WisDOT contract 20250211043 bid tabulation

V Hatley, Columbus Street; Plover River Bridge, B-37-0478 (LOC STR, Marathon County Columbus Street). Let by Wisconsin DOT on February 11, 2025, Marathon. 4 bids received; low bid $612,509 by Sheet Piling Services LLC.

Owner
Wisconsin DOT
Letting
11 FEB 2025
Pay items
62
Data through
10 NOV 2026

3 of the 4 bids matched their published totals to within a dollar and are shown; the others are left out.

Bidders

RankBidderTotal bidAgainst the low bid
1Sheet Piling Services LLC$612,509Low
3Janke General Contractors, Inc.$669,993+9.0%
4Lunda Construction Company$693,324+13%
WisDOT contract 20250211043: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Sheet Piling Services LLC2. Janke General Contractors, Inc.3. Lunda Construction Company
1Clearing (201.0105)STA4$1,000.00$50.00$1,635.00
2Grubbing (201.0205)STA4$1,000.00$650.00$416.00
3Removing structure over waterway minimal debris (structure) 01. P-37- 707 (203.0260)EACH1$80,000$58,350$175,000
4Excavation common (205.0100)CY163$22.43$21.00$17.60
5Excavation, hauling, and disposal of creosote contaminated soil (205.0506.S)TON190$110.00$115.00$75.00
6Excavation for structures bridges (structure) 01. B-37-478 (206.1001)EACH1$50,000$58,000$15,000
7Backfill granular grade 2 (209.2500)TON92$27.46$40.00$30.00
8Backfill structure type A (210.1500)TON270$27.46$27.00$14.00
9Finishing roadway (project) 01. 9531-03-70 (213.0100)EACH1$1,000.00$100.00$500.00
10Base aggregate dense 3/4-inch (305.0110)TON30$33.00$40.00$37.30
11Base aggregate dense 1 1/4-inch (305.0120)TON340$23.37$24.00$18.90
12Tack coat (455.0605)GAL38$12.90$12.90$12.90
13Asphaltic surface (465.0105)TON120$140.30$140.30$140.30
14Concrete masonry bridges (502.0100)CY219$820.00$825.00$750.00
15Protective surface treatment (502.3200)SY293$5.00$5.50$5.00
16Bar steel reinforcement HS structures (505.0400)LB4,910$1.20$1.70$1.00
17Bar steel reinforcement HS coated structures (505.0600)LB31,300$1.30$1.70$1.05
18Railing tubular type M (513.4061)LF198$240.00$300.00$260.00
19Rubberized membrane waterproofing (516.0500)SY18$30.00$45.00$25.00
20Pre-boring rock or consolidated materials (550.0020)LF66$275.00$486.00$400.00
21Pile points (550.0500)EACH8$130.00$174.00$110.00
22Piling steel HP 12-inch X 53 LB (550.1120)LF305$55.00$55.00$60.00
23Riprap heavy (606.0300)CY170$85.00$113.00$75.00
24Pipe underdrain wrapped 6-inch (612.0406)LF200$7.15$13.50$6.50
25Maintenance and repair of haul roads (project) 01. 9531-03-70 (618.0100)EACH1$0.01$100.00$500.00
26Mobilization (619.1000)EACH1$39,056$75,000$85,755
27Water (624.0100)MGAL12$50.00$30.00$0.50
28Topsoil (625.0100)SY610$9.72$8.00$5.20
29Silt fence (628.1504)LF550$2.85$3.80$2.40
30Silt fence maintenance (628.1520)LF550$0.10$0.01$0.01
31Mobilizations erosion control (628.1905)EACH5$200.00$1.00$647.00
32Mobilizations emergency erosion control (628.1910)EACH2$250.00$1.00$100.00
33Erosion mat urban class I type B (628.2008)SY610$1.90$2.75$2.20
34Erosion mat class II type C (628.2027)SY100$4.15$6.50$4.65
35Turbidity barriers (628.6005)SY320$49.50$20.00$38.90
36Temporary ditch checks (628.7504)LF20$12.89$10.00$7.25
37Rock bags (628.7570)EACH98$10.00$15.00$16.60
38Fertilizer type B (629.0210)CWT0.45$110.00$435.00$206.00
39Seeding mixture no. 20 (630.0120)LB18$8.15$16.00$16.95
40Seeding temporary (630.0200)LB18$3.50$8.00$7.30
41Seed water (630.0500)MGAL13$20.00$35.00$0.50
42Posts wood 4X6-inch X 12-FT (634.0612)EACH4$120.00$150.00$85.75
43Signs type II reflective F (637.2230)SF12$30.00$35.00$28.95
44Moving signs type II (638.2102)EACH2$20.00$100.00$113.00
45Removing signs type II (638.2602)EACH2$15.00$200.00$21.75
46Field office type B (642.5001)EACH1$1,250.00$1,000.00$3,500.00
47Traffic control barricades type III (643.0420)DAY1,890$0.40$0.40$0.50
48Traffic control warning lights type A (643.0705)DAY2,930$0.10$0.10$0.25
49Traffic control signs (643.0900)DAY1,470$0.30$0.30$0.50
50Traffic control (643.5000)EACH1$905.00$905.00$1,000.00
51Geotextile type DF schedule A (645.0111)SY160$6.10$3.90$4.30
52Geotextile type HR (645.0120)SY310$5.00$4.50$5.00
53Construction staking subgrade (650.4500)LF200$0.50$0.50$0.50
54Construction staking base (650.5000)LF200$2.00$2.00$2.00
55Construction staking structure layout (structure) 01. B-37-478 (650.6501)EACH1$2,900.00$2,900.00$2,900.00
56Construction staking supplemental control (project) 01. 9531-03-70 (650.9911)EACH1$428.00$428.00$428.00
57Construction staking slope stakes (650.9920)LF200$2.00$2.00$2.00
58Sawing asphalt (690.0150)LF42$5.00$2.45$2.95
59Incentive strength concrete structures (715.0502)DOL1,320$1.00$1.00$1.00
60Maintaining bird deterrent system (station) station 10+00 (999.2005.S)EACH1$0.01$500.00$1.00
61On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS300$5.00$5.00$5.00
62On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS600$5.00$5.00$5.00
WisDOT contract 20250211043: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of February 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy