WisDOT contract 20260310026 bid tabulation
Westfield - STH 22; 7th Court to CTH B (CTH E, Marquette County Westfield - STH 22). Let by Wisconsin DOT on March 10, 2026, Marquette. 3 bids received; low bid $2,322,324 by D L Gasser Construction.
- Owner
- Wisconsin DOT
- Letting
- 10 MAR 2026
- Pay items
- 56
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D L Gasser Construction | $2,322,324 | Low |
| 2 | Northeast Asphalt, Inc | $2,521,674 | +9.0% |
| 3 | Tri-County Paving, Inc. | $2,629,971 | +13% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D L Gasser Construction | 2. Northeast Asphalt, Inc | 3. Tri-County Paving, Inc. |
|---|---|---|---|---|---|---|
| 1 | Removing asphaltic surface butt joints (204.0115) | SY | 73 | $14.40 | $14.25 | $12.00 |
| 2 | Removing asphaltic surface milling (204.0120) | SY | 66,200 | $1.45 | $5.80 | $1.70 |
| 3 | Removing fence (204.0170) | LF | 52 | $20.00 | $10.00 | $10.00 |
| 4 | Excavation common (205.0100) | CY | 2,399 | $15.95 | $12.25 | $15.85 |
| 5 | Borrow (208.0100) | CY | 82 | $0.01 | $30.00 | $0.01 |
| 6 | Prepare foundation for asphaltic paving (project) 01. 6694-04-71 (211.0101) | EACH | 1 | $11,995 | $69,250 | $94,500 |
| 7 | Finishing roadway (project) 01. 6694-04-71 (213.0100) | EACH | 1 | $1.00 | $1,500.00 | $10,000 |
| 8 | Base aggregate dense 3/4-inch (305.0110) | TON | 3,863 | $27.05 | $36.39 | $32.00 |
| 9 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 1,300 | $21.48 | $12.00 | $21.35 |
| 10 | Base aggregate dense 3-inch (305.0130) | TON | 2,860 | $21.48 | $12.00 | $21.35 |
| 11 | Tack coat (455.0605) | GAL | 9,300 | $0.01 | $1.00 | $2.75 |
| 12 | Incentive density HMA pavement (460.2000) | DOL | 15,300 | $1.00 | $1.00 | $1.00 |
| 13 | HMA pavement 3 MT 58-28 S (460.6223) | TON | 15,150 | $67.40 | $54.30 | $67.20 |
| 14 | HMA pavement 4 MT 58-28 S (460.6224) | TON | 8,670 | $72.60 | $62.40 | $71.70 |
| 15 | Asphaltic surface driveways and field entrances (465.0120) | TON | 33 | $175.00 | $235.00 | $128.90 |
| 16 | Asphaltic rumble strips, centerline (465.0560) | LF | 5,139 | $0.78 | $0.43 | $1.00 |
| 17 | Salvaged rail (614.0920) | LF | 484 | $5.00 | $5.00 | $6.00 |
| 18 | MGS guardrail 3 (614.2300) | LF | 751.50 | $26.00 | $30.00 | $26.00 |
| 19 | MGS guardrail 3 K (614.2330) | LF | 125 | $42.00 | $42.00 | $38.00 |
| 20 | MGS guardrail 3 L (614.2340) | LF | 900 | $28.00 | $37.00 | $28.00 |
| 21 | MGS guardrail short radius (614.2350) | LF | 67 | $28.00 | $50.00 | $38.00 |
| 22 | MGS guardrail terminal eat (614.2610) | EACH | 19 | $3,353.00 | $5,100.00 | $4,000.00 |
| 23 | MGS guardrail short radius terminal (614.2630) | EACH | 1 | $2,533.00 | $3,500.00 | $3,000.00 |
| 24 | Maintenance and repair of haul roads (project) 01. 6694-04-71 (618.0100) | EACH | 1 | $1,000.00 | $1.00 | $4,000.00 |
| 25 | Mobilization (619.1000) | EACH | 1 | $21,955 | $114,500 | $150,000 |
