Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Michels Road & Stone, Inc. | $13,172,405 | Low |
| 2 | Vinton Construction Company | $15,987,874 | +21% |
| 3 | James Peterson Sons, Inc. | $16,275,900 | +24% |
| 4 | Hoffman Construction Company | $20,741,613 | +57% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Michels Road & Stone, Inc. | 2. Vinton Construction Company | 3. James Peterson Sons, Inc. | 4. Hoffman Construction Company |
|---|---|---|---|---|---|---|---|
| 1 | Removing concrete pavement (204.0100) | SY | 1,840 | $3.00 | $3.00 | $2.89 | $10.00 |
| 2 | Removing curb (204.0130) | LF | 55 | $10.00 | $10.00 | $25.00 | $10.00 |
| 3 | Removing guardrail (204.0165) | LF | 2,275 | $5.00 | $5.00 | $5.00 | $5.00 |
| 4 | Removing delineators and markers (204.0180) | EACH | 95 | $25.00 | $25.00 | $25.00 | $25.00 |
| 5 | Removing surface drains (204.0190) | EACH | 2 | $250.00 | $250.00 | $500.00 | $500.00 |
| 6 | Removing inlets (204.0220) | EACH | 9 | $310.00 | $535.00 | $300.00 | $535.00 |
| 7 | Removing storm sewer (size) 01. 12-inch (204.0245) | LF | 110 | $12.00 | $15.00 | $35.84 | $15.00 |
| 8 | Removing storm sewer (size) 02. 18-inch (204.0245) | LF | 211 | $15.00 | $15.00 | $40.84 | $15.00 |
| 9 | Removing storm sewer (size) 03. 24-inch (204.0245) | LF | 415 | $16.00 | $20.00 | $45.84 | $20.00 |
| 10 | Removing storm sewer (size) 04. 30-inch (204.0245) | LF | 28 | $18.00 | $20.00 | $50.84 | $20.00 |
| 11 | Removing ancillary structure (structure) 01. S-44-136 (204.0246) | EACH | 1 | $10,000 | $10,000 | $10,000 | $10,000 |
| 12 | Removing ancillary structure (structure) 02. S-44-143 (204.0246) | EACH | 1 | $10,000 | $10,000 | $10,000 | $10,000 |
| 13 | Sealing pipes (204.0280) | EACH | 2 | $447.00 | $465.00 | $500.00 | $465.00 |
| 14 | Removing (item description) 01. apron endwalls (204.9060.S) | EACH | 1 | $600.00 | $430.00 | $500.00 | $430.00 |
| 15 | Excavation common (205.0100) | CY | 150,093 | $12.00 | $22.26 | $15.35 | $34.00 |
| 16 | Prepare foundation for asphaltic paving (project) 01. 1130-67-71 (211.0101) | EACH | 1 | $51,350 | $214,750 | $214,750 | $100.00 |
| 17 | Finishing roadway (project) 01. 1130-67-71 (213.0100) | EACH | 1 | $5,500.00 | $5,000.00 | $5,000.00 | $100.00 |
| 18 | Base aggregate dense 3/4-inch (305.0110) | TON | 170 | $35.00 | $40.00 | $50.00 | $50.00 |
| 19 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 53,345 | $14.00 | $16.00 | $21.42 | $25.00 |
| 20 | Select crushed material (312.0110) | TON | 214,335 | $13.20 | $14.80 | $20.39 | $28.00 |
| 21 | Tack coat (455.0605) | GAL | 6,495 | $4.25 | $4.25 | $4.25 | $4.25 |
| 22 | Asphaltic surface (465.0105) | TON | 25,930 | $89.20 | $89.20 | $89.20 | $89.20 |
| 23 | Asphaltic flumes (465.0315) | SY | 20 | $65.00 | $65.00 | $65.00 | $65.00 |
| 24 | Culvert pipe reinforced concrete class IV 18-inch (522.0418) | LF | 45 | $86.00 | $100.00 | $83.88 | $100.00 |
| 25 | Apron endwalls for culvert pipe reinforced concrete 15-inch (522.1015) | EACH | 1 | $1,234.00 | $1,240.00 | $1,308.75 | $1,240.00 |
| 26 | Apron endwalls for culvert pipe reinforced concrete 18-inch (522.1018) | EACH | 5 | $1,387.00 | $1,410.00 | $1,481.74 | $1,410.00 |
| 27 | Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024) | EACH | 5 | $1,637.00 | $1,745.00 | $1,816.41 | $1,745.00 |
| 28 | Apron endwalls for culvert pipe reinforced concrete 30-inch (522.1030) | EACH | 1 | $1,939.00 | $2,160.00 | $2,508.74 | $2,160.00 |
| 29 | Concrete curb & gutter 18-inch type A (601.0405) | LF | 850 | $19.20 | $19.20 | $19.20 | $19.20 |
| 30 | Concrete curb & gutter 30-inch type A (601.0409) | LF | 410 | $21.55 | $21.55 | $21.55 | $21.55 |
| 31 | Concrete barrier temporary precast delivered (603.8000) | LF | 70,583 | $14.00 | $0.01 | $0.01 | $0.01 |
| 32 | Concrete barrier temporary precast installed (603.8125) | LF | 74,373 | $1.50 | $12.00 | $12.00 | $12.00 |
| 33 | Anchoring concrete barrier temporary precast (603.8500) | LF | 1,345 | $8.00 | $7.00 | $7.00 | $7.00 |
| 34 | Riprap medium (606.0200) | CY | 35 | $155.00 | $117.00 | $100.00 | $175.00 |
| 35 | Storm sewer pipe reinforced concrete class IV 12-inch (608.0412) | LF | 14 | $114.00 | $121.00 | $106.48 | $121.00 |
| 36 | Storm sewer pipe reinforced concrete class IV 15-inch (608.0415) | LF | 117 | $73.00 | $81.70 | $80.04 | $81.70 |
| 37 | Storm sewer pipe reinforced concrete class IV 18-inch (608.0418) | LF | 487 | $78.00 | $90.50 | $83.67 | $90.50 |
| 38 | Storm sewer pipe reinforced concrete class IV 24-inch (608.0424) | LF | 1,391 | $109.00 | $100.30 | $117.24 | $100.30 |
| 39 | Storm sewer pipe reinforced concrete class IV 30-inch (608.0430) | LF | 1,487 | $145.00 | $132.60 | $165.40 | $132.60 |
| 40 | Storm sewer pipe reinforced concrete class IV 36-inch (608.0436) | LF | 311 | $175.00 | $176.00 | $205.34 | $176.00 |
| 41 | Storm sewer pipe reinforced concrete horizontal elliptical class HE-III 14X23-inch (608.2314) | LF | 222 | $120.00 | $116.60 | $137.14 | $116.60 |
| 42 | Storm sewer pipe reinforced concrete horizontal elliptical class HE-III 24X38-inch (608.2324) | LF | 9 | $147.00 | $285.00 | $401.40 | $285.00 |
| 43 | Reconstructing manholes (611.0420) | EACH | 4 | $723.00 | $1,500.00 | $500.00 | $1,500.00 |
| 44 | Manhole covers type J (611.0530) | EACH | 2 | $507.00 | $445.00 | $939.00 | $445.00 |
| 45 | Manhole covers type L (611.0545) | EACH | 2 | $378.00 | $335.00 | $814.00 | $335.00 |
| 46 | Inlet covers type B (611.0606) | EACH | 2 | $799.00 | $694.00 | $1,216.00 | $694.00 |
| 47 | Inlet covers type H-S (611.0639) | EACH | 2 | $755.00 | $657.00 | $1,177.00 | $657.00 |
| 48 | Inlet covers type MS (611.0642) | EACH | 14 | $520.00 | $455.00 | $951.00 | $455.00 |
