$1.00
90Traffic control barricades type III (643.0420)DAY2,600$1.50$1.50$1.50$1.50$1.50
91Traffic control warning lights type A (643.0705)DAY5,200$0.25$0.25$0.25$0.25$0.25
92Traffic control signs (643.0900)DAY27,380$0.17$0.17$0.17$0.17$0.17
93Traffic control covering signs type I (643.0910)EACH4$245.00$245.00$245.00$245.00$245.00
94Traffic control covering signs type II (643.0920)EACH9$105.00$105.00$105.00$105.00$105.00
95Traffic control signs fixed message (643.1000)SF104$30.25$30.25$30.25$30.25$30.25
96Traffic control signs PCMS (643.1050)DAY42$18.50$18.50$18.50$18.50$18.50
97Traffic control (643.5000)EACH1$11,550$11,550$11,550$11,550$11,550
98Temporary pedestrian barricade (644.1810)LF12$15.00$15.00$15.00$15.00$15.00
99Geotextile type DF schedule A (645.0111)SY1,230$1.14$2.00$0.75$6.00$3.10
100Geotextile type HR (645.0120)SY140$3.99$5.00$2.50$6.00$8.56
101Marking line epoxy 6-inch (646.2020)LF6,240$0.60$0.60$0.70$0.60$0.70
102Marking line grooved wet ref epoxy 6-inch (646.2040)LF6,945$1.56$1.56$1.60$1.56$1.60
103Marking outfall epoxy (646.5520)EACH2$50.00$50.00$160.00$50.00$160.00
104Marking dotted extension epoxy 18-inch (646.6320)LF78$15.50$15.50$13.00$15.50$13.00
105Marking diagonal epoxy 12-inch (646.7120)LF290$15.50$15.50$6.50$15.50$6.50
106Marking crosswalk epoxy transverse line 6-inch (646.7420)LF270$15.00$15.50$11.00$15.00$11.00
107Marking curb epoxy (646.8120)LF220$7.50$7.50$5.50$7.50$5.50
108Marking island nose epoxy (646.8220)EACH4$295.00$295.00$250.00$295.00$250.00
109Construction staking storm sewer (650.4000)EACH30$42.31$42.31$42.31$42.31$42.31
110Construction staking subgrade (650.4500)LF1,080$0.01$0.01$0.01$0.01$0.01
111Construction staking base (650.5000)LF1,080$1.21$1.21$1.21$1.21$1.21
112Construction staking curb gutter and curb & gutter (650.5500)LF301$0.65$0.65$0.65$0.65$0.65
113Construction staking pipe culverts (650.6000)EACH3$106.09$106.09$106.09$106.09$106.90
114Construction staking electrical installations (project) 01. 6430-24- 71 (650.8501)EACH1$1,310.68$1,310.68$1,310.68$1,310.68$1,310.68
115Construction staking sidewalk (project) 01. 6430-24-71 (650.9500)EACH1$1,740.70$1,740.70$1,740.70$1,740.70$1,740.70
116Construction staking supplemental control (project) 01. 6430-24-71 (650.9911)EACH1$422.81$422.81$422.81$422.81$422.81
117Construction staking slope stakes (650.9920)LF1,080$0.84$0.84$0.84$0.84$0.84
118Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF1,790$10.00$10.00$10.00$10.00$10.00
119Pull boxes non-conductive 24X42- inch (653.0164)EACH8$1,950.00$1,950.00$1,950.00$1,950.00$1,950.00
120Concrete bases type 5 (654.0105)EACH18$1,775.00$1,775.00$1,775.00$1,775.00$1,775.00
121Concrete control cabinet bases type 10 (654.0220)EACH1$2,000.00$2,000.00$2,000.00$2,000.00$2,000.00
122Electrical wire lighting 12 AWG (655.0610)LF2,700$0.80$0.80$0.80$0.80$0.80
123Electrical wire lighting 10 AWG (655.0615)LF7,700$0.90$0.90$0.90$0.90$0.90
124Electrical service meter breaker pedestal (location) 01. STH 76 & larsen road (656.0201)EACH1$1,900.00$1,900.00$1,900.00$1,900.00$1,900.00
125Transformer bases breakaway 11 1/2-inch bolt circle (657.0255)EACH18$600.00$600.00$600.00$600.00$600.00
126Poles type 5-aluminum (657.0322)EACH18$1,650.00$1,650.00$1,650.00$1,650.00$1,650.00
127Luminaire arms truss type 4 1/2- inch clamp 12-FT (657.0710)EACH18$625.00$625.00$625.00$625.00$625.00
128Luminaires utility LED A (659.1115)EACH18$350.00$350.00$350.00$350.00$350.00
129Sawing asphalt (690.0150)LF154$1.95$1.95$1.95$1.95$1.95
130Sawing concrete (690.0250)LF42$2.35$2.35$2.35$2.35$2.35
131On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS1,200$5.00$5.00$5.00$5.00$5.00
132On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS600$5.00$5.00$5.00$5.00$5.00
133Special 01. foundation backfill (SPV.0035)CY130$32.32$35.00$30.60$32.00$44.38
134Special 01. construction staking roundabout (SPV.0060)EACH1$6,650.00$6,650.00$6,650.00$6,650.00$6,650.00
135Special 02. inlets 4-FT diameter, special (SPV.0060)EACH2$3,458.59$3,868.00$3,424.00$3,424.00$3,147.00
136Special 03. removing sign, foundation and landscaping - parcel 6 (SPV.0060)EACH1$1,713.99$2,800.00$2,800.00$2,800.00$2,800.00
137Special 01. seeding low maintenance fescue (SPV.0085)LB25$15.00$15.00$15.00$15.00$15.00
138Special 01. concrete curb & gutter 30-inch type D modified (SPV.0090)LF2,597$20.45$19.15$20.45$20.45$20.45
139Special 02. concrete curb & gutter 4-inch sloped 36-inch type A modified (SPV.0090)LF178$24.40$27.00$24.40$24.40$24.40
140Special 03. concrete curb & gutter 4-inch sloped 36-inch type D modified (SPV.0090)LF1,000$24.40$23.95$24.40$24.40$24.40
141Special 04. concrete curb & gutter 4-inch sloped 36-inch type R modified (SPV.0090)LF318$24.40$24.00$24.40$24.40$24.40
142Special 01. traffic bond limestone 3/8-inch (SPV.0195)TON53$44.36$40.00$38.00$40.00$35.00
WisDOT contract 20250513024: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of May 13, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way