WisDOT contract 20250408006 bid tabulation
C Beloit, State Street; Il State Line to USH 51 (STH 213, Rock County C Beloit, State Street). Let by Wisconsin DOT on April 8, 2025, Rock. 2 bids received; low bid $453,436 by Rock Road Companies, Inc..
- Owner
- Wisconsin DOT
- Letting
- 08 APR 2025
- Pay items
- 93
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rock Road Companies, Inc. | $453,436 | Low |
| 2 | Payne and Dolan, Inc | $487,369 | +7.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rock Road Companies, Inc. | 2. Payne and Dolan, Inc |
|---|---|---|---|---|---|
| 1 | Removing concrete pavement (204.0100) | SY | 135 | $5.16 | $27.00 |
| 2 | Removing asphaltic surface (204.0110) | SY | 200 | $4.98 | $5.00 |
| 3 | Removing asphaltic surface butt joints (204.0115) | SY | 64 | $9.55 | $35.00 |
| 4 | Removing asphaltic surface milling (204.0120) | SY | 6,305 | $3.40 | $1.50 |
| 5 | Removing curb & gutter (204.0150) | LF | 580 | $5.15 | $15.50 |
| 6 | Removing concrete sidewalk (204.0155) | SY | 480 | $10.37 | $33.35 |
| 7 | Removing concrete bases (204.0195) | EACH | 2 | $294.74 | $1,500.00 |
| 8 | Prepare foundation for asphaltic paving (project) 01. 5570-01-73 (211.0101) | EACH | 1 | $0.01 | $150.00 |
| 9 | Finishing roadway (project) 01. 5570-01-73 (213.0100) | EACH | 1 | $4,581.69 | $150.00 |
| 10 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 210 | $14.89 | $17.50 |
| 11 | Drilled tie bars (416.0610) | EACH | 80 | $10.00 | $10.00 |
| 12 | Tack coat (455.0605) | GAL | 431 | $3.71 | $2.00 |
| 13 | Incentive density HMA pavement (460.2000) | DOL | 460 | $1.00 | $1.00 |
| 14 | HMA pavement 4 MT 58-28 H (460.6424) | TON | 706 | $94.93 | $100.00 |
| 15 | Asphaltic surface (465.0105) | TON | 39 | $193.33 | $400.00 |
| 16 | Asphaltic surface patching (465.0110) | TON | 10 | $193.33 | $700.00 |
| 17 | Concrete curb & gutter 18-inch type D (601.0407) | LF | 26 | $40.00 | $40.00 |
| 18 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 303 | $46.75 | $46.75 |
| 19 | Concrete curb pedestrian (601.0600) | LF | 119 | $50.00 | $50.00 |
| 20 | Concrete sidewalk 4-inch (602.0405) | SF | 4,500 | $9.00 | $9.00 |
| 21 | Curb ramp detectable warning field natural patina (602.0515) | SF | 286 | $40.00 | $40.00 |
| 22 | Curb ramp detectable warning field radial natural patina (602.0615) | SF | 30 | $60.00 | $60.00 |
| 23 | Concrete driveway 6-inch (602.0810) | SY | 63 | $90.00 | $90.00 |
| 24 | Adjusting manhole covers (611.8110) | EACH | 21 | $1,107.07 | $1,000.00 |
| 25 | Maintenance and repair of haul roads (project) 01. 5570-01-03 (618.0100) | EACH | 1 | $0.01 | $150.00 |
| 26 | Mobilization (619.1000) | EACH | 1 | $35,664 | $61,000 |
| 27 | Water (624.0100) | MGAL | 2.10 | $0.01 | $1.00 |
| 28 | Silt fence (628.1504) | LF | 270 | $2.00 | $3.00 |
| 29 | Silt fence maintenance (628.1520) | LF | 270 | $1.00 | $1.00 |
| 30 | Mobilizations erosion control (628.1905) | EACH | 4 | $350.00 | $300.00 |
| 31 | Mobilizations emergency erosion control (628.1910) | EACH | 4 | $350.00 | $300.00 |
| 32 | Inlet protection type C (628.7015) | EACH | 11 | $75.00 | $75.00 |
| 33 | Inlet protection type D (628.7020) | EACH | 2 | $125.00 | $125.00 |
| 34 | Moving signs type II (638.2102) | EACH | 7 | $45.00 | $150.00 |
| 35 | Moving small sign supports (638.4000) | EACH | 3 | $200.00 | $100.00 |
| 36 | Field office type B (642.5001) | EACH | 1 | $3,000.00 | $1,500.00 |
| 37 | Traffic control drums (643.0300) | DAY | 2,624 | $0.49 | $0.49 |
| 38 | Traffic control barricades type III (643.0420) | DAY | 340 | $1.20 | $1.20 |
| 39 | Traffic control flexible tubular marker posts (643.0500) | EACH | 14 | $15.46 | $15.46 |
| 40 | Traffic control flexible tubular marker bases (643.0600) | EACH | 14 | $23.74 | $23.74 |
| 41 | Traffic control warning lights type A (643.0705) | DAY | 611 | $0.13 | $0.13 |
| 42 | Traffic control warning lights type C (643.0715) | DAY | 400 | $0.19 | $0.19 |
| 43 | Traffic control arrow boards (643.0800) | DAY | 72 | $10.96 | $10.96 |
| 44 | Traffic control signs (643.0900) | DAY | 3,404 | $0.34 | $0.34 |
| 45 | Traffic control covering signs type II (643.0920) | EACH | 9 | $64.03 | $64.03 |
| 46 | Traffic control signs PCMS (643.1050) | DAY | 28 | $35.63 | $35.63 |
| 47 | Temporary marking line removable tape 6-inch (643.3180) | LF | 1,800 | $2.40 | $2.40 |
