WisDOT contract 20250114020 bid tabulation
V Vernon-Center Dr; Bridge Over Fox River P67-0100 (LOC STR, Waukesha County V Vernon - Center Dr). Let by Wisconsin DOT on January 14, 2025, Waukesha. 3 bids received; low bid $1,739,086 by Lunda Construction Company.
- Owner
- Wisconsin DOT
- Letting
- 14 JAN 2025
- Pay items
- 100
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Lunda Construction Company | $1,739,086 | Low |
| 2 | Zenith Tech., Inc. - Waukesha | $1,868,192 | +7.0% |
| 3 | Sheet Piling Services LLC | $2,090,323 | +20% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Lunda Construction Company | 2. Zenith Tech., Inc. - Waukesha | 3. Sheet Piling Services LLC |
|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 1 | $750.00 | $1,500.00 | $1,706.10 |
| 2 | Clearing (201.0120) | ID | 20 | $50.00 | $40.00 | $22.75 |
| 3 | Grubbing (201.0205) | STA | 1 | $500.00 | $500.00 | $1,185.13 |
| 4 | Grubbing (201.0220) | ID | 20 | $25.00 | $40.00 | $23.70 |
| 5 | Removing small pipe culverts (203.0100) | EACH | 2 | $500.00 | $850.00 | $500.00 |
| 6 | Removing structure over waterway minimal debris (structure) 01. P-67- 0100 (203.0260) | EACH | 1 | $200,000 | $150,000 | $275,000 |
| 7 | Removing curb & gutter (204.0150) | LF | 40 | $15.00 | $8.35 | $11.00 |
| 8 | Removing guardrail (204.0165) | LF | 540 | $5.00 | $3.00 | $3.00 |
| 9 | Removing surface drains (204.0190) | EACH | 4 | $350.00 | $50.00 | $215.00 |
| 10 | Excavation common (205.0100) | CY | 343 | $21.00 | $25.00 | $44.00 |
| 11 | Excavation for structures bridges (structure) 01. B-67-402 (206.1001) | EACH | 1 | $42,000 | $30,000 | $150,000 |
| 12 | Cofferdams (structure) 01. B-67-402 (206.5001) | EACH | 3 | $15,000 | $25,000 | $22,000 |
| 13 | Borrow (208.0100) | CY | 392 | $12.00 | $35.00 | $9.00 |
| 14 | Backfill structure type A (210.1500) | TON | 140 | $26.00 | $34.00 | $48.00 |
| 15 | Finishing roadway (project) 01. 2719-00-71 (213.0100) | EACH | 1 | $100.00 | $500.00 | $0.01 |
| 16 | Base aggregate dense 3/4-inch (305.0110) | TON | 157 | $40.00 | $43.00 | $56.00 |
| 17 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 795 | $25.00 | $29.80 | $28.00 |
| 18 | Concrete pavement 10-inch (415.0100) | SY | 10 | $75.00 | $75.00 | $256.64 |
| 19 | Concrete pavement approach slab (415.0410) | SY | 80 | $230.00 | $230.00 | $354.22 |
| 20 | Tack coat (455.0605) | GAL | 60 | $8.00 | $2.50 | $8.00 |
| 21 | Incentive density HMA pavement (460.2000) | DOL | 70 | $1.00 | $1.00 | $1.00 |
| 22 | HMA pavement 3 LT 58-28 S (460.5223) | TON | 57 | $220.00 | $220.00 | $220.00 |
| 23 | HMA pavement 4 LT 58-28 S (460.5224) | TON | 45 | $240.00 | $240.00 | $240.00 |
| 24 | Asphaltic surface (465.0105) | TON | 48 | $225.00 | $335.00 | $225.00 |
| 25 | Concrete masonry bridges (502.0100) | CY | 589.90 | $965.00 | $900.00 | $1,020.00 |
| 26 | Protective surface treatment (502.3200) | SY | 773 | $5.00 | $4.00 | $5.00 |
| 27 | Underwater substructure inspection (structure) 01. B-67-402 (502.9000.S) | EACH | 2 | $5,200.00 | $5,000.00 | $5,200.00 |
| 28 | Bar steel reinforcement HS structures (505.0400) | LB | 8,820 | $0.95 | $1.05 | $1.35 |
| 29 | Bar steel reinforcement HS coated structures (505.0600) | LB | 85,080 | $1.15 | $1.25 | $1.45 |
| 30 | Piling steel sheet temporary (512.1000) | SF | 495 | $15.00 | $25.00 | $25.00 |
| 31 | Railing tubular type M (513.4061) | LF | 179 | $250.00 | $250.00 | $270.00 |
| 32 | Railing steel type NY4 (513.7084) | LF | 179 | $350.00 | $325.00 | $330.00 |
| 33 | Rubberized membrane waterproofing (516.0500) | SY | 22 | $35.00 | $60.00 | $35.00 |
| 34 | Culvert pipe reinforced concrete horizontal elliptical class HE-III 34X53-inch (522.2334) | LF | 80 | $286.50 | $800.00 | $772.00 |
| 35 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 34X53-inch (522.2634) | EACH | 4 | $2,810.00 | $4,900.00 | $3,300.00 |
| 36 | Culvert pipe corrugated polyethylene 12-inch (530.0112) | LF | 96 | $90.00 | $35.40 | $95.00 |
| 37 | Pre-boring unconsolidated materials (550.0010) | LF | 140 | $65.00 | $200.00 | $50.00 |
| 38 | Pile points (550.0500) | EACH | 32 | $125.00 | $110.00 | $200.00 |
| 39 | Piling steel HP 10-inch X 42 LB (550.1100) | LF | 735 | $38.00 | $42.50 | $52.00 |
| 40 | Piling steel HP 12-inch X 53 LB (550.1120) | LF | 1,125 | $43.00 | $52.50 | $58.00 |
| 41 | Concrete curb & gutter 30-inch type A (601.0409) | LF | 33 | $35.00 | $35.00 | $64.96 |
| 42 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 262 | $30.00 | $30.00 | $52.26 |
| 43 | Concrete sidewalk 4-inch (602.0405) | SF | 177 | $8.00 | $8.00 | $11.38 |
| 44 | Concrete surface drains (602.3010) | CY | 2 | $1,100.00 | $1,100.00 | $1,596.73 |
| 45 | Riprap medium (606.0200) | CY | 46 | $110.00 | $135.00 | $113.00 |
| 46 | Riprap heavy (606.0300) | CY | 360 | $105.00 | $135.00 | $120.00 |
| 47 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 200 | $12.00 | $16.00 | $8.00 |
| 48 | MGS guardrail 3 (614.2300) | LF | 52 | $30.00 | $35.00 | $29.10 |
| 49 | MGS thrie beam transition (614.2500) | LF | 160 | $99.00 | $98.00 | $99.10 |
| 50 | MGS guardrail terminal eat (614.2610) | EACH | 4 | $5,000.00 | $4,000.00 | $4,100.00 |
| 51 | Maintenance and repair of haul roads (project) 01. 2719-00-71 (618.0100) | EACH | 1 | $1.00 | $500.00 | $0.01 |
| 52 | Mobilization (619.1000) | EACH | 1 | $172,331 | $140,000 | $176,671 |
| 53 | Water (624.0100) | MGAL | 120 | $50.00 | $70.00 | $30.00 |
| 54 | Salvaged topsoil (625.0500) | SY | 1,200 | $6.00 | $2.80 | $8.80 |
| 55 | Mulching (627.0200) | SY | 1,200 | $0.50 | $0.25 | $0.01 |
| 56 | Silt fence (628.1504) | LF | 408 | $2.50 | $2.50 | $2.15 |
| 57 | Silt fence maintenance (628.1520) | LF | 408 | $0.01 | $0.25 | $0.10 |
| 58 | Silt fence heavy duty (628.1530.S) | LF | 778 | $9.00 | $13.50 | $13.00 |
| 59 | Silt fence heavy duty maintenance (628.1535.S) | LF | 778 | $0.01 | $5.00 | $0.01 |
| 60 | Mobilizations erosion control (628.1905) | EACH | 3 | $250.00 | $250.00 | $100.00 |
| 61 | Mobilizations emergency erosion control (628.1910) | EACH | 3 | $250.00 | $300.00 | $1.00 |
| 62 | Erosion mat class II type C (628.2027) | SY | 1,200 | $8.00 | $3.95 | $3.97 |
| 63 | Culvert pipe checks (628.7555) | EACH | 20 | $15.00 | $17.50 | $25.00 |
| 64 | Fertilizer type B (629.0210) | CWT | 0.80 | $250.00 | $200.00 | $90.00 |
| 65 | Seeding mixture no. 30 (630.0130) | LB | 22 | $15.00 | $35.00 | $13.00 |
| 66 | Seeding temporary (630.0200) | LB | 22 | $15.00 | $10.00 | $3.00 |