| 49 | Manholes 4-FT diameter (611.2004) | EACH | 1 | $3,224.00 | $3,600.00 | $2,586.27 | $3,600.00 |
| 50 | Manholes 5-FT diameter (611.2005) | EACH | 23 | $5,043.00 | $4,135.00 | $4,343.85 | $4,135.00 |
| 51 | Manholes 6-FT diameter (611.2006) | EACH | 3 | $6,943.00 | $5,928.00 | $6,668.29 | $5,928.00 |
| 52 | Manholes 7-FT diameter (611.2007) | EACH | 1 | $8,960.00 | $8,305.00 | $8,112.78 | $8,305.00 |
| 53 | Inlets 3-FT diameter (611.3003) | EACH | 3 | $2,313.50 | $2,530.00 | $1,912.25 | $2,530.00 |
| 54 | Inlets 4-FT diameter (611.3004) | EACH | 2 | $3,339.50 | $3,910.00 | $2,174.86 | $3,910.00 |
| 55 | Inlets 2X3-FT (611.3230) | EACH | 2 | $2,653.00 | $3,610.00 | $1,646.96 | $3,610.00 |
| 56 | Inlets median 1 grate (611.3901) | EACH | 2 | $2,880.00 | $3,410.00 | $2,327.93 | $3,410.00 |
| 57 | Inlets median 2 grate (611.3902) | EACH | 6 | $3,957.00 | $4,060.00 | $3,374.85 | $4,060.00 |
| 58 | Pipe underdrain 6-inch (612.0106) | LF | 750 | $25.00 | $20.00 | $25.00 | $20.00 |
| 59 | Crash cushions temporary (614.0905) | EACH | 2 | $4,850.00 | $9,000.00 | $4,850.00 | $10,750 |
| 60 | Fence chain link salvaged 5-FT (616.0405) | LF | 3,910 | $10.00 | $10.00 | $10.00 | $10.00 |
| 61 | Fence safety (616.0700.S) | LF | 5,585 | $0.01 | $0.01 | $1.00 | $0.01 |
| 62 | Maintenance and repair of haul roads (project) 01. 1130-67-71 (618.0100) | EACH | 1 | $1.00 | $0.01 | $1.00 | $100.00 |
| 63 | Mobilization (619.1000) | EACH | 1 | $1,176,260 | $1,280,500 | $833,000 | $1,103,450 |
| 64 | Water (624.0100) | MGAL | 4,025 | $5.00 | $0.01 | $45.00 | $0.01 |
| 65 | Salvaged topsoil (625.0500) | SY | 53,160 | $1.40 | $1.47 | $0.85 | $2.00 |
| 66 | Silt fence (628.1504) | LF | 17,860 | $2.00 | $2.00 | $2.00 | $2.00 |
| 67 | Silt fence maintenance (628.1520) | LF | 35,720 | $0.01 | $0.01 | $0.01 | $0.01 |
| 68 | Mobilizations erosion control (628.1905) | EACH | 15 | $1.00 | $1.00 | $1.00 | $1.00 |
| 69 | Mobilizations emergency erosion control (628.1910) | EACH | 10 | $1.00 | $1.00 | $1.00 | $1.00 |
| 70 | Erosion mat class I type A (628.2002) | SY | 53,160 | $1.50 | $1.50 | $1.50 | $1.50 |
| 71 | Inlet protection type A (628.7005) | EACH | 30 | $150.00 | $150.00 | $150.00 | $150.00 |
| 72 | Inlet protection type B (628.7010) | EACH | 5 | $100.00 | $100.00 | $100.00 | $100.00 |
| 73 | Inlet protection type C (628.7015) | EACH | 3 | $100.00 | $100.00 | $100.00 | $100.00 |
| 74 | Inlet protection type D (628.7020) | EACH | 3 | $150.00 | $150.00 | $150.00 | $150.00 |
| 75 | Temporary ditch checks (628.7504) | LF | 130 | $10.00 | $10.00 | $10.00 | $10.00 |
| 76 | Stone ditch checks (628.7515.S) | CY | 550 | $50.00 | $50.00 | $50.00 | $45.00 |
| 77 | Culvert pipe checks (628.7555) | EACH | 70 | $20.00 | $20.00 | $20.00 | $20.00 |