| 48 | Temporary marking crosswalk paint 6-inch (643.3305) | LF | 476 | $10.00 | $10.00 |
| 49 | Temporary marking arrow removable tape (643.3550) | EACH | 1 | $269.92 | $269.92 |
| 50 | Temporary marking stop line paint 18-inch (643.3805) | LF | 86 | $11.00 | $11.00 |
| 51 | Traffic control (643.5000) | EACH | 1 | $15,659 | $15,659 |
| 52 | Temporary pedestrian surface asphalt (644.1410) | SF | 300 | $10.46 | $20.00 |
| 53 | Temporary pedestrian curb ramp (644.1601) | DAY | 32 | $16.07 | $16.07 |
| 54 | Temporary pedestrian detectable warning field (644.1605) | SF | 40 | $11.10 | $11.10 |
| 55 | Temporary pedestrian barricade (644.1810) | LF | 1,344 | $3.45 | $3.45 |
| 56 | Marking line epoxy 6-inch (646.2020) | LF | 1,941 | $1.70 | $1.70 |
| 57 | Marking line epoxy 10-inch (646.4020) | LF | 430 | $2.85 | $2.85 |
| 58 | Marking arrow epoxy (646.5020) | EACH | 10 | $225.00 | $225.00 |
| 59 | Marking railroad crossing epoxy (646.5320) | EACH | 8 | $1,475.00 | $1,475.00 |
| 60 | Marking stop line epoxy 18-inch (646.6120) | LF | 215 | $13.00 | $13.00 |
| 61 | Marking diagonal epoxy 6-inch (646.7020) | LF | 63 | $8.50 | $8.50 |
| 62 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 830 | $10.50 | $10.50 |
| 63 | Marking parking stall epoxy (646.8320) | LF | 80 | $4.50 | $4.50 |
| 64 | Marking removal line water blasting 4-inch (646.9010) | LF | 15 | $9.00 | $9.00 |
| 65 | Marking removal line water blasting 6-inch (646.9012) | LF | 517 | $9.10 | $9.10 |
| 66 | Marking removal line water blasting wide (646.9210) | LF | 93 | $14.00 | $14.00 |
| 67 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 670 | $3.00 | $3.00 |
| 68 | Construction staking resurfacing reference (650.8000) | LF | 910 | $0.95 | $0.95 |
| 69 | Construction staking electrical installations (project) 01. 5570-01- 73 (650.8501) | EACH | 1 | $300.00 | $300.00 |
| 70 | Construction staking curb ramps (650.9000) | EACH | 25 | $190.00 | $190.00 |
| 71 | Construction staking sidewalk (project) 01. 5570-01-73 (650.9500) | EACH | 1 | $1,900.00 | $1,900.00 |
| 72 | Construction staking supplemental control (project) 01. 5570-01-73 (650.9911) | EACH | 1 | $1,200.00 | $1,200.00 |
| 73 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 123 | $15.00 | $15.00 |
| 74 | Install conduit into existing item (652.0700.S) | EACH | 2 | $300.00 | $300.00 |
| 75 | Pull boxes non-conductive 24X42- inch (653.0164) | EACH | 1 | $2,500.00 | $2,500.00 |
| 76 | Removing pull boxes (653.0905) | EACH | 1 | $245.13 | $1,250.00 |
| 77 | Electrical wire lighting 12 AWG (655.0610) | LF | 1,137 | $3.00 | $3.00 |
| 78 | Sawing asphalt (690.0150) | LF | 240 | $1.69 | $1.75 |
| 79 | Sawing concrete (690.0250) | LF | 790 | $2.50 | $2.35 |
| 80 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 1,200 | $5.00 | $5.00 |
| 81 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 600 | $5.00 | $5.00 |
| 82 | Special 01. adjusting water valve boxes (SPV.0060) | EACH | 10 | $480.89 | $750.00 |
| 83 | Special 02. research and locate existing land parcel monuments (SPV.0060) | EACH | 14 | $100.00 | $100.00 |
| 84 | Special 03. verify and replace existing land parcel monuments (SPV.0060) | EACH | 14 | $100.00 | $100.00 |
| 85 | Special 04. bagging signal head (SPV.0060) | EACH | 3 | $500.00 | $500.00 |
| 86 | Special 05. salvage street light sta 13+70 LT (SPV.0060) | EACH | 1 | $1,700.00 | $1,700.00 |
| 87 | Special 06. salvage street light sta 13+77 RT (SPV.0060) | EACH | 1 | $1,700.00 | $1,700.00 |
| 88 | Special 07. grading, shaping, & finishing curb ramps one ramp (SPV.0060) | EACH | 9 | $1,787.29 | $775.00 |
| 89 | Special 08. grading, shaping, & finishing curb ramps two ramps (SPV.0060) | EACH | 8 | $2,604.37 | $775.00 |
| 90 | Special 09. grading, shaping, & finishing driveways (SPV.0060) | EACH | 1 | $3,937.83 | $850.00 |
| 91 | Special 01. joint and crack plunge milling and patching (SPV.0090) | LF | 480 | $23.36 | $40.00 |
| 92 | Special 02. concrete curb & gutter 30-inch type A modified (SPV.0090) | LF | 63 | $66.85 | $66.85 |
| 93 | Special 03. concrete curb & gutter 30-inch type D modified (SPV.0090) | LF | 159 | $53.30 | $53.30 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of April 8, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.