| 26 | Water (624.0100) | MGAL | 66.80 | $20.00 | $0.01 | $50.00 |
| 27 | Salvaged topsoil (625.0500) | SY | 3,521 | $4.36 | $5.00 | $4.33 |
| 28 | Mulching (627.0200) | SY | 3,503 | $0.40 | $0.65 | $0.50 |
| 29 | Mobilizations erosion control (628.1905) | EACH | 3 | $383.00 | $350.00 | $200.00 |
| 30 | Mobilizations emergency erosion control (628.1910) | EACH | 2 | $295.00 | $150.00 | $200.00 |
| 31 | Erosion mat urban class I type A (628.2006) | SY | 1,191 | $2.99 | $2.00 | $1.80 |
| 32 | Erosion mat class III type D (628.2039) | SY | 60 | $25.00 | $20.00 | $14.00 |
| 33 | Soil stabilizer type A (628.6505) | ACRE | 0.03 | $10,000 | $500.00 | $4,000.00 |
| 34 | Temporary ditch checks (628.7504) | LF | 60 | $11.35 | $8.00 | $12.00 |
| 35 | Culvert pipe checks (628.7555) | EACH | 1 | $50.00 | $50.00 | $500.00 |
| 36 | Tracking pads (628.7560) | EACH | 1 | $0.01 | $1.00 | $0.01 |
| 37 | Fertilizer type B (629.0210) | CWT | 8.56 | $105.00 | $250.00 | $90.00 |
| 38 | Seeding mixture no. 30 (630.0130) | LB | 180 | $12.00 | $10.00 | $12.00 |
| 39 | Seeding mixture no. 60 (630.0160) | LB | 3.31 | $45.00 | $100.00 | $80.00 |
| 40 | Seeding borrow pit (630.0300) | LB | 33 | $10.00 | $8.00 | $12.00 |
| 41 | Seed water (630.0500) | MGAL | 96 | $5.00 | $10.00 | $40.00 |
| 42 | Field office type C (642.5201) | EACH | 1 | $6,300.00 | $8,100.00 | $20,000 |
| 43 | Traffic control barricades type III (643.0420) | DAY | 552 | $0.51 | $1.00 | $1.43 |
| 44 | Traffic control warning lights type A (643.0705) | DAY | 1,104 | $0.15 | $0.75 | $0.68 |
| 45 | Traffic control signs (643.0900) | DAY | 1,794 | $0.30 | $1.00 | $0.68 |
| 46 | Traffic control (643.5000) | EACH | 1 | $8,160.80 | $4,150.00 | $8,973.00 |
| 47 | Marking line grooved wet ref epoxy 4-inch (646.1040) | LF | 88,820 | $0.77 | $0.77 | $0.77 |
| 48 | Construction staking resurfacing reference (650.8000) | LF | 26,022 | $0.15 | $0.14 | $0.15 |
| 49 | Construction staking supplemental control (project) 01. 6694-04-71 (650.9911) | EACH | 1 | $800.00 | $2,000.00 | $800.00 |
| 50 | Construction staking slope stakes (650.9920) | LF | 2,766 | $0.89 | $0.75 | $0.89 |
| 51 | Sawing asphalt (690.0150) | LF | 1,846 | $1.49 | $1.49 | $3.00 |
| 52 | Incentive iri ride (740.0440) | DOL | 19,714 | $1.00 | $1.00 | $1.00 |
| 53 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,000 | $5.00 | $5.00 | $5.00 |
| 54 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 1,260 | $5.00 | $5.00 | $5.00 |
| 55 | Special 01. research and locate existing land parcel monuments (SPV.0060) | EACH | 7 | $87.00 | $175.00 | $87.00 |
| 56 | Special 02. verify and replace existing land parcel monuments (SPV.0060) | EACH | 7 | $87.00 | $100.00 | $87.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of March 10, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.