WisDOT contract 20250114038 bid tabulation
Bayfield - Cornucopia; Sand River Bridge B-04-0011 (STH 013, Bayfield County Bayfield - Cornucopia). Let by Wisconsin DOT on January 14, 2025, Bayfield. 2 bids received; low bid $746,767 by Zenith Tech., Inc. - Waukesha.
- Owner
- Wisconsin DOT
- Letting
- 14 JAN 2025
- Pay items
- 60
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Zenith Tech., Inc. - Waukesha | $746,767 | Low |
| 2 | Lunda Construction Company | $900,331 | +21% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Zenith Tech., Inc. - Waukesha | 2. Lunda Construction Company |
|---|---|---|---|---|---|
| 1 | Removing structure (structure) 01. B-4-11 (203.0220) | EACH | 1 | $79,000 | $157,000 |
| 2 | Debris containment over waterway (structure) 01. B-4-11 (203.0335) | EACH | 1 | $2,500.00 | $500.00 |
| 3 | Removing concrete pavement (204.0100) | SY | 133 | $40.00 | $25.25 |
| 4 | Excavation common (205.0100) | CY | 72 | $60.00 | $49.75 |
| 5 | Finishing roadway (project) 01. 8510-00-72 (213.0100) | EACH | 1 | $500.00 | $500.00 |
| 6 | Base aggregate dense 3/4-inch (305.0110) | TON | 20 | $150.00 | $120.00 |
| 7 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 105 | $80.00 | $47.50 |
| 8 | Concrete pavement approach slab (415.0410) | SY | 94 | $338.08 | $338.08 |
| 9 | Tack coat (455.0605) | GAL | 36 | $4.03 | $4.03 |
| 10 | Asphaltic surface (465.0105) | TON | 60 | $292.82 | $292.82 |
| 11 | Concrete masonry bridges (502.0100) | CY | 26 | $2,500.00 | $875.00 |
| 12 | Expansion device (502.3101) | LF | 60 | $325.00 | $225.00 |
| 13 | Protective surface treatment (502.3200) | SY | 62 | $4.00 | $4.25 |
| 14 | Adhesive anchors no. 5 bar (502.4205) | EACH | 64 | $30.00 | $30.70 |
| 15 | Bar steel reinforcement HS coated structures (505.0600) | LB | 8,870 | $3.00 | $3.00 |
| 16 | Bar couplers no. 5 (505.0905) | EACH | 26 | $55.00 | $46.00 |
| 17 | Bridge jacking (structure) 01. B-4- 11 (506.7061.S) | EACH | 1 | $6,500.00 | $15,500 |
| 18 | Joint repair (509.1000) | SY | 29 | $1,500.00 | $1,500.00 |
| 19 | Concrete surface repair (509.1500) | SF | 130 | $185.00 | $250.00 |
| 20 | Railing tubular type M (513.4061) | LF | 134 | $250.00 | $365.00 |
| 21 | Preparation and coating of top flanges (structure) 01. B-4-11 (517.0901.S) | EACH | 1 | $8,200.00 | $8,200.00 |
| 22 | Structure repainting recycled abrasive (structure) 01. B-4-11 (517.1801.S) | EACH | 1 | $65,200 | $65,200 |
| 23 | Negative pressure containment and collection of waste materials (structure) 01. B-4-11 (517.4501.S) | EACH | 1 | $29,500 | $29,500 |
| 24 | Portable decontamination facility 01. B-4-11 (517.6001.S) | EACH | 1 | $5,600.00 | $5,600.00 |
| 25 | Concrete barrier temporary precast delivered (603.8000) | LF | 500 | $30.00 | $20.00 |
| 26 | Concrete barrier temporary precast installed (603.8125) | LF | 1,000 | $5.00 | $15.00 |
| 27 | Anchoring concrete barrier temporary precast (603.8500) | LF | 725 | $0.01 | $20.00 |
| 28 | Adjusting steel plate beam guard (614.0400) | LF | 50 | $31.00 | $72.50 |
| 29 | Crash cushions temporary (614.0905) | EACH | 2 | $4,000.00 | $4,000.00 |
| 30 | Replacing guardrail posts and blocks (614.0950) | EACH | 30 | $167.00 | $167.50 |
| 31 | Maintenance and repair of haul roads (project) 01. 8510-00-72 (618.0100) | EACH | 1 | $500.00 | $500.00 |
| 32 | Mobilization (619.1000) | EACH | 1 | $125,000 | $204,420 |
| 33 | Water (624.0100) | MGAL | 2 | $1.00 | $1.00 |
| 34 | Field office type B (642.5001) | EACH | 1 | $4,000.00 | $6,000.00 |
| 35 | Traffic control drums (643.0300) | DAY | 4,320 | $0.40 | $0.40 |
| 36 | Traffic control barricades type III (643.0420) | DAY | 180 | $5.00 | $5.00 |
| 37 | Traffic control warning lights type C (643.0715) | DAY | 2,160 | $0.15 | $0.15 |
| 38 | Traffic control signs (643.0900) | DAY | 3,600 | $0.85 | $0.85 |
| 39 | Traffic control signs fixed message (643.1000) | SF | 64 | $25.00 | $25.00 |
| 40 | Temporary marking line removable tape 6-inch (643.3180) | LF | 2,290 | $2.38 | $2.38 |
| 41 | Temporary marking stop line removable tape 18-inch (643.3850) | LF | 24 | $14.00 | $14.00 |
| 42 | Traffic control (643.5000) | EACH | 1 | $16,000 | $9,500.00 |
| 43 | Marking line epoxy 4-inch (646.1020) | LF | 2,860 | $2.55 | $2.55 |
| 44 | Marking removal line water blasting 4-inch (646.9010) | LF | 1,385 | $2.50 | $2.50 |
| 45 | Construction staking subgrade (650.4500) | LF | 82 | $0.05 | $0.01 |
| 46 | Construction staking base (650.5000) | LF | 52 | $0.05 | $0.01 |
| 47 | Construction staking structure layout (structure) 01. B-04-0011 (650.6501) | EACH | 1 | $1,000.00 | $2,500.00 |
| 48 | Construction staking supplemental control (project) 01. 8510-00-72 (650.9911) | EACH | 1 | $1,851.80 | $1,500.00 |
| 49 | Temporary traffic signals for bridges (structure) 01. B-04-0011 (661.0101) | EACH | 1 | $16,800 | $16,800 |
| 50 | Sawing asphalt (690.0150) | LF | 59 | $2.95 | $2.95 |
| 51 | Incentive strength concrete structures (715.0502) | DOL | 500 | $1.00 | $1.00 |
| 52 | Incentive compressive strength concrete pavement (715.0720) | DOL | 500 | $1.00 | $1.00 |
| 53 | Installing and maintaining bird deterrent system (station) 01. station 395+97 (999.2000.S) | EACH | 1 | $1,000.00 | $1.00 |
| 54 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 300 | $5.00 | $5.00 |
| 55 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 300 | $5.00 | $5.00 |
| 56 | Special 01. cleaning and painting bearings (SPV.0060) | EACH | 10 | $850.00 | $850.00 |
| 57 | Special 02. embedded galvanic anodes (SPV.0060) | EACH | 76 | $45.00 | $52.00 |
| 58 | Special 01. flashing stainless steel (SPV.0090) | LF | 132 | $50.00 | $65.00 |
| 59 | Special 01. abutment seat cleaning and sealing (SPV.0180) | SY | 20 | $75.00 | $125.00 |
| 60 | Special 02. methacrylate flood seal (SPV.0180) | SY | 450 | $32.00 | $31.29 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of January 14, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.