WisDOT contract 20250211002 bid tabulation
C Columbus, Ludington Street; Faith Drive to Middleton Street (STH 073, Columbia COunty C Columbus, Ludington Street). Let by Wisconsin DOT on February 11, 2025, Columbia. 3 bids received; low bid $1,405,754 by Rock Road Companies, Inc..
- Owner
- Wisconsin DOT
- Letting
- 11 FEB 2025
- Pay items
- 91
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rock Road Companies, Inc. | $1,405,754 | Low |
| 2 | Northeast Asphalt, Inc | $1,429,901 | +2.0% |
| 3 | Kartechner Brothers LLC | $2,199,855 | +56% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rock Road Companies, Inc. | 2. Northeast Asphalt, Inc | 3. Kartechner Brothers LLC |
|---|---|---|---|---|---|---|
| 1 | Grubbing (201.0205) | STA | 2 | $599.00 | $1,000.00 | $713.12 |
| 2 | Removing asphaltic surface (204.0110) | SY | 417 | $20.11 | $5.00 | $5.95 |
| 3 | Removing asphaltic surface butt joints (204.0115) | SY | 1,276 | $2.76 | $5.00 | $41.51 |
| 4 | Removing asphaltic surface milling (204.0120) | SY | 32,175 | $3.07 | $2.00 | $3.68 |
| 5 | Removing curb & gutter (204.0150) | LF | 1,566 | $10.95 | $3.00 | $5.95 |
| 6 | Removing concrete sidewalk (204.0155) | SY | 997 | $10.72 | $4.00 | $5.95 |
| 7 | Removing fence (204.0170) | LF | 11 | $20.00 | $25.00 | $126.62 |
| 8 | Removing (item description) 01. boulder (204.9060.S) | EACH | 1 | $1,000.00 | $200.00 | $2,262.49 |
| 9 | Excavation common (205.0100) | CY | 127 | $35.07 | $26.40 | $262.40 |
| 10 | Prepare foundation for asphaltic paving (project) 01. 3060-00-74 (211.0101) | EACH | 1 | $0.01 | $14,500 | $53,837 |
| 11 | Finishing roadway (project) 01. 3060-00-74 (213.0100) | EACH | 1 | $5,065.30 | $2,750.00 | $18,196 |
| 12 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 644 | $17.39 | $28.30 | $43.40 |
| 13 | Drilled tie bars (416.0610) | EACH | 192 | $10.23 | $10.23 | $11.91 |
| 14 | Tack coat (455.0605) | GAL | 4,329 | $2.53 | $3.50 | $4.62 |
| 15 | Incentive density HMA pavement (460.2000) | DOL | 4,490 | $1.00 | $1.00 | $1.00 |
| 16 | HMA pavement 4 MT 58-28 H (460.6424) | TON | 7,009 | $85.90 | $82.90 | $105.00 |
| 17 | Asphaltic surface (465.0105) | TON | 330 | $128.65 | $157.75 | $317.71 |
| 18 | Asphaltic surface patching (465.0110) | TON | 101 | $141.65 | $164.25 | $579.99 |
| 19 | Asphaltic surface driveways and field entrances (465.0120) | TON | 16 | $226.69 | $198.75 | $262.78 |
| 20 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 1,556 | $25.19 | $25.19 | $70.00 |
| 21 | Concrete curb pedestrian (601.0600) | LF | 172 | $57.33 | $57.33 | $59.53 |
| 22 | Concrete sidewalk 5-inch (602.0410) | SF | 9,111 | $6.04 | $6.04 | $15.06 |
| 23 | Curb ramp detectable warning field yellow (602.0505) | SF | 660 | $53.10 | $53.10 | $59.53 |
| 24 | Curb ramp detectable warning field radial yellow (602.0605) | SF | 88 | $65.67 | $65.67 | $89.29 |
| 25 | Concrete driveway 7-inch (602.0815) | SY | 56 | $73.33 | $73.33 | $114.65 |
