WisDOT contract 20250311039 bid tabulation
Hudson - Baldwin; STH 35 S Interchange N-55,02,03,04 (IH 094, St Croix County Hudson - Baldwin). Let by Wisconsin DOT on March 11, 2025, St Croix. 2 bids received; low bid $3,566,073 by Zenith Tech., Inc. - Waukesha.
- Owner
- Wisconsin DOT
- Letting
- 11 MAR 2025
- Pay items
- 43
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Zenith Tech., Inc. - Waukesha | $3,566,073 | Low |
| 2 | Lunda Construction Company | $4,254,230 | +19% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Zenith Tech., Inc. - Waukesha | 2. Lunda Construction Company |
|---|---|---|---|---|---|
| 1 | Grubbing (201.0205) | STA | 4 | $550.00 | $550.00 |
| 2 | Grubbing (201.0220) | ID | 35 | $40.00 | $40.00 |
| 3 | Removing guardrail (204.0165) | LF | 14 | $15.60 | $15.60 |
| 4 | Removing fence (204.0170) | LF | 2,580 | $2.35 | $2.35 |
| 5 | Excavation common (205.0100) | CY | 16.90 | $65.00 | $65.00 |
| 6 | Finishing roadway (project) 01. 1020-00-85 (213.0100) | EACH | 1 | $5,000.00 | $500.00 |
| 7 | Base aggregate dense 3/4-inch (305.0110) | TON | 14 | $68.50 | $68.50 |
| 8 | Noise barriers double-sided sound absorptive (structure) 01. N-55-02 (541.0300.S) | SF | 12,995 | $80.00 | $73.00 |
| 9 | Noise barriers double-sided sound absorptive (structure) 02. N-55-03 (541.0300.S) | SF | 22,875 | $77.00 | $74.00 |
| 10 | Noise barriers double-sided sound absorptive (structure) 03. N-55-04 (541.0300.S) | SF | 3,425 | $85.00 | $78.00 |
| 11 | Adjusting steel plate beam guard (614.0400) | LF | 25 | $10.85 | $10.85 |
| 12 | MGS guardrail 3 (614.2300) | LF | 89 | $38.00 | $38.00 |
| 13 | MGS guardrail terminal type 2 (614.2620) | EACH | 1 | $3,792.00 | $3,792.00 |
| 14 | Fence woven wire (height) 01. 4- foot (616.0100) | LF | 48 | $31.00 | $31.00 |
| 15 | Mobilization (619.1000) | EACH | 1 | $384,500 | $1,261,722 |
| 16 | Water (624.0100) | MGAL | 1 | $165.00 | $165.00 |
| 17 | Salvaged topsoil (625.0500) | SY | 5,400 | $3.65 | $3.65 |
| 18 | Mulching (627.0200) | SY | 150 | $1.70 | $1.70 |
| 19 | Silt fence (628.1504) | LF | 255 | $2.90 | $2.90 |
| 20 | Silt fence maintenance (628.1520) | LF | 515 | $0.01 | $0.01 |
| 21 | Mobilizations erosion control (628.1905) | EACH | 4 | $365.00 | $365.00 |
| 22 | Mobilizations emergency erosion control (628.1910) | EACH | 2 | $365.00 | $365.00 |
| 23 | Erosion mat class I type A (628.2002) | SY | 2,200 | $1.20 | $1.20 |
| 24 | Erosion mat urban class I type A (628.2006) | SY | 3,100 | $1.70 | $1.70 |
| 25 | Soil stabilizer type B (628.6510) | ACRE | 0.11 | $1,935.00 | $1,935.00 |
| 26 | Temporary ditch checks (628.7504) | LF | 210 | $7.35 | $7.35 |
| 27 | Culvert pipe checks (628.7555) | EACH | 8 | $18.60 | $18.60 |
| 28 | Tracking pads (628.7560) | EACH | 3 | $710.00 | $710.00 |
| 29 | Fertilizer type B (629.0210) | CWT | 3.60 | $101.00 | $101.00 |
| 30 | Seeding mixture no. 30 (630.0130) | LB | 258 | $8.50 | $8.50 |
| 31 | Seeding borrow pit (630.0300) | LB | 4 | $7.75 | $7.75 |
| 32 | Seed water (630.0500) | MGAL | 129 | $10.45 | $10.45 |
| 33 | Field office type C (642.5201) | EACH | 1 | $7,500.00 | $6,500.00 |
| 34 | Traffic control drums (643.0300) | DAY | 5,224 | $0.20 | $0.20 |
| 35 | Traffic control arrow boards (643.0800) | DAY | 225 | $10.00 | $10.00 |
| 36 | Traffic control signs (643.0900) | DAY | 750 | $0.35 | $0.35 |
| 37 | Traffic control signs PCMS (643.1050) | DAY | 21 | $22.50 | $22.50 |
| 38 | Traffic control (643.5000) | EACH | 1 | $6,325.00 | $6,325.00 |
| 39 | Construction staking structure layout (structure) 01. N-55-02 (650.6501) | EACH | 1 | $2,100.00 | $2,100.00 |
| 40 | Construction staking structure layout (structure) 02. N-55-03 (650.6501) | EACH | 1 | $2,100.00 | $2,100.00 |
| 41 | Construction staking structure layout (structure) 03. N-55-04 (650.6501) | EACH | 1 | $2,100.00 | $2,100.00 |
| 42 | Construction staking supplemental control (project) 01. 1020-00-85 (650.9911) | EACH | 1 | $500.00 | $500.00 |
| 43 | Construction staking slope stakes (650.9920) | LF | 25 | $0.01 | $0.01 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of March 11, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.