WisDOT contract 20250211046 bid tabulation

STH 153 - CTH P; Rocky Run River Bridge B-37-0480 (CTH H, Marathon County STH 153 - CTH P). Let by Wisconsin DOT on February 11, 2025, Marathon. 4 bids received; low bid $825,127 by Sheet Piling Services LLC.

Owner
Wisconsin DOT
Letting
11 FEB 2025
Pay items
64
Data through
10 NOV 2026

3 of the 4 bids matched their published totals to within a dollar and are shown; the others are left out.

Bidders

RankBidderTotal bidAgainst the low bid
1Sheet Piling Services LLC$825,127Low
2Lunda Construction Company$921,899+12%
4Janke General Contractors, Inc.$994,950+21%
WisDOT contract 20250211046: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Sheet Piling Services LLC2. Lunda Construction Company3. Janke General Contractors, Inc.
1Clearing (201.0105)STA6$1.00$1.00$50.00
2Grubbing (201.0205)STA6$1.00$1.00$450.00
3Removing structure over waterway remove debris (structure) 01. B-37- 0085 (203.0250)EACH1$85,000$125,000$63,619
4Removing guardrail (204.0165)LF373$3.70$3.70$3.75
5Excavation common (205.0100)CY595$13.60$13.60$30.00
6Excavation, hauling, and disposal of creosote contaminated soil (205.0506.S)TON220$90.00$75.00$140.00
7Excavation for structures bridges (structure) 01. B-37-0480 (206.1001)EACH1$55,000$15,000$45,000
8Cofferdams (structure) 01. B-37- 0480 (206.5001)EACH1$35,000$50,000$32,000
9Backfill structure type A (210.1500)TON320$22.85$22.85$27.00
10Finishing roadway (project) 01. 9958-02-70 (213.0100)EACH1$486.00$486.00$100.00
11Base aggregate dense 3/4-inch (305.0110)TON44$29.55$29.55$55.00
12Base aggregate dense 1 1/4-inch (305.0120)TON740$21.00$21.00$32.00
13Concrete pavement 6-inch (415.0060)SY20$167.25$167.25$200.00
14Concrete pavement approach slab (415.0410)SY118$308.31$308.31$250.00
15Tack coat (455.0605)GAL100$7.30$7.30$7.30
16Asphaltic surface (465.0105)TON299$136.10$136.10$136.10
17Concrete masonry bridges (502.0100)CY284$850.00$650.00$780.00
18Protective surface treatment (502.3200)SY372$3.00$5.00$5.70
19Underwater substructure inspection (structure) 01. B-37-0480 (502.9000.S)EACH1$5,000.00$5,100.00$2,000.00
20Bar steel reinforcement HS structures (505.0400)LB7,320$1.05$1.00$1.80
21Bar steel reinforcement HS coated structures (505.0600)LB37,550$1.10$1.25$1.80
22Railing tubular type M (513.4061)LF169$250.00$300.00$300.00
23Rubberized membrane waterproofing (516.0500)SY20$25.00$25.00$38.00
24Pre-boring rock or consolidated materials (550.0020)LF624$50.00$140.00$235.00
25Piling steel HP 10-inch X 42 LB (550.1100)LF760$42.00$50.00$55.00
26Riprap heavy (606.0300)CY155$55.00$70.00$90.00
27Pipe underdrain wrapped 6-inch (612.0406)LF150$6.40$6.40$11.00
28MGS guardrail 3 (614.2300)LF175$22.25$22.25$25.00
29MGS thrie beam transition (614.2500)LF156$85.65$85.65$93.00
30MGS guardrail terminal eat (614.2610)EACH4$3,360.00$3,360.00$3,233.00
31Maintenance and repair of haul roads (project) 01. 9958-02-70 (618.0100)EACH1$1.00$500.00$378.56
32Mobilization (619.1000)EACH1$36,250$87,419$55,555
33Water (624.0100)MGAL8$1.00$1.00$30.00
34Topsoil (625.0100)SY890$4.15$4.15$7.15
35Silt fence (628.1504)LF925$2.05$2.05$2.85
36Silt fence maintenance (628.1520)LF925$0.01$0.01$0.03
37Mobilizations erosion control (628.1905)EACH4$400.00$400.00$101.00
38Mobilizations emergency erosion control (628.1910)EACH2$75.00$75.00$101.00
39Erosion mat urban class I type B (628.2008)SY890$2.00$2.00$2.45
40Turbidity barriers (628.6005)SY110$50.00$50.00$42.00
41Fertilizer type B (629.0210)CWT0.09$186.00$186.00$1,317.65
42Seeding mixture no. 30 (630.0130)LB61$14.50$14.50$8.95
43Seed water (630.0500)MGAL16$1.00$1.00$5.00
44Posts wood 4X6-inch X 12-FT (634.0612)EACH4$85.75$85.75$125.00
45Signs type II reflective F (637.2230)SF12$28.95$28.95$50.00
46Field office type B (642.5001)EACH1$1,500.00$3,500.00$1,000.00
47Traffic control barricades type III (643.0420)DAY2,060$0.37$0.70$0.37
48Traffic control warning lights type A (643.0705)DAY3,376$0.10$0.20$0.10
49Traffic control signs (643.0900)DAY11,625$0.30$0.30$0.30
50Traffic control covering signs type II (643.0920)EACH3$30.00$115.00$30.00
51Traffic control signs fixed message (643.1000)SF18$11.20$19.00$11.20
52Traffic control (643.5000)EACH1$1,000.00$8,525.00$1,000.00
53Geotextile type DF schedule A (645.0111)SY100$4.70$4.70$4.32
54Geotextile type HR (645.0120)SY280$3.50$4.00$4.70
55Marking line epoxy 4-inch (646.1020)LF1,350$3.00$3.00$3.85
56Construction staking subgrade (650.4500)LF520$0.01$0.01$0.75
57Construction staking base (650.5000)LF520$0.01$0.01$2.00
58Construction staking structure layout (structure) 01. B-37-0480 (650.6501)EACH1$3,000.00$3,000.00$3,300.00
59Construction staking supplemental control (project) 01. 9958-02-70 (650.9911)EACH1$1,000.00$1,000.00$735.00
60Construction staking slope stakes (650.9920)LF520$1.25$1.25$2.00
61Sawing asphalt (690.0150)LF130$2.00$2.00$2.45
62Incentive strength concrete structures (715.0502)DOL1,704$1.00$1.00$1.00
63Incentive compressive strength concrete pavement (715.0720)DOL500$1.00$1.00$1.00
64Maintaining bird deterrent system (station) 01. 10+00 (999.2005.S)EACH1$0.01$1.00$500.00
WisDOT contract 20250211046: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of February 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.