| 78 | Tracking pads (628.7560) | EACH | 10 | $3,600.00 | $0.01 | $3,000.00 | $100.00 |
| 79 | Rock bags (628.7570) | EACH | 750 | $2.00 | $2.00 | $2.00 | $2.00 |
| 80 | Fertilizer type B (629.0210) | CWT | 34 | $150.00 | $150.00 | $150.00 | $150.00 |
| 81 | Seeding mixture no. 30 (630.0130) | LB | 2,410 | $7.50 | $7.50 | $7.50 | $7.50 |
| 82 | Seed water (630.0500) | MGAL | 1,180 | $0.01 | $0.01 | $0.01 | $0.01 |
| 83 | Markers culvert end (633.5200) | EACH | 12 | $100.00 | $100.00 | $100.00 | $100.00 |
| 84 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 5 | $200.00 | $200.00 | $200.00 | $200.00 |
| 85 | Posts tubular steel 2X2-inch X 16- FT (634.0816) | EACH | 30 | $250.00 | $250.00 | $250.00 | $250.00 |
| 86 | Moving signs type II (638.2102) | EACH | 65 | $200.00 | $200.00 | $200.00 | $200.00 |
| 87 | Removing signs type I (638.2601) | EACH | 6 | $750.00 | $750.00 | $750.00 | $750.00 |
| 88 | Removing signs type II (638.2602) | EACH | 10 | $50.00 | $50.00 | $50.00 | $50.00 |
| 89 | Removing small sign supports (638.3000) | EACH | 13 | $50.00 | $50.00 | $50.00 | $50.00 |
| 90 | Removing structural steel sign supports (638.3100) | EACH | 8 | $500.00 | $500.00 | $500.00 | $500.00 |
| 91 | Moving small sign supports (638.4000) | EACH | 70 | $1.00 | $1.00 | $1.00 | $1.00 |
| 92 | Traffic control drums (643.0300) | DAY | 59,030 | $0.18 | $0.18 | $0.18 | $0.18 |
| 93 | Traffic control barricades type III (643.0420) | DAY | 2,178 | $1.00 | $1.00 | $1.00 | $1.00 |
| 94 | Traffic control warning lights type A (643.0705) | DAY | 4,356 | $0.20 | $0.20 | $0.20 | $0.20 |
| 95 | Traffic control warning lights type C (643.0715) | DAY | 2,490 | $0.20 | $0.20 | $0.20 | $0.20 |
| 96 | Traffic control arrow boards (643.0800) | DAY | 267 | $14.00 | $14.00 | $14.00 | $14.00 |
| 97 | Traffic control signs (643.0900) | DAY | 29,472 | $0.30 | $0.30 | $0.30 | $0.30 |
| 98 | Traffic control covering signs type II (643.0920) | EACH | 320 | $35.00 | $35.00 | $35.00 | $35.00 |
| 99 | Traffic control signs fixed message (643.1000) | SF | 202.50 | $24.50 | $24.50 | $24.50 | $24.50 |
| 100 | Traffic control signs PCMS (643.1050) | DAY | 67 | $24.25 | $24.25 | $24.50 | $24.25 |
| 101 | Temporary marking line paint 6- inch (643.3165) | LF | 64,525 | $0.25 | $0.25 | $0.25 | $0.25 |
| 102 | Temporary marking line paint 10- inch (643.3265) | LF | 1,130 | $0.50 | $0.50 | $0.50 | $0.50 |
| 103 | Temporary marking raised pavement marker type I (643.3760) | EACH | 930 | $5.85 | $5.85 | $5.85 | $5.85 |
| 104 | Traffic control (643.5000) | EACH | 1 | $275,000 | $275,000 | $275,000 | $275,000 |
| 105 | Geotextile type HR (645.0120) | SY | 109 | $10.00 | $10.00 | $10.00 | $10.00 |
| 106 | Geotextile type R (645.0130) | SY | 1,150 | $5.00 | $5.00 | $5.00 | $5.00 |
| 107 | Geotextile type sas (645.0140) | SY | 31,550 | $2.00 | $1.65 | $1.82 | $2.00 |