| 26 | Adjusting manhole covers (611.8110) | EACH | 2 | $1,199.90 | $1,430.00 | $3,042.37 |
| 27 | Adjusting inlet covers (611.8115) | EACH | 18 | $473.13 | $1,430.00 | $2,276.88 |
| 28 | Cover plates temporary (611.8120.S) | EACH | 41 | $50.00 | $375.00 | $2,550.65 |
| 29 | Mobilization (619.1000) | EACH | 1 | $117,966 | $149,600 | $124,497 |
| 30 | Water (624.0100) | MGAL | 33 | $0.01 | $75.00 | $94.05 |
| 31 | Topsoil (625.0100) | SY | 954 | $12.00 | $12.88 | $5.89 |
| 32 | Mulching (627.0200) | SY | 1,047 | $1.00 | $0.75 | $0.65 |
| 33 | Erosion bales (628.1104) | EACH | 100 | $10.00 | $12.00 | $14.29 |
| 34 | Silt fence (628.1504) | LF | 269 | $5.00 | $3.00 | $3.87 |
| 35 | Silt fence maintenance (628.1520) | LF | 135 | $1.00 | $0.25 | $0.01 |
| 36 | Mobilizations erosion control (628.1905) | EACH | 5 | $750.00 | $300.00 | $238.10 |
| 37 | Mobilizations emergency erosion control (628.1910) | EACH | 5 | $150.00 | $500.00 | $238.10 |
| 38 | Inlet protection type B (628.7010) | EACH | 1 | $100.00 | $50.00 | $65.48 |
| 39 | Inlet protection type C (628.7015) | EACH | 65 | $100.00 | $75.00 | $71.43 |
| 40 | Rock bags (628.7570) | EACH | 25 | $10.00 | $20.00 | $16.67 |
| 41 | Fertilizer type B (629.0210) | CWT | 3 | $200.00 | $100.00 | $113.10 |
| 42 | Seeding temporary (630.0200) | LB | 32 | $5.00 | $8.00 | $5.95 |
| 43 | Sod water (631.0300) | MGAL | 33 | $200.00 | $25.00 | $89.29 |
| 44 | Sod lawn (631.1000) | SY | 1,047 | $10.00 | $10.00 | $9.46 |
| 45 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 1 | $200.00 | $125.00 | $166.67 |
| 46 | Posts tubular steel 2X2-inch X 16- FT (634.0816) | EACH | 10 | $250.00 | $400.00 | $267.86 |
| 47 | Signs type II reflective H (637.2210) | SF | 16.50 | $50.00 | $40.00 | $29.76 |
| 48 | Moving signs type II (638.2102) | EACH | 11 | $150.00 | $150.00 | $142.86 |
| 49 | Removing small sign supports (638.3000) | EACH | 11 | $50.00 | $50.00 | $41.67 |
| 50 | Field office type B (642.5001) | EACH | 1 | $5,000.00 | $11,250 | $12,619 |
| 51 | Traffic control drums (643.0300) | DAY | 18,000 | $0.23 | $0.20 | $0.27 |
| 52 | Traffic control barricades type III (643.0420) | DAY | 317 | $1.50 | $3.00 | $1.79 |
| 53 | Traffic control warning lights type A (643.0705) | DAY | 640 | $0.50 | $0.50 | $0.60 |
| 54 | Traffic control signs (643.0900) | DAY | 25,030 | $0.28 | $0.20 | $0.33 |
| 55 | Traffic control covering signs type I (643.0910) | EACH | 6 | $250.00 | $350.00 | $297.63 |
| 56 | Traffic control covering signs type II (643.0920) | EACH | 3 | $100.00 | $30.00 | $119.05 |
| 57 | Traffic control signs fixed message (643.1000) | SF | 182.25 | $15.00 | $22.00 | $17.86 |
| 58 | Traffic control signs PCMS (643.1050) | DAY | 28 | $45.00 | $65.00 | $53.57 |
| 59 | Temporary marking line paint 6- inch (643.3165) | LF | 12,149 | $0.52 | $0.50 | $0.62 |
| 60 | Temporary marking line paint 10- inch (643.3265) | LF | 30 | $5.00 | $5.00 | $5.95 |
| 61 | Temporary marking crosswalk paint 6-inch (643.3305) | LF | 2,528 | $2.75 | $0.30 | $1.19 |
