1480-30-71. Let by Wisconsin DOT on March 11, 2025, Door. 3 bids received; low bid $3,889,233 by Peters Concrete Company.
- Owner
- Wisconsin DOT
- Letting
- 11 MAR 2025
- Pay items
- 152
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Peters Concrete Company | $3,889,233 | Low |
| 2 | Vinton Construction Company | $4,203,130 | +8.0% |
| 3 | Michels Road & Stone, Inc. | $4,537,539 | +17% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Peters Concrete Company | 2. Vinton Construction Company | 3. Michels Road & Stone, Inc. |
|---|---|---|---|---|---|---|
| 1 | Grubbing (201.0220) | ID | 27 | $25.00 | $20.00 | $36.00 |
| 2 | Roadside clearing (202.0105) | STA | 3 | $500.00 | $150.00 | $650.00 |
| 3 | Removing small pipe culverts (203.0100) | EACH | 2 | $200.00 | $365.00 | $400.00 |
| 4 | Removing asphaltic surface butt joints (204.0115) | SY | 12 | $145.00 | $145.00 | $145.00 |
| 5 | Removing asphaltic surface milling (204.0120) | SY | 455 | $8.60 | $8.60 | $8.60 |
| 6 | Removing curb & gutter (204.0150) | LF | 2,545 | $3.65 | $4.00 | $4.00 |
| 7 | Removing fence (204.0170) | LF | 550 | $3.50 | $3.50 | $3.50 |
| 8 | Removing delineators and markers (204.0180) | EACH | 18 | $15.00 | $15.00 | $15.00 |
| 9 | Removing manholes (204.0210) | EACH | 1 | $400.00 | $540.00 | $475.00 |
| 10 | Removing inlets (204.0220) | EACH | 8 | $250.00 | $320.00 | $375.00 |
| 11 | Removing storm sewer (size) 01. 18-inch (204.0245) | LF | 136 | $5.00 | $12.95 | $15.00 |
| 12 | Removing storm sewer (size) 02. 36-inch (204.0245) | LF | 50 | $5.00 | $18.50 | $18.00 |
| 13 | Removing storm sewer (size) 03. 48-inch (204.0245) | LF | 32 | $20.00 | $27.00 | $24.00 |
| 14 | Excavation common (205.0100) | CY | 15,228 | $14.80 | $16.25 | $12.90 |
| 15 | Borrow (208.0100) | CY | 2,666 | $0.10 | $0.01 | $0.01 |
| 16 | Finishing roadway (project) 01. 1480-30-71 (213.0100) | EACH | 1 | $1,000.00 | $2,500.00 | $7,500.00 |
| 17 | Finishing roadway (project) 02. 1480-30-72 (213.0100) | EACH | 1 | $1,000.00 | $2,500.00 | $7,500.00 |
| 18 | Base aggregate dense 3/4-inch (305.0110) | TON | 1,180 | $28.70 | $32.85 | $55.00 |
| 19 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 25,605 | $12.90 | $14.25 | $14.50 |
| 20 | Select crushed material (312.0110) | TON | 3,145 | $12.95 | $15.50 | $12.80 |
| 21 | Coloring concrete wisdot red (405.0100) | CY | 108 | $66.00 | $100.00 | $84.48 |
| 22 | Concrete truck apron 12-inch (415.2010) | SY | 323 | $81.00 | $104.50 | $153.04 |
| 23 | Drilled tie bars (416.0610) | EACH | 145 | $8.00 | $9.00 | $21.39 |
| 24 | Drilled dowel bars (416.0620) | EACH | 535 | $14.00 | $16.50 | $24.44 |
| 25 | Concrete pavement repair (416.1710) | SY | 385 | $84.45 | $105.00 | $241.23 |
| 26 | Concrete pavement replacement (416.1720) | SY | 810 | $84.45 | $105.00 | $239.52 |
| 27 | Tack coat (455.0605) | GAL | 1,570 | $4.50 | $4.50 | $4.50 |
| 28 | Incentive density HMA pavement (460.2000) | DOL | 5,520 | $1.00 | $1.00 | $1.00 |
| 29 | HMA pavement 3 MT 58-28 S (460.6223) | TON | 5,575 | $104.35 | $88.70 | $88.70 |
| 30 | HMA pavement 4 MT 58-28 H (460.6424) | TON | 3,050 | $113.80 | $98.15 | $98.15 |
| 31 | Asphaltic flumes (465.0315) | SY | 159 | $85.00 | $85.00 | $85.00 |
| 32 | Concrete collars for pipe (520.8000) | EACH | 20 | $300.00 | $835.00 | $675.00 |
| 33 | Apron endwalls for culvert pipe sloped side drains steel 18-inch 10 to 1 (521.1618) | EACH | 7 | $100.00 | $2,356.00 | $2,550.00 |
| 34 | Culvert pipe reinforced concrete class IV 18-inch (522.0418) | LF | 255 | $74.45 | $97.25 | $82.00 |
| 35 | Apron endwalls for culvert pipe reinforced concrete 18-inch (522.1018) | EACH | 5 | $1,400.00 | $1,485.00 | $1,445.75 |
| 36 | Apron endwalls for culvert pipe reinforced concrete 36-inch (522.1036) | EACH | 2 | $2,800.00 | $3,290.00 | $2,744.50 |
| 37 | Apron endwalls for culvert pipe reinforced concrete 48-inch (522.1048) | EACH | 2 | $3,800.00 | $4,310.00 | $3,815.00 |
| 38 | Concrete curb & gutter 4-inch sloped 36-inch type A (601.0551) | LF | 530 | $33.00 | $27.75 | $30.00 |
| 39 | Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557) | LF | 5,295 | $33.00 | $26.60 | $30.00 |
| 40 | Concrete sidewalk 4-inch (602.0405) | SF | 11,175 | $6.50 | $6.75 | $6.75 |
| 41 | Riprap light (606.0100) | CY | 60 | $50.00 | $104.00 | $115.00 |
| 42 | Storm sewer rock excavation (608.0005) | CY | 232 | $75.00 | $119.45 | $150.00 |
| 43 | Storm sewer pipe reinforced concrete class III 18-inch (608.0318) | LF | 168 | $88.60 | $97.45 | $86.00 |
| 44 | Storm sewer pipe reinforced concrete class III 36-inch (608.0336) | LF | 65 | $239.00 | $196.15 | $172.50 |
| 45 | Storm sewer pipe reinforced concrete class III 48-inch (608.0348) | LF | 51 | $376.00 | $292.80 | $279.00 |
| 46 | Storm sewer pipe reinforced concrete class IV 12-inch (608.0412) | LF | 74 | $95.60 | $106.15 | $90.00 |
| 47 | Storm sewer pipe reinforced concrete class IV 15-inch (608.0415) | LF | 131 | $101.40 | $103.80 | $80.00 |
| 48 | Storm sewer pipe reinforced concrete class IV 18-inch (608.0418) | LF | 229 | $104.00 | $104.00 | $86.00 |
| 49 | Storm sewer pipe reinforced concrete class IV 24-inch (608.0424) | LF | 358 | $111.50 | $111.55 | $108.00 |
| 50 | Storm sewer pipe class III-A 18- inch (608.3018) | LF | 526 | $62.06 | $81.80 | $61.00 |
| 51 | Manhole covers type J (611.0530) | EACH | 2 | $465.00 | $488.00 | $531.00 |
| 52 | Manhole covers type L (611.0545) | EACH | 2 | $335.00 | $363.00 | $403.00 |
| 53 | Inlet covers type HM (611.0627) | EACH | 13 | $720.00 | $724.00 | $68.00 |
| 54 | Inlet covers type HM-S (611.0636) | EACH | 4 | $720.00 | $724.00 | $781.50 |
| 55 | Inlet covers type MS (611.0642) | EACH | 9 | $460.00 | $500.00 | $544.00 |
| 56 | Manholes 4-FT diameter (611.2004) | EACH | 2 | $3,025.00 | $4,733.00 | $4,392.00 |
| 57 | Manholes 6-FT diameter (611.2006) | EACH | 1 | $7,680.00 | $9,566.00 | $8,930.00 |
| 58 | Manholes 7-FT diameter (611.2007) | EACH | 2 | $10,930 | $12,045 | $11,076 |
| 59 | Inlets 4-FT diameter (611.3004) | EACH | 10 | $3,070.00 | $4,707.00 | $3,750.00 |
| 60 | Inlets 2X3-FT (611.3230) | EACH | 6 | $2,100.00 | $3,315.00 | $3,091.00 |
| 61 | Inlets median 1 grate (611.3901) | EACH | 7 | $2,820.00 | $3,620.00 | $3,815.00 |
| 62 | Inlets median 2 grate (611.3902) | EACH | 1 | $4,250.00 | $4,532.00 | $4,374.00 |
| 63 | Fence woven wire (height) 01. 4- FT (616.0100) | LF | 180 | $13.50 | $13.50 | $13.50 |
| 64 | Fence chain link 5-FT (616.0205) | LF | 370 | $43.85 | $43.85 | $90.00 |
| 65 | Maintenance and repair of haul roads (project) 01. 1480-30-71 (618.0100) | EACH | 1 | $1.00 | $0.01 | $1.00 |
| 66 | Maintenance and repair of haul roads (project) 02. 1480-30-72 (618.0100) | EACH | 1 | $1.00 | $0.01 | $1.00 |
| 67 | Mobilization (619.1000) | EACH | 1 | $358,000 | $555,000 | $695,864 |
| 68 | Concrete median sloped nose (620.0300) | SF | 1,350 | $12.00 | $13.00 | $15.00 |
| 69 | Water (624.0100) | MGAL | 522 | $10.00 | $0.01 | $60.00 |
| 70 | Topsoil (625.0100) | SY | 27,600 | $1.76 | $2.75 | $2.50 |
| 71 | Silt fence (628.1504) | LF | 2,650 | $1.98 | $1.98 | $1.98 |
| 72 | Silt fence maintenance (628.1520) | LF | 2,650 | $0.01 | $0.01 | $0.01 |
| 73 | Mobilizations erosion control (628.1905) | EACH | 6 | $25.00 | $25.00 | $25.00 |
| 74 | Mobilizations emergency erosion control (628.1910) | EACH | 6 | $25.00 | $25.00 | $25.00 |
| 75 | Erosion mat urban class I type B (628.2008) | SY | 27,600 | $1.65 | $1.65 | $1.65 |
| 76 | Inlet protection type A (628.7005) | EACH | 19 | $50.00 | $50.00 | $50.00 |
| 77 | Inlet protection type C (628.7015) | EACH | 17 | $65.00 | $65.00 | $65.00 |
| 78 | Temporary ditch checks (628.7504) | LF | 45 | $9.00 | $9.00 | $9.00 |
| 79 | Culvert pipe checks (628.7555) | EACH | 67 | $14.00 | $14.00 | $14.00 |
| 80 | Fertilizer type B (629.0210) | CWT | 23 | $90.00 | $90.00 | $90.00 |
| 81 | Seeding mixture no. 30 (630.0130) | LB | 1,635 | $7.95 | $7.95 | $7.95 |
| 82 | Seeding temporary (630.0200) | LB | 980 | $4.00 | $4.00 | $4.00 |
| 83 | Seed water (630.0500) | MGAL | 2,060 | $2.00 | $2.00 | $2.00 |
| 84 | Markers culvert end (633.5200) | EACH | 27 | $66.00 | $66.00 | $66.00 |
| 85 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 35 | $84.00 | $84.00 | $84.00 |
| 86 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 48 | $88.00 | $88.00 | $88.00 |
| 87 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 57 | $94.00 | $94.00 | $94.00 |
| 88 | Signs type II reflective H (637.2210) | SF | 1,919.56 | $24.25 | $24.25 | $24.25 |
| 89 | Signs type II reflective F (637.2230) | SF | 16 | $24.15 | $24.15 | $24.15 |
| 90 | Removing signs type II (638.2602) | EACH | 71 | $30.00 | $30.00 | $30.00 |
| 91 | Removing small sign supports (638.3000) | EACH | 91 | $30.00 | $30.00 | $30.00 |
| 92 | Field office type B (642.5001) | EACH | 1 | $8,000.00 | $12,000 | $17,000 |
| 93 | Traffic control drums (643.0300) | DAY | 41,000 | $0.20 | $0.18 | $0.18 |
| 94 | Traffic control barricades type III (643.0420) | DAY | 6,378 | $1.00 | $0.50 | $0.50 |
| 95 | Traffic control warning lights type A (643.0705) | DAY | 9,956 | $0.10 | $0.12 | $0.12 |
| 96 | Traffic control warning lights type C (643.0715) | DAY | 7,250 | $0.10 | $0.12 | $0.12 |
| 97 | Traffic control signs (643.0900) | DAY | 16,618 | $0.50 | $0.24 | $0.24 |
| 98 | Traffic control covering signs type II (643.0920) | EACH | 55 | $19.00 | $90.00 | $90.00 |
| 99 | Traffic control signs fixed message (643.1000) | SF | 62 | $10.00 | $17.25 | $17.25 |
| 100 | Traffic control signs PCMS (643.1050) | DAY | 56 | $60.00 | $24.50 | $24.50 |
| 101 | Basic traffic queue warning system (643.1205.S) | DAY | 248 | $160.00 | $135.00 | $135.00 |
| 102 | Temporary marking line removable tape 6-inch (643.3180) | LF | 28,800 | $1.10 | $1.45 | $1.45 |
| 103 | Temporary marking removable mask out tape 6-inch (643.3960) | LF | 1,200 | $1.10 | $3.25 | $3.25 |
| 104 | Traffic control (643.5000) | EACH | 1 | $25,000 | $93,000 | $98,000 |
| 105 | Geotextile type HR (645.0120) | SY | 242 | $3.00 | $5.00 | $5.00 |
| 106 | Marking line epoxy 6-inch (646.2020) | LF | 3,200 | $1.25 | $1.25 | $1.25 |
| 107 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 14,235 | $1.85 | $1.85 | $1.85 |
| 108 | Marking line grooved permanent tape 6-inch (646.2050) | LF | 2,700 | $10.00 | $10.00 | $10.00 |
| 109 | Marking line grooved wet ref epoxy 10-inch (646.4040) | LF | 510 | $3.50 | $3.50 | $3.50 |
| 110 | Marking line grooved permanent tape 10-inch (646.4050) | LF | 16,480 | $12.00 | $12.00 | $12.00 |
| 111 | Marking arrow epoxy (646.5020) | EACH | 34 | $330.00 | $330.00 | $330.00 |
| 112 | Marking word epoxy (646.5120) | EACH | 14 | $340.00 | $340.00 | $340.00 |
| 113 | Marking stop line epoxy 18-inch (646.6120) | LF | 25 | $40.00 | $40.00 | $40.00 |
| 114 | Marking diagonal epoxy 12-inch (646.7120) | LF | 2,485 | $12.00 | $12.00 | $12.00 |
| 115 | Marking curb epoxy (646.8120) | LF | 60 | $17.00 | $17.00 | $17.00 |
| 116 | Marking island nose epoxy (646.8220) | EACH | 6 | $325.00 | $325.00 | $325.00 |
| 117 | Marking removal line 4-inch (646.9000) | LF | 8,790 | $0.45 | $0.70 | $0.70 |
| 118 | Marking removal line grooved contrast permanent tape 4-inch (646.9055) | LF | 2,700 | $1.10 | $3.10 | $3.10 |
| 119 | Marking removal line grooved contrast permanent tape 8-inch (646.9155) | LF | 3,065 | $1.10 | $3.75 | $3.75 |
| 120 | Construction staking storm sewer (650.4000) | EACH | 39 | $85.00 | $85.00 | $85.00 |
| 121 | Construction staking subgrade (650.4500) | LF | 14,429 | $0.01 | $0.01 | $0.01 |
| 122 | Construction staking base (650.5000) | LF | 14,429 | $0.30 | $0.30 | $0.30 |
| 123 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 5,825 | $0.90 | $0.90 | $0.90 |
| 124 | Construction staking pipe culverts (650.6000) | EACH | 3 | $190.00 | $190.00 | $190.00 |
| 125 | Construction staking resurfacing reference (650.8000) | LF | 147 | $0.07 | $0.07 | $0.07 |
| 126 | Construction staking electrical installations (project) 01. 1480-30- 71 (650.8501) | EACH | 1 | $3,000.00 | $3,000.00 | $3,000.00 |
| 127 | Construction staking electrical installations (project) 02. 1480-30- 72 (650.8501) | EACH | 1 | $3,000.00 | $3,000.00 | $3,000.00 |
| 128 | Construction staking sidewalk (project) 01. 1480-30-71 (650.9500) | EACH | 1 | $10.00 | $10.00 | $10.00 |
| 129 | Construction staking sidewalk (project) 02. 1480-30-72 (650.9500) | EACH | 1 | $10.00 | $10.00 | $10.00 |
| 130 | Construction staking supplemental control (project) 01. 1480-30-71 (650.9911) | EACH | 1 | $10.00 | $10.00 | $10.00 |
| 131 | Construction staking supplemental control (project) 02. 1480-30-72 (650.9911) | EACH | 1 | $10.00 | $10.00 | $10.00 |
| 132 | Construction staking slope stakes (650.9920) | LF | 12,236 | $0.60 | $0.60 | $0.60 |
| 133 | Conduit special 2-inch (652.0605) | LF | 3,555 | $22.00 | $22.00 | $22.00 |
| 134 | Conduit special 3-inch (652.0615) | LF | 1,300 | $75.00 | $75.00 | $75.00 |
| 135 | Pull boxes non-conductive 24X42- inch (653.0164) | EACH | 12 | $1,950.00 | $1,950.00 | $1,950.00 |
| 136 | Concrete bases type 5 (654.0105) | EACH | 26 | $1,775.00 | $1,775.00 | $1,775.00 |
| 137 | Concrete control cabinet bases type 10 (654.0220) | EACH | 2 | $2,000.00 | $2,000.00 | $2,000.00 |
| 138 | Electrical wire lighting 12 AWG (655.0610) | LF | 4,350 | $0.80 | $0.80 | $0.80 |
| 139 | Electrical wire lighting 10 AWG (655.0615) | LF | 23,437 | $0.90 | $0.90 | $0.90 |
| 140 | Electrical service meter breaker pedestal (location) 01. STH 57 & CTH H (656.0201) | EACH | 1 | $1,900.00 | $1,900.00 | $1,900.00 |
| 141 | Electrical service meter breaker pedestal (location) 02. STH 57 & stone road (656.0201) | EACH | 1 | $1,900.00 | $1,900.00 | $1,900.00 |
| 142 | Transformer bases breakaway 11 1/2-inch bolt circle (657.0255) | EACH | 26 | $600.00 | $600.00 | $600.00 |
| 143 | Poles type 5-aluminum (657.0322) | EACH | 26 | $1,500.00 | $1,500.00 | $1,500.00 |
| 144 | Luminaire arms truss type 4 1/2- inch clamp 12-FT (657.0710) | EACH | 30 | $650.00 | $650.00 | $650.00 |
| 145 | Luminaires utility LED A (659.1115) | EACH | 30 | $350.00 | $350.00 | $350.00 |
| 146 | Sawing asphalt (690.0150) | LF | 500 | $1.95 | $3.00 | $1.95 |
| 147 | Sawing concrete (690.0250) | LF | 1,040 | $2.95 | $3.50 | $2.95 |
| 148 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,000 | $5.00 | $5.00 | $5.00 |
| 149 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 1,320 | $5.00 | $5.00 | $5.00 |
| 150 | Special 01. digital speed reduction system (DSRS) (SPV.0045) | DAY | 816 | $63.00 | $22.50 | $22.50 |
| 151 | Special 02. connected work zone start and end location markers (SPV.0045) | DAY | 816 | $5.00 | $8.50 | $8.50 |
| 152 | Special 03. connected arrow board (SPV.0045) | DAY | 408 | $20.00 | $15.50 | $15.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of March 11, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.