WisDOT contract 20250211002 bid tabulation

C Columbus, Ludington Street; Faith Drive to Middleton Street (STH 073, Columbia COunty C Columbus, Ludington Street). Let by Wisconsin DOT on February 11, 2025, Columbia. 3 bids received; low bid $1,405,754 by Rock Road Companies, Inc..

Owner
Wisconsin DOT
Letting
11 FEB 2025
Pay items
91
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Rock Road Companies, Inc.$1,405,754Low
2Northeast Asphalt, Inc$1,429,901+2.0%
3Kartechner Brothers LLC$2,199,855+56%
WisDOT contract 20250211002: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Rock Road Companies, Inc.2. Northeast Asphalt, Inc3. Kartechner Brothers LLC
1Grubbing (201.0205)STA2$599.00$1,000.00$713.12
2Removing asphaltic surface (204.0110)SY417$20.11$5.00$5.95
3Removing asphaltic surface butt joints (204.0115)SY1,276$2.76$5.00$41.51
4Removing asphaltic surface milling (204.0120)SY32,175$3.07$2.00$3.68
5Removing curb & gutter (204.0150)LF1,566$10.95$3.00$5.95
6Removing concrete sidewalk (204.0155)SY997$10.72$4.00$5.95
7Removing fence (204.0170)LF11$20.00$25.00$126.62
8Removing (item description) 01. boulder (204.9060.S)EACH1$1,000.00$200.00$2,262.49
9Excavation common (205.0100)CY127$35.07$26.40$262.40
10Prepare foundation for asphaltic paving (project) 01. 3060-00-74 (211.0101)EACH1$0.01$14,500$53,837
11Finishing roadway (project) 01. 3060-00-74 (213.0100)EACH1$5,065.30$2,750.00$18,196
12Base aggregate dense 1 1/4-inch (305.0120)TON644$17.39$28.30$43.40
13Drilled tie bars (416.0610)EACH192$10.23$10.23$11.91
14Tack coat (455.0605)GAL4,329$2.53$3.50$4.62
15Incentive density HMA pavement (460.2000)DOL4,490$1.00$1.00$1.00
16HMA pavement 4 MT 58-28 H (460.6424)TON7,009$85.90$82.90$105.00
17Asphaltic surface (465.0105)TON330$128.65$157.75$317.71
18Asphaltic surface patching (465.0110)TON101$141.65$164.25$579.99
19Asphaltic surface driveways and field entrances (465.0120)TON16$226.69$198.75$262.78
20Concrete curb & gutter 30-inch type D (601.0411)LF1,556$25.19$25.19$70.00
21Concrete curb pedestrian (601.0600)LF172$57.33$57.33$59.53
22Concrete sidewalk 5-inch (602.0410)SF9,111$6.04$6.04$15.06
23Curb ramp detectable warning field yellow (602.0505)SF660$53.10$53.10$59.53
24Curb ramp detectable warning field radial yellow (602.0605)SF88$65.67$65.67$89.29
25Concrete driveway 7-inch (602.0815)SY56$73.33$73.33$114.65
26Adjusting manhole covers (611.8110)EACH2$1,199.90$1,430.00$3,042.37
27Adjusting inlet covers (611.8115)EACH18$473.13$1,430.00$2,276.88
28Cover plates temporary (611.8120.S)EACH41$50.00$375.00$2,550.65
29Mobilization (619.1000)EACH1$117,966$149,600$124,497
30Water (624.0100)MGAL33$0.01$75.00$94.05
31Topsoil (625.0100)SY954$12.00$12.88$5.89
32Mulching (627.0200)SY1,047$1.00$0.75$0.65
33Erosion bales (628.1104)EACH100$10.00$12.00$14.29
34Silt fence (628.1504)LF269$5.00$3.00$3.87
35Silt fence maintenance (628.1520)LF135$1.00$0.25$0.01
36Mobilizations erosion control (628.1905)EACH5$750.00$300.00$238.10
37Mobilizations emergency erosion control (628.1910)EACH5$150.00$500.00$238.10
38Inlet protection type B (628.7010)EACH1$100.00$50.00$65.48
39Inlet protection type C (628.7015)EACH65$100.00$75.00$71.43
40Rock bags (628.7570)EACH25$10.00$20.00$16.67
41Fertilizer type B (629.0210)CWT3$200.00$100.00$113.10
42Seeding temporary (630.0200)LB32$5.00$8.00$5.95
43Sod water (631.0300)MGAL33$200.00$25.00$89.29
44Sod lawn (631.1000)SY1,047$10.00$10.00$9.46
45Posts wood 4X6-inch X 16-FT (634.0616)EACH1$200.00$125.00$166.67
46Posts tubular steel 2X2-inch X 16- FT (634.0816)EACH10$250.00$400.00$267.86
47Signs type II reflective H (637.2210)SF16.50$50.00$40.00$29.76
48Moving signs type II (638.2102)EACH11$150.00$150.00$142.86
49Removing small sign supports (638.3000)EACH11$50.00$50.00$41.67
50Field office type B (642.5001)EACH1$5,000.00$11,250$12,619
51Traffic control drums (643.0300)DAY18,000$0.23$0.20$0.27
52Traffic control barricades type III (643.0420)DAY317$1.50$3.00$1.79
53Traffic control warning lights type A (643.0705)DAY640$0.50$0.50$0.60
54Traffic control signs (643.0900)DAY25,030$0.28$0.20$0.33
55Traffic control covering signs type I (643.0910)EACH6$250.00$350.00$297.63
56Traffic control covering signs type II (643.0920)EACH3$100.00$30.00$119.05
57Traffic control signs fixed message (643.1000)SF182.25$15.00$22.00$17.86
58Traffic control signs PCMS (643.1050)DAY28$45.00$65.00$53.57
59Temporary marking line paint 6- inch (643.3165)LF12,149$0.52$0.50$0.62
60Temporary marking line paint 10- inch (643.3265)LF30$5.00$5.00$5.95
61Temporary marking crosswalk paint 6-inch (643.3305)LF2,528$2.75$0.30$1.19
62Temporary marking stop line paint 18-inch (643.3805)LF16$15.00$5.00$17.86
63Traffic control (643.5000)EACH1$29,000$6,900.00$34,525
64Temporary pedestrian surface matting (644.1440)SF671$5.00$11.00$5.95
65Temporary pedestrian curb ramp (644.1601)DAY840$8.00$9.49$9.52
66Temporary pedestrian detectable warning field (644.1605)SF220$15.00$15.00$17.86
67Temporary pedestrian barricade (644.1810)LF1,254$5.00$5.69$5.95
68Geotextile type sas (645.0140)SY123$1.10$10.00$2.70
69Marking line epoxy 10-inch (646.4020)LF30$2.00$6.00$7.14
70Marking line same day epoxy 6- inch (646.4720)LF12,466$0.90$1.25$1.49
71Marking railroad crossing epoxy (646.5320)EACH2$1,500.00$1,100.00$1,309.56
72Marking stop line epoxy 18-inch (646.6120)LF280$15.00$14.00$16.67
73Marking crosswalk epoxy transverse line 6-inch (646.7420)LF2,888$10.00$12.25$15.48
74Marking parking stall epoxy (646.8320)LF150$4.00$7.00$8.33
75Marking removal line water blasting 4-inch (646.9010)LF316$1.00$2.00$1.19
76Marking removal line water blasting 6-inch (646.9012)LF165$3.00$3.00$3.57
77Marking removal line 8-inch (646.9100)LF1,226$3.25$1.00$3.87
78Marking removal line wide (646.9200)LF16$10.00$10.00$11.91
79Construction staking curb gutter and curb & gutter (650.5500)LF1,556$1.21$1.21$2.38
80Construction staking resurfacing reference (650.8000)LF6,680$0.19$0.19$0.14
81Construction staking curb ramps (650.9000)EACH68$176.01$176.01$357.15
82Construction staking sidewalk (project) 01. 3060-00-74 (650.9500)EACH1$1,515.67$1,515.67$11,905
83Construction staking supplemental control (project) 01. 3060-00-74 (650.9911)EACH1$921.63$921.63$5,952.53
84Sawing asphalt (690.0150)LF2,975$1.39$1.39$1.65
85Sawing concrete (690.0250)LF768$2.25$2.25$2.68
86Incentive iri ride (740.0440)DOL5,290$1.00$1.00$1.00
87Special 01. adjusting water valves (SPV.0060)EACH26$311.38$300.00$646.07
88Special 02. adjusting sanitary manhole covers (SPV.0060)EACH21$1,768.34$1,930.00$894.70
89Special 03. dynamic right turn yield to pedestrians sign (SPV.0060)EACH2$7,710.00$7,710.00$4,395.95
90Special 01. temporary curb & gutter 30-inch (SPV.0090)LF8$50.00$325.00$119.05
91Special 01. removing distressed pavement milling (SPV.0180)SY1,616$4.05$11.24$20.22
WisDOT contract 20250211002: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of February 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy