WisDOT contract 20250408011 bid tabulation
V Rochester CTH A; Intersection With CTH J (CTH J, Racine County V Rochester - CTH A Intersection). Let by Wisconsin DOT on April 8, 2025, Racine. 6 bids received; low bid $2,097,599 by Musson Bros., Inc..
- Owner
- Wisconsin DOT
- Letting
- 08 APR 2025
- Pay items
- 127
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Musson Bros., Inc. | $2,097,599 | Low |
| 2 | Willkomm Excav. & Grading | $2,179,167 | +4.0% |
| 3 | Wanasek, the Corp. | $2,189,189 | +4.0% |
| 4 | A.W. Oakes & Son, Inc. | $2,318,713 | +11% |
| 5 | James Peterson Sons, Inc. | $2,378,229 | +13% |
| 6 | Michels Road & Stone, Inc. | $2,416,322 | +15% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Musson Bros., Inc. | 2. Willkomm Excav. & Grading | 3. Wanasek, the Corp. | 4. A.W. Oakes & Son, Inc. | 5. James Peterson Sons, Inc. | 6. Michels Road & Stone, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Grubbing (201.0205) | STA | 17 | $265.00 | $276.47 | $270.00 | $300.00 | $265.00 | $265.00 |
| 2 | Removing small pipe culverts (203.0100) | EACH | 15 | $321.65 | $508.08 | $480.00 | $368.00 | $500.00 | $1,214.00 |
| 3 | Removing asphaltic surface milling (204.0120) | SY | 1,020 | $5.60 | $5.84 | $5.70 | $6.00 | $5.60 | $5.60 |
| 4 | Removing guardrail (204.0165) | LF | 820 | $5.00 | $2.87 | $5.00 | $5.00 | $5.00 | $5.00 |
| 5 | Removing fence (204.0170) | LF | 1,260 | $10.00 | $2.40 | $3.25 | $10.00 | $10.00 | $10.00 |
| 6 | Removing utility poles (204.0205) | EACH | 1 | $500.00 | $532.05 | $114.00 | $1,000.00 | $1,500.00 | $600.00 |
| 7 | Removing catch basins (204.0215) | EACH | 1 | $430.31 | $966.08 | $543.00 | $260.00 | $500.00 | $862.00 |
| 8 | Excavation common (205.0100) | CY | 26,590 | $9.31 | $12.60 | $9.50 | $11.77 | $15.62 | $12.60 |
| 9 | Finishing roadway (project) 01. 2814-03-70 (213.0100) | EACH | 1 | $500.00 | $3,330.29 | $3,790.00 | $4,000.00 | $3,000.00 | $5,500.00 |
| 10 | Base aggregate dense 3/4-inch (305.0110) | TON | 370 | $26.86 | $59.90 | $49.50 | $25.72 | $41.48 | $41.50 |
| 11 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 10,400 | $12.69 | $16.03 | $15.70 | $17.23 | $15.47 | $14.70 |
| 12 | Base aggregate dense 3-inch (305.0130) | TON | 13,950 | $0.01 | $14.86 | $16.00 | $21.20 | $21.31 | $15.30 |
| 13 | Select crushed material (312.0110) | TON | 10,500 | $21.82 | $15.59 | $21.00 | $19.49 | $20.99 | $25.90 |
| 14 | Coloring concrete wisdot red (405.0100) | CY | 108 | $266.37 | $277.90 | $271.00 | $200.00 | $266.37 | $266.37 |
| 15 | Concrete truck apron 12-inch (415.2010) | SY | 554 | $92.08 | $96.07 | $94.00 | $87.50 | $92.08 | $92.08 |
| 16 | Tack coat (455.0605) | GAL | 771 | $2.00 | $2.09 | $2.00 | $2.00 | $2.00 | $2.00 |
| 17 | Incentive density HMA pavement (460.2000) | DOL | 2,050 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 18 | HMA pavement 3 LT 58-28 S (460.5223) | TON | 1,960 | $73.45 | $76.63 | $74.80 | $75.00 | $73.45 | $73.45 |
| 19 | HMA pavement 4 LT 58-28 S (460.5224) | TON | 1,240 | $73.45 | $76.63 | $74.80 | $75.00 | $73.45 | $73.45 |
| 20 | Asphaltic surface driveways and field entrances (465.0120) | TON | 70 | $130.00 | $135.60 | $133.00 | $150.00 | $130.00 | $130.00 |
| 21 | Asphaltic flumes (465.0315) | SY | 119 | $36.00 | $37.56 | $37.00 | $40.00 | $36.00 | $36.00 |
| 22 | Apron endwalls for culvert pipe 24- inch (520.1024) | EACH | 4 | $806.79 | $1,377.14 | $810.00 | $1,376.00 | $450.00 | $1,780.00 |
| 23 | Culvert pipe class IV 24-inch (520.4124) | LF | 208 | $87.42 | $114.76 | $87.00 | $94.00 | $95.00 | $130.00 |
| 24 | Apron endwalls for culvert pipe steel 12-inch (521.1012) | EACH | 2 | $266.63 | $188.84 | $213.00 | $401.00 | $300.00 | $387.00 |
| 25 | Apron endwalls for culvert pipe steel 15-inch (521.1015) | EACH | 6 | $287.75 | $213.87 | $218.00 | $428.00 | $300.00 | $411.00 |
| 26 | Apron endwalls for culvert pipe steel 18-inch (521.1018) | EACH | 12 | $368.55 | $238.91 | $247.00 | $464.00 | $350.00 | $435.00 |
| 27 | Culvert pipe corrugated steel 15- inch (521.3115) | LF | 120 | $83.26 | $81.38 | $72.00 | $57.00 | $60.00 | $82.00 |
| 28 | Culvert pipe corrugated steel 18- inch (521.3118) | LF | 222 | $95.92 | $81.38 | $78.00 | $65.00 | $70.00 | $71.00 |
| 29 | Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012) | EACH | 1 | $1,068.15 | $927.48 | $635.00 | $670.00 | $1,400.00 | $1,535.00 |
| 30 | Culvert pipe salvaged 12-inch (524.0112) | LF | 28 | $69.12 | $73.03 | $75.00 | $93.00 | $60.00 | $71.00 |
| 31 | Concrete curb & gutter 18-inch type A (601.0405) | LF | 174 | $23.28 | $24.29 | $23.70 | $35.75 | $23.28 | $23.28 |
| 32 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 1,321 | $22.43 | $23.40 | $22.85 | $25.00 | $22.43 | $22.43 |
| 33 | Concrete curb & gutter 6-inch sloped 30-inch type G (601.0413) | LF | 91 | $29.83 | $31.12 | $31.00 | $50.00 | $29.83 | $29.83 |
| 34 | Concrete curb & gutter 4-inch sloped 36-inch type D (601.0553) | LF | 1,586 | $23.82 | $24.85 | $24.25 | $24.45 | $23.82 | $23.82 |
| 35 | Concrete sidewalk 4-inch (602.0405) | SF | 8,530 | $4.61 | $4.81 | $4.70 | $6.00 | $4.61 | $4.61 |
| 36 | Riprap medium (606.0200) | CY | 5 | $303.56 | $258.73 | $142.00 | $120.00 | $265.00 | $230.00 |
| 37 | Riprap heavy (606.0300) | CY | 83 | $132.75 | $186.75 | $106.00 | $137.00 | $122.50 | $194.00 |
| 38 | Storm sewer pipe reinforced concrete class IV 12-inch (608.0412) | LF | 50 | $83.45 | $109.54 | $79.00 | $90.60 | $95.00 | $99.00 |
| 39 | Inlet covers type T (611.0652) | EACH | 1 | $1,329.22 | $1,000.51 | $990.00 | $1,264.00 | $1,000.00 | $1,250.00 |
| 40 | Inlets 2X2.5-FT (611.3225) | EACH | 1 | $1,747.70 | $2,979.63 | $2,150.00 | $1,557.00 | $2,650.00 | $1,917.00 |
| 41 | Pipe underdrain 6-inch (612.0106) | LF | 158 | $15.89 | $41.73 | $23.00 | $13.00 | $15.00 | $9.00 |
| 42 | Drain tile exploration (612.0700) | LF | 400 | $3.57 | $40.78 | $14.00 | $2.00 | $15.00 | $15.00 |
| 43 | MGS guardrail 3 (614.2300) | LF | 904 | $30.00 | $31.09 | $30.50 | $30.00 | $30.00 | $30.00 |
| 44 | MGS guardrail short radius (614.2350) | LF | 13 | $46.00 | $41.52 | $47.00 | $50.00 | $46.00 | $46.00 |
| 45 | MGS guardrail terminal eat (614.2610) | EACH | 5 | $5,000.00 | $4,392.23 | $5,090.00 | $5,000.00 | $5,000.00 | $5,000.00 |
| 46 | MGS guardrail terminal type 2 (614.2620) | EACH | 1 | $4,000.00 | $4,381.80 | $4,072.00 | $4,000.00 | $4,000.00 | $4,000.00 |
| 47 | MGS guardrail short radius terminal (614.2630) | EACH | 1 | $3,500.00 | $4,068.81 | $3,563.00 | $3,500.00 | $3,500.00 | $3,500.00 |
| 48 | Fencing small animal (616.0120.S) | LF | 3,200 | $22.00 | $43.82 | $23.00 | $25.00 | $22.00 | $22.00 |
| 49 | Maintenance and repair of haul roads (project) 01. 2814-03-70 (618.0100) | EACH | 1 | $1.00 | $737.17 | $1,475.00 | $0.01 | $100.00 | $0.01 |
| 50 | Mobilization (619.1000) | EACH | 1 | $380,000 | $40,410 | $173,035 | $146,500 | $132,850 | $243,378 |
| 51 | Concrete median sloped nose (620.0300) | SF | 387 | $13.87 | $14.47 | $14.00 | $15.00 | $13.87 | $13.87 |
| 52 | Water (624.0100) | MGAL | 210 | $0.01 | $23.89 | $18.00 | $41.00 | $44.00 | $60.00 |
| 53 | Topsoil (625.0100) | SY | 3,040 | $0.01 | $5.08 | $3.80 | $0.01 | $2.99 | $3.70 |
| 54 | Salvaged topsoil (625.0500) | SY | 15,100 | $1.57 | $2.42 | $1.90 | $2.30 | $1.99 | $2.40 |
| 55 | Silt fence (628.1504) | LF | 176 | $10.00 | $5.22 | $4.00 | $4.00 | $4.00 | $4.00 |
| 56 | Silt fence maintenance (628.1520) | LF | 176 | $1.00 | $0.01 | $1.00 | $1.00 | $1.00 | $1.00 |
| 57 | Silt fence heavy duty (628.1530.S) | LF | 1,720 | $10.00 | $13.68 | $10.00 | $10.00 | $10.00 | $10.00 |
| 58 | Silt fence heavy duty maintenance (628.1535.S) | LF | 1,720 | $1.00 | $0.01 | $1.00 | $1.00 | $1.00 | $1.00 |
| 59 | Mobilizations erosion control (628.1905) | EACH | 6 | $500.00 | $52.17 | $510.00 | $500.00 | $500.00 | $500.00 |
| 60 | Mobilizations emergency erosion control (628.1910) | EACH | 4 | $250.00 | $2.09 | $255.00 | $250.00 | $250.00 | $250.00 |
| 61 | Erosion mat urban class I type A (628.2006) | SY | 15,100 | $2.25 | $2.09 | $2.30 | $2.50 | $2.25 | $2.25 |
| 62 | Erosion mat urban class I type B (628.2008) | SY | 3,060 | $2.25 | $2.09 | $2.30 | $2.50 | $2.25 | $2.25 |
| 63 | Inlet protection type A (628.7005) | EACH | 1 | $200.00 | $156.49 | $204.00 | $200.00 | $200.00 | $200.00 |
| 64 | Inlet protection type D (628.7020) | EACH | 1 | $200.00 | $156.49 | $204.00 | $200.00 | $200.00 | $200.00 |
| 65 | Temporary ditch checks (628.7504) | LF | 251 | $12.00 | $8.35 | $12.00 | $15.00 | $12.00 | $12.00 |
| 66 | Culvert pipe checks (628.7555) | EACH | 29 | $30.00 | $18.78 | $31.00 | $30.00 | $30.00 | $30.00 |
| 67 | Tracking pads (628.7560) | EACH | 4 | $500.00 | $1,493.99 | $3,210.00 | $0.01 | $500.00 | $500.00 |
| 68 | Seeding mixture no. 30 (630.0130) | LB | 114 | $30.00 | $9.39 | $31.00 | $30.00 | $30.00 | $30.00 |
| 69 | Seeding mixture no. 60 (630.0160) | LB | 18 | $75.00 | $9.39 | $77.00 | $75.00 | $75.00 | $75.00 |
| 70 | Seeding temporary (630.0200) | LB | 397 | $6.00 | $3.55 | $6.00 | $6.00 | $6.00 | $6.00 |
| 71 | Seed water (630.0500) | MGAL | 400 | $10.00 | $5.22 | $10.00 | $10.00 | $10.00 | $10.00 |
| 72 | Sod water (631.0300) | MGAL | 1 | $100.00 | $5.22 | $102.00 | $100.00 | $100.00 | $100.00 |
| 73 | Sod erosion control (631.1100) | SY | 25 | $25.00 | $15.65 | $26.00 | $25.00 | $25.00 | $25.00 |
| 74 | Markers culvert end (633.5200) | EACH | 25 | $85.00 | $72.72 | $87.00 | $85.00 | $85.00 | $85.00 |
| 75 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 2 | $150.00 | $156.50 | $153.00 | $150.00 | $150.00 | $150.00 |
| 76 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 36 | $165.00 | $125.19 | $168.00 | $170.00 | $165.00 | $165.00 |
| 77 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 10 | $185.00 | $135.63 | $189.00 | $190.00 | $185.00 | $185.00 |
| 78 | Posts wood 4X6-inch X 20-FT (634.0620) | EACH | 10 | $215.00 | $156.49 | $219.00 | $220.00 | $215.00 | $215.00 |
| 79 | Posts wood 4X6-inch X 22-FT (634.0622) | EACH | 12 | $225.00 | $177.36 | $229.00 | $230.00 | $225.00 | $225.00 |
| 80 | Signs type II reflective H (637.2210) | SF | 528 | $34.00 | $24.10 | $35.00 | $35.00 | $34.00 | $34.00 |
| 81 | Signs type II reflective F (637.2230) | SF | 161 | $34.00 | $24.10 | $35.00 | $35.00 | $34.00 | $34.00 |
| 82 | Moving signs type II (638.2102) | EACH | 2 | $50.00 | $83.47 | $51.00 | $50.00 | $50.00 | $50.00 |
| 83 | Removing signs type II (638.2602) | EACH | 52 | $50.00 | $15.65 | $51.00 | $50.00 | $50.00 | $50.00 |
| 84 | Removing small sign supports (638.3000) | EACH | 38 | $100.00 | $18.78 | $102.00 | $100.00 | $100.00 | $100.00 |
| 85 | Field office type B (642.5001) | EACH | 1 | $8,000.00 | $9,911.21 | $8,800.00 | $15,000 | $17,000 | $13,500 |
| 86 | Traffic control drums (643.0300) | DAY | 1,110 | $0.25 | $0.26 | $0.25 | $0.30 | $0.25 | $0.25 |
| 87 | Traffic control barricades type III (643.0420) | DAY | 888 | $0.65 | $0.68 | $3.05 | $3.00 | $3.00 | $3.00 |
| 88 | Traffic control signs (643.0900) | DAY | 32,750 | $0.25 | $0.26 | $0.15 | $0.20 | $0.15 | $0.15 |
| 89 | Traffic control signs PCMS (643.1050) | DAY | 28 | $35.00 | $36.52 | $36.00 | $40.00 | $35.00 | $35.00 |
| 90 | Traffic control (643.5000) | EACH | 1 | $8,660.00 | $9,034.85 | $8,400.00 | $9,000.00 | $8,250.00 | $8,250.00 |
| 91 | Geotextile type HR (645.0120) | SY | 138 | $3.29 | $10.04 | $3.00 | $5.00 | $10.00 | $7.00 |
| 92 | Geotextile type sas (645.0140) | SY | 6,980 | $0.89 | $1.17 | $1.50 | $2.00 | $2.25 | $2.60 |
| 93 | Marking line epoxy 4-inch (646.1020) | LF | 7,890 | $1.22 | $1.27 | $0.45 | $0.50 | $0.42 | $0.42 |
| 94 | Marking line epoxy 8-inch (646.3020) | LF | 192 | $2.44 | $2.55 | $1.55 | $1.50 | $1.50 | $1.50 |
| 95 | Marking dotted extension epoxy 18-inch (646.6320) | LF | 78 | $19.75 | $20.60 | $15.00 | $15.00 | $14.65 | $14.65 |
| 96 | Marking diagonal epoxy 12-inch (646.7120) | LF | 321 | $13.15 | $13.72 | $15.00 | $15.00 | $14.50 | $14.50 |
| 97 | Marking curb epoxy (646.8120) | LF | 281 | $8.25 | $8.61 | $7.00 | $10.00 | $7.00 | $7.00 |
| 98 | Marking island nose epoxy (646.8220) | EACH | 6 | $250.00 | $260.82 | $285.00 | $300.00 | $280.00 | $280.00 |
| 99 | Construction staking storm sewer (650.4000) | EACH | 2 | $105.00 | $245.17 | $107.00 | $500.00 | $105.00 | $250.00 |
| 100 | Construction staking subgrade (650.4500) | LF | 2,955 | $0.01 | $1.56 | $0.05 | $0.01 | $0.01 | $0.01 |
| 101 | Construction staking base (650.5000) | LF | 2,955 | $1.75 | $1.77 | $1.80 | $0.01 | $1.75 | $1.50 |
| 102 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 3,434 | $2.50 | $1.15 | $2.55 | $1.00 | $2.50 | $1.75 |
| 103 | Construction staking pipe culverts (650.6000) | EACH | 12 | $110.00 | $110.07 | $112.00 | $150.00 | $110.00 | $250.00 |
| 104 | Construction staking electrical installations (project) 01. 2814-03- 70 (650.8501) | EACH | 1 | $840.00 | $1,314.54 | $855.00 | $2,000.00 | $840.00 | $2,000.00 |
| 105 | Construction staking sidewalk (project) 01. 2814-03-70 (650.9500) | EACH | 1 | $1,200.00 | $1,512.77 | $1,225.00 | $0.01 | $1,200.00 | $1,500.00 |
| 106 | Construction staking supplemental control (project) 01. 2814-03-70 (650.9911) | EACH | 1 | $1,400.00 | $1,356.27 | $1,425.00 | $5,000.00 | $1,400.00 | $1,600.00 |
| 107 | Construction staking slope stakes (650.9920) | LF | 2,955 | $0.50 | $0.78 | $0.55 | $1.00 | $0.50 | $1.30 |
| 108 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 1,983 | $9.82 | $10.25 | $10.00 | $10.00 | $9.82 | $9.82 |
| 109 | Conduit rigid nonmetallic schedule 40 3-inch (652.0235) | LF | 434 | $13.46 | $14.04 | $13.70 | $14.00 | $13.46 | $13.46 |
| 110 | Pull boxes steel 24X42-inch (653.0140) | EACH | 8 | $1,482.75 | $1,546.93 | $1,510.00 | $1,500.00 | $1,482.75 | $1,482.75 |
| 111 | Concrete bases type 5 (654.0105) | EACH | 12 | $1,120.79 | $1,169.30 | $1,140.00 | $1,200.00 | $1,120.79 | $1,120.79 |
| 112 | Concrete control cabinet bases type L24 (654.0224) | EACH | 1 | $1,507.71 | $1,572.98 | $1,535.00 | $1,550.00 | $1,507.71 | $1,507.71 |
| 113 | Electrical wire lighting 12 AWG (655.0610) | LF | 1,548 | $0.93 | $0.97 | $1.00 | $1.00 | $0.93 | $0.93 |
| 114 | Electrical wire lighting 8 AWG (655.0620) | LF | 10,128 | $1.27 | $1.32 | $1.30 | $1.30 | $1.27 | $1.27 |
| 115 | Electrical service meter breaker pedestal (location) 01. 1127+93.50,72.61'LT (656.0201) | EACH | 1 | $1,427.36 | $1,489.14 | $1,450.00 | $1,500.00 | $1,427.36 | $1,427.36 |
| 116 | Transformer bases breakaway 11 1/2-inch bolt circle (657.0255) | EACH | 12 | $658.41 | $686.91 | $670.00 | $700.00 | $658.41 | $658.41 |
| 117 | Poles type 5-aluminum (657.0322) | EACH | 12 | $2,049.78 | $2,138.51 | $2,090.00 | $2,050.00 | $2,049.78 | $2,049.78 |
| 118 | Luminaire arms single member 4- inch clamp 8-FT (657.0614) | EACH | 12 | $293.23 | $305.92 | $300.00 | $300.00 | $293.23 | $293.23 |
| 119 | Luminaires utility LED A (659.1115) | EACH | 12 | $402.91 | $420.35 | $410.00 | $425.00 | $402.91 | $402.91 |
| 120 | Lighting control cabinets 120/240 24-inch (659.2124) | EACH | 1 | $8,992.99 | $9,382.26 | $9,155.00 | $9,000.00 | $8,992.99 | $8,992.99 |
| 121 | Sawing asphalt (690.0150) | LF | 750 | $1.20 | $2.03 | $2.00 | $2.00 | $1.20 | $1.69 |
| 122 | Incentive compressive strength concrete pavement (715.0720) | DOL | 500 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 123 | Incentive iri ride (740.0440) | DOL | 960 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 124 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 800 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 125 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 2,280 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 126 | Special 01. silt fence turtle exclusion barrier (SPV.0090) | LF | 3,040 | $10.00 | $12.52 | $10.00 | $12.00 | $10.00 | $10.00 |
| 127 | Special 02. concrete curb and gutter 3-inch sloped 36-inch, type T (SPV.0090) | LF | 262 | $25.17 | $26.26 | $26.00 | $40.00 | $25.17 | $25.17 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of April 8, 2025. Compiled by Mirage Metrics.