| 108 | Geogrid type SR (645.0220) | SY | 31,550 | $1.70 | $1.50 | $1.82 | $1.75 |
| 109 | Marking line epoxy 6-inch (646.2020) | LF | 62,655 | $0.45 | $0.45 | $0.45 | $0.45 |
| 110 | Marking line epoxy 10-inch (646.4020) | LF | 1,130 | $0.98 | $0.98 | $0.98 | $0.98 |
| 111 | Marking removal line 4-inch (646.9000) | LF | 64,525 | $0.14 | $0.14 | $0.14 | $0.14 |
| 112 | Marking removal line 8-inch (646.9100) | LF | 1,130 | $0.35 | $0.35 | $0.35 | $0.35 |
| 113 | Marking removal special marking (646.9300) | EACH | 2 | $80.00 | $80.00 | $80.00 | $80.00 |
| 114 | Sawing asphalt (690.0150) | LF | 22,230 | $1.39 | $1.39 | $1.55 | $1.39 |
| 115 | Sawing concrete (690.0250) | LF | 560 | $2.50 | $4.50 | $2.35 | $2.50 |
| 116 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,400 | $5.00 | $5.00 | $5.00 | $5.00 |
| 117 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 4,400 | $5.00 | $5.00 | $5.00 | $5.00 |
| 118 | Special 01. cover plates (SPV.0060) | EACH | 55 | $150.00 | $305.00 | $440.00 | $305.00 |
| 119 | Special 02. reconnect storm sewer (SPV.0060) | EACH | 13 | $593.00 | $845.00 | $500.00 | $845.00 |
| 120 | Special 03. storm sewer plug (SPV.0060) | EACH | 2 | $250.00 | $695.00 | $500.00 | $695.00 |
| 121 | Special 04. fixed message sign portable support (SPV.0060) | EACH | 2 | $1,250.00 | $1,250.00 | $1,250.00 | $1,250.00 |
| 122 | Special 05. emergency response to traffic involving concrete barrier temporary (SPV.0060) | EACH | 10 | $2,000.00 | $250.00 | $250.00 | $2,750.00 |
| 123 | Special 06. emergency response to traffic involving crash cushion temporary (SPV.0060) | EACH | 10 | $250.00 | $250.00 | $250.00 | $250.00 |
| 124 | Special 07. crash cushions temporary left in place (SPV.0060) | EACH | 7 | $34,250 | $38,450 | $34,250 | $34,250 |
| 125 | Special 08. construction staking survey project 1130-67-71 (SPV.0060) | EACH | 1 | $39,000 | $39,000 | $39,000 | $39,000 |
| 126 | Special 01. street sweeping (SPV.0075) | HRS | 175 | $225.00 | $145.00 | $200.00 | $250.00 |
| 127 | Special 01. removal and salvage of high-tension cable guard and posts (SPV.0090) | LF | 27,705 | $2.25 | $2.25 | $2.25 | $2.25 |
| 128 | Special 02. HMA longitudinal joint repair (SPV.0090) | LF | 9,485 | $3.75 | $3.75 | $3.75 | $3.75 |
| 129 | Special 03. drain slotted vane permanent (SPV.0090) | LF | 1,548 | $237.00 | $246.79 | $249.50 | $246.79 |
| 130 | Special 04. concrete barrier temporary precast left in place (SPV.0090) | LF | 29,863 | $15.00 | $43.12 | $43.15 | $43.12 |
| 131 | Special 05. safety fence special (SPV.0090) | LF | 200 | $12.00 | $12.00 | $12.00 | $12.00 |
| 132 | Special 06. removing asphaltic surface rumble strips (SPV.0090) | LF | 8,210 | $3.95 | $3.95 | $3.95 | $3.95 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of February 11, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.