| 62 | Temporary marking stop line paint 18-inch (643.3805) | LF | 16 | $15.00 | $5.00 | $17.86 |
| 63 | Traffic control (643.5000) | EACH | 1 | $29,000 | $6,900.00 | $34,525 |
| 64 | Temporary pedestrian surface matting (644.1440) | SF | 671 | $5.00 | $11.00 | $5.95 |
| 65 | Temporary pedestrian curb ramp (644.1601) | DAY | 840 | $8.00 | $9.49 | $9.52 |
| 66 | Temporary pedestrian detectable warning field (644.1605) | SF | 220 | $15.00 | $15.00 | $17.86 |
| 67 | Temporary pedestrian barricade (644.1810) | LF | 1,254 | $5.00 | $5.69 | $5.95 |
| 68 | Geotextile type sas (645.0140) | SY | 123 | $1.10 | $10.00 | $2.70 |
| 69 | Marking line epoxy 10-inch (646.4020) | LF | 30 | $2.00 | $6.00 | $7.14 |
| 70 | Marking line same day epoxy 6- inch (646.4720) | LF | 12,466 | $0.90 | $1.25 | $1.49 |
| 71 | Marking railroad crossing epoxy (646.5320) | EACH | 2 | $1,500.00 | $1,100.00 | $1,309.56 |
| 72 | Marking stop line epoxy 18-inch (646.6120) | LF | 280 | $15.00 | $14.00 | $16.67 |
| 73 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 2,888 | $10.00 | $12.25 | $15.48 |
| 74 | Marking parking stall epoxy (646.8320) | LF | 150 | $4.00 | $7.00 | $8.33 |
| 75 | Marking removal line water blasting 4-inch (646.9010) | LF | 316 | $1.00 | $2.00 | $1.19 |
| 76 | Marking removal line water blasting 6-inch (646.9012) | LF | 165 | $3.00 | $3.00 | $3.57 |
| 77 | Marking removal line 8-inch (646.9100) | LF | 1,226 | $3.25 | $1.00 | $3.87 |
| 78 | Marking removal line wide (646.9200) | LF | 16 | $10.00 | $10.00 | $11.91 |
| 79 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 1,556 | $1.21 | $1.21 | $2.38 |
| 80 | Construction staking resurfacing reference (650.8000) | LF | 6,680 | $0.19 | $0.19 | $0.14 |
| 81 | Construction staking curb ramps (650.9000) | EACH | 68 | $176.01 | $176.01 | $357.15 |
| 82 | Construction staking sidewalk (project) 01. 3060-00-74 (650.9500) | EACH | 1 | $1,515.67 | $1,515.67 | $11,905 |
| 83 | Construction staking supplemental control (project) 01. 3060-00-74 (650.9911) | EACH | 1 | $921.63 | $921.63 | $5,952.53 |
| 84 | Sawing asphalt (690.0150) | LF | 2,975 | $1.39 | $1.39 | $1.65 |
| 85 | Sawing concrete (690.0250) | LF | 768 | $2.25 | $2.25 | $2.68 |
| 86 | Incentive iri ride (740.0440) | DOL | 5,290 | $1.00 | $1.00 | $1.00 |
| 87 | Special 01. adjusting water valves (SPV.0060) | EACH | 26 | $311.38 | $300.00 | $646.07 |
| 88 | Special 02. adjusting sanitary manhole covers (SPV.0060) | EACH | 21 | $1,768.34 | $1,930.00 | $894.70 |
| 89 | Special 03. dynamic right turn yield to pedestrians sign (SPV.0060) | EACH | 2 | $7,710.00 | $7,710.00 | $4,395.95 |
| 90 | Special 01. temporary curb & gutter 30-inch (SPV.0090) | LF | 8 | $50.00 | $325.00 | $119.05 |
| 91 | Special 01. removing distressed pavement milling (SPV.0180) | SY | 1,616 | $4.05 | $11.24 | $20.22 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of February 11, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.