| 67 | Seed water (630.0500) | MGAL | 27 | $10.00 | $100.00 | $33.00 |
| 68 | Markers culvert end (633.5200) | EACH | 5 | $85.00 | $55.00 | $58.75 |
| 69 | Posts tubular steel 2X2-inch X 14- FT (634.0814) | EACH | 4 | $250.00 | $225.00 | $230.00 |
| 70 | Posts tubular steel 2X2-inch X 16- FT (634.0816) | EACH | 4 | $250.00 | $250.00 | $230.00 |
| 71 | Signs type II reflective H (637.2210) | SF | 14 | $40.00 | $35.00 | $30.00 |
| 72 | Signs type II reflective F (637.2230) | SF | 12 | $40.00 | $35.00 | $30.00 |
| 73 | Removing signs type II (638.2602) | EACH | 8 | $50.00 | $40.00 | $10.00 |
| 74 | Removing small sign supports (638.3000) | EACH | 8 | $100.00 | $40.00 | $15.00 |
| 75 | Moving small sign supports (638.4000) | EACH | 4 | $100.00 | $75.00 | $40.00 |
| 76 | Field office type B (642.5001) | EACH | 1 | $5,000.00 | $10,000 | $3,000.00 |
| 77 | Traffic control barricades type III (643.0420) | DAY | 2,576 | $0.45 | $0.45 | $0.45 |
| 78 | Traffic control warning lights type A (643.0705) | DAY | 3,680 | $0.15 | $0.15 | $0.15 |
| 79 | Traffic control signs (643.0900) | DAY | 7,360 | $0.30 | $0.30 | $0.30 |
| 80 | Traffic control signs PCMS (643.1050) | DAY | 14 | $50.00 | $50.00 | $50.00 |
| 81 | Traffic control (643.5000) | EACH | 1 | $1,700.00 | $1,700.00 | $1,700.00 |
| 82 | Geotextile type DF schedule A (645.0111) | SY | 72 | $7.00 | $6.00 | $6.00 |
| 83 | Geotextile type HR (645.0120) | SY | 315 | $7.00 | $3.00 | $5.00 |
| 84 | Marking line epoxy 4-inch (646.1020) | LF | 1,538 | $3.40 | $3.00 | $2.75 |
| 85 | Construction staking subgrade (650.4500) | LF | 652 | $0.01 | $0.01 | $0.01 |
| 86 | Construction staking base (650.5000) | LF | 618 | $2.00 | $1.50 | $2.00 |
| 87 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 295 | $3.00 | $2.00 | $3.00 |
| 88 | Construction staking pipe culverts (650.6000) | EACH | 3 | $180.00 | $200.00 | $180.00 |
| 89 | Construction staking structure layout (structure) 01. B-67-402 (650.6501) | EACH | 1 | $3,200.00 | $8,000.00 | $3,200.00 |
| 90 | Construction staking supplemental control (project) 01. 2719-00-71 (650.9911) | EACH | 1 | $1,500.00 | $1,000.00 | $1,500.00 |
| 91 | Construction staking slope stakes (650.9920) | LF | 618 | $1.00 | $1.50 | $1.00 |
| 92 | Sawing asphalt (690.0150) | LF | 584 | $1.85 | $1.95 | $1.15 |
| 93 | Incentive strength concrete structures (715.0502) | DOL | 3,539.40 | $1.00 | $1.00 | $1.00 |
| 94 | Incentive compressive strength concrete pavement (715.0720) | DOL | 500 | $1.00 | $1.00 | $1.00 |
| 95 | Installing and maintaining bird deterrent system (station) 01. 25+50 (999.2000.S) | EACH | 1 | $0.01 | $0.01 | $0.01 |
| 96 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 1,600 | $5.00 | $5.00 | $5.00 |
| 97 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 3,200 | $5.00 | $5.00 | $5.00 |
| 98 | Special 01. temporary causeway (SPV.0060) | EACH | 1 | $15,000 | $125,000 | $0.01 |
| 99 | Special 01. flashing stainless steel (SPV.0090) | LF | 153 | $45.00 | $60.00 | $55.00 |
| 100 | Special 01. enhanced turbidity barrier (SPV.0180) | SY | 387 | $65.00 | $50.00 | $50.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of January 14, 2025. Compiled by Mirage Metrics.