WisDOT contract 20250311018 bid tabulation

T Richmond, CTH A; W County Line to CTH P (CTH A, Walworth County T Richmond, CTH A). Let by Wisconsin DOT on March 11, 2025, Walworth. 2 bids received; low bid $2,993,656 by Payne and Dolan, Inc.

Owner
Wisconsin DOT
Letting
11 MAR 2025
Pay items
66
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Payne and Dolan, Inc$2,993,656Low
2Rock Road Companies, Inc.$3,154,431+5.0%
WisDOT contract 20250311018: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Payne and Dolan, Inc2. Rock Road Companies, Inc.
1Removing small pipe culverts (203.0100)EACH27$150.00$325.00
2Removing asphaltic surface butt joints (204.0115)SY893$0.01$0.10
3Removing asphaltic surface milling (204.0120)SY104,834$0.50$0.10
4Excavation common (205.0100)CY13,055$17.00$0.01
5Borrow (208.0100)CY5,175$22.75$0.01
6Temporary lane shift during culvert work (208.1500.S)EACH10$1,040.00$17,300
7Backfill granular grade 2 (209.2100)CY375$21.00$36.50
8Prepare foundation for asphaltic paving (project) 01. 3697-05-70 (211.0101)EACH1$1,000.00$28,008
9Finishing roadway (project) 01. 3697-05-70 (213.0100)EACH1$1,000.00$4,738.47
10Base aggregate dense 3/4-inch (305.0110)TON1,210$24.50$32.50
11Base aggregate dense 1 1/4-inch (305.0120)TON6,560$18.50$11.50
12Shaping shoulders (305.0500)STA311$1.00$8.91
13Tack coat (455.0605)GAL6,560$2.50$2.80
14HMA percent within limits (PWL) test strip volumetrics (460.0105.S)EACH1$780.00$3,500.00
15HMA percent within limits (PWL) test strip density (460.0110.S)EACH1$13,000$3,500.00
16Incentive density PWL HMA pavement (460.2005)DOL21,160$1.00$1.00
17Incentive density HMA pavement longitudinal joints (460.2007)DOL6,210$1.00$1.00
18Incentive air voids HMA pavement (460.2010)DOL27,530$1.00$1.00
19HMA pavement 4 LT 58-28 S (460.5224)TON27,530$63.45$70.00
20Asphaltic surface (465.0105)TON880$85.00$82.91
21Asphaltic surface driveways and field entrances (465.0120)TON465$163.00$108.14
22Cleaning culvert pipes (520.8700)EACH5$950.00$950.00
23Apron endwalls for culvert pipe steel 18-inch (521.1018)EACH30$185.00$410.00
24Apron endwalls for culvert pipe steel 21-inch (521.1021)EACH4$240.00$539.00
25Apron endwalls for culvert pipe steel 24-inch (521.1024)EACH16$252.00$617.00
26Apron endwalls for culvert pipe steel 30-inch (521.1030)EACH6$451.50$1,840.00
27Apron endwalls for culvert pipe steel 36-inch (521.1036)EACH2$695.35$1,200.00
28Culvert pipe corrugated steel 18- inch (521.3118)LF403$97.80$96.50
29Culvert pipe corrugated steel 21- inch (521.3121)LF40$153.26$106.00
30Culvert pipe corrugated steel 24- inch (521.3124)LF637$151.40$343.00
31Culvert pipe corrugated steel 30- inch (521.3130)LF268$290.00$381.00
32Culvert pipe corrugated steel 36- inch (521.3136)LF138$411.75$446.00
33Adjusting steel plate beam guard (614.0400)LF725$12.00$12.00
34Replacing guardrail posts and blocks (614.0950)EACH10$115.00$115.00
35Replacing guardrail rail and hardware (614.0951)LF50$20.00$20.00
36Replacing guardrail reflectors (614.0952)EACH10$15.00$15.00
37Mobilization (619.1000)EACH1$9,000.00$50,000
38Topsoil (625.0100)SY480$15.00$24.50
39Silt fence (628.1504)LF2,750$2.75$2.75
40Silt fence maintenance (628.1520)LF2,750$0.01$0.01
41Mobilizations erosion control (628.1905)EACH2$100.00$100.00
42Mobilizations emergency erosion control (628.1910)EACH2$100.00$100.00
43Erosion mat urban class I type B (628.2008)SY480$3.00$3.00
44Culvert pipe checks (628.7555)EACH39$25.00$25.00
45Fertilizer type A (629.0205)CWT2$200.00$200.00
46Seeding mixture no. 20 (630.0120)LB35$20.00$20.00
47Seeding temporary (630.0200)LB35$10.00$10.00
48Markers culvert end (633.5200)EACH26$65.00$65.00
49Posts wood 4X6-inch X 16-FT (634.0616)EACH46$90.00$90.00
50Posts wood 4X6-inch X 18-FT (634.0618)EACH11$95.00$95.00
51Signs type II reflective H (637.2210)SF219.77$20.00$20.00
52Signs type II reflective F (637.2230)SF159.50$22.00$22.00
53Removing signs type II (638.2602)EACH63$30.00$30.00
54Removing small sign supports (638.3000)EACH55$30.00$30.00
55Traffic control signs (643.0900)DAY1,700$0.50$0.50
56Traffic control (643.5000)EACH1$1,700.00$1,700.00
57Marking line epoxy 4-inch (646.1020)LF124,200$0.35$0.35
58Marking stop line epoxy 18-inch (646.6120)LF40$12.45$12.45
59Locating no-passing zones (648.0100)MI5.88$371.00$371.00
60Construction staking pipe culverts (650.6000)EACH11$150.00$200.00
61Construction staking resurfacing reference (650.8000)LF31,030$0.20$0.12
62Construction staking supplemental control (project) 01. 3697-05-70 (650.9911)EACH1$200.00$800.00
63Incentive iri ride (740.0440)DOL23,510$1.00$1.00
64On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS600$5.00$5.00
65On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS1,320$5.00$5.00
66Special 01. proof rolling (SPV.0170)STA311$1.00$25.90
WisDOT contract 20250311018: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of March 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy