WisDOT contract 20250408020 bid tabulation
Hudson - Baldwin; St Croix River B-55-0061, B-55-0126 (IH 094, St Croix County Hudson - Baldwin). Let by Wisconsin DOT on April 8, 2025, St Croix. 2 bids received; low bid $9,848,188 by Lunda Construction Company.
- Owner
- Wisconsin DOT
- Letting
- 08 APR 2025
- Pay items
- 150
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Lunda Construction Company | $9,848,188 | Low |
| 2 | Zenith Tech., Inc. - Waukesha | $10,339,172 | +5.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Lunda Construction Company | 2. Zenith Tech., Inc. - Waukesha |
|---|---|---|---|---|---|
| 1 | Removing structure (structure) 01. R-55-21 (203.0220) | EACH | 1 | $19,295 | $19,295 |
| 2 | Removing structure over waterway debris capture (structure) 01. B-55- 61 (203.0270) | EACH | 1 | $25,000 | $375,000 |
| 3 | Removing structure over waterway debris capture (structure) 02. B-55- 126 (203.0270) | EACH | 1 | $1,000.00 | $350,000 |
| 4 | Debris containment over waterway (structure) 01. B-55-61 (203.0335) | EACH | 1 | $500.00 | $150,000 |
| 5 | Debris containment over waterway (structure) 02. B-55-126 (203.0335) | EACH | 1 | $500.00 | $150,000 |
| 6 | Removing concrete pavement (204.0100) | SY | 440 | $34.50 | $62.15 |
| 7 | Removing asphaltic surface (204.0110) | SY | 8,028 | $6.70 | $6.70 |
| 8 | Removing curb & gutter (204.0150) | LF | 173 | $12.95 | $12.95 |
| 9 | Removing guardrail (204.0165) | LF | 317 | $3.50 | $3.50 |
| 10 | Removing concrete slope paving (204.0175) | SY | 150 | $103.50 | $103.50 |
| 11 | Excavation common (205.0100) | CY | 211 | $64.55 | $64.55 |
| 12 | Excavation for structures bridges (structure) 01. B-55-61 (206.1001) | EACH | 1 | $40,000 | $25,000 |
| 13 | Excavation for structures retaining walls (structure) 01. R-55-29 (206.3001) | EACH | 1 | $58,190 | $60,000 |
| 14 | Backfill structure type A (210.1500) | TON | 410 | $35.00 | $35.00 |
| 15 | Prepare foundation for asphaltic shoulders (211.0400) | STA | 69 | $137.30 | $137.30 |
| 16 | Finishing roadway (project) 01. 1020-00-80 (213.0100) | EACH | 1 | $1,000.00 | $2,000.00 |
| 17 | Base aggregate dense 3/4-inch (305.0110) | TON | 146 | $54.70 | $54.70 |
| 18 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 1,181 | $42.45 | $42.45 |
| 19 | Shaping roadway (305.0502.S) | STA | 8 | $379.00 | $379.00 |
| 20 | Concrete pavement 12-inch (415.0120) | SY | 221 | $210.34 | $210.34 |
| 21 | Concrete pavement approach slab (415.0410) | SY | 220 | $394.42 | $394.42 |
| 22 | Drilled tie bars (416.0610) | EACH | 165 | $16.16 | $16.16 |
| 23 | Drilled dowel bars (416.0620) | EACH | 99 | $21.02 | $21.02 |
| 24 | Tack coat (455.0605) | GAL | 703 | $4.25 | $4.25 |
| 25 | Asphaltic surface (465.0105) | TON | 2,353 | $122.50 | $122.50 |
| 26 | Asphaltic rumble strips, shoulder divided roadway (465.0510) | LF | 5,365 | $1.25 | $1.25 |
| 27 | Concrete masonry bridges (502.0100) | CY | 244 | $400.00 | $1.00 |
| 28 | Expansion device (502.3101) | LF | 125 | $300.00 | $275.00 |
| 29 | Expansion device modular (502.3111.S) | LF | 428 | $2,750.00 | $2,675.00 |
| 30 | Pigmented surface sealer (502.3210) | SY | 5,985 | $5.00 | $15.00 |
| 31 | Adhesive anchors 5/8-inch (502.4105) | EACH | 964 | $10.00 | $25.00 |
| 32 | Adhesive anchors no. 5 bar (502.4205) | EACH | 395 | $20.00 | $30.00 |
| 33 | Bar steel reinforcement HS coated structures (505.0600) | LB | 32,360 | $3.31 | $3.60 |
| 34 | Preparation decks type 1 (509.0301) | SY | 520 | $120.00 | $210.00 |
| 35 | Sawing pavement deck preparation areas (509.0310.S) | LF | 371 | $5.00 | $15.00 |
| 36 | Joint repair (509.1000) | SY | 341 | $2,500.00 | $3,000.00 |
| 37 | Concrete surface repair (509.1500) | SF | 560 | $125.00 | $190.00 |
| 38 | Concrete masonry deck repair (509.2100.S) | CY | 30 | $300.00 | $3,500.00 |
| 39 | Polymer overlay (509.5100.S) | SY | 33,835 | $32.00 | $34.00 |
| 40 | Removing polymer overlay (structure) 01. B-55-61 (509.9015.S) | SY | 15,835 | $5.90 | $5.80 |
| 41 | Removing polymer overlay (structure) 02. B-55-126 (509.9015.S) | SY | 18,000 | $5.90 | $5.80 |
| 42 | Cleaning parapets (509.9050.S) | LF | 11,875 | $5.00 | $3.65 |
| 43 | Temporary shoring (structure) 01. B-55-61 (511.1200) | SF | 815 | $50.00 | $90.00 |
| 44 | Temporary shoring (structure) 02. R-55-29 (511.1200) | SF | 3,860 | $5.00 | $75.00 |
| 45 | Railing steel type C2 (513.7011) | LF | 2,382 | $200.00 | $210.00 |
| 46 | Rubberized membrane waterproofing (516.0500) | SY | 18 | $25.00 | $60.00 |
| 47 | Preparation and coating of top flanges (structure) 01. B-55-61 (517.0901.S) | EACH | 1 | $8,160.00 | $8,160.00 |
| 48 | Preparation and coating of top flanges (structure) 02. B-55-126 (517.0901.S) | EACH | 1 | $5,100.00 | $5,100.00 |
| 49 | Structure overcoating cleaning and priming (structure) 01. B-55-61 (517.3001.S) | EACH | 1 | $131,600 | $131,600 |
| 50 | Structure overcoating cleaning and priming (structure) 02. B-55-126 (517.3001.S) | EACH | 1 | $57,400 | $57,400 |
| 51 | Containment and collection of waste materials (structure) 01. B- 55-61 (517.4001.S) | EACH | 1 | $47,000 | $47,000 |
| 52 | Containment and collection of waste materials (structure) 02. B- 55-126 (517.4001.S) | EACH | 1 | $20,500 | $20,500 |
| 53 | Portable decontamination facility (517.6001.S) | EACH | 2 | $2,000.00 | $2,000.00 |
| 54 | Concrete curb & gutter integral 30- inch type J (601.0454) | LF | 7 | $98.24 | $98.24 |
| 55 | Concrete curb & gutter 6-inch sloped 36-inch type A (601.0555) | LF | 176 | $100.21 | $100.21 |
| 56 | Concrete barrier temporary precast delivered (603.8000) | LF | 20,911 | $13.74 | $8.25 |
| 57 | Concrete barrier temporary precast installed (603.8125) | LF | 26,645 | $2.96 | $4.50 |
| 58 | Slope paving concrete (604.0400) | SY | 230 | $195.60 | $195.60 |
| 59 | Adjusting inlet covers (611.8115) | EACH | 3 | $717.00 | $717.00 |
| 60 | Pipe underdrain unperforated 6- inch (612.0206) | LF | 180 | $17.75 | $17.75 |
| 61 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 700 | $6.25 | $6.25 |
| 62 | Anchor assemblies for steel plate beam guard 01. B-55-61 (614.0150) | EACH | 2 | $250.00 | $450.00 |
| 63 | Anchor assemblies for steel plate beam guard 02. B-55-0126 (614.0150) | EACH | 2 | $250.00 | $450.00 |
| 64 | Crash cushions temporary (614.0905) | EACH | 2 | $4,750.00 | $2,000.00 |
| 65 | MGS guardrail 3 (614.2300) | LF | 225 | $28.20 | $28.20 |
| 66 | MGS thrie beam transition (614.2500) | LF | 39 | $108.00 | $108.00 |
| 67 | MGS guardrail terminal eat (614.2610) | EACH | 1 | $3,725.00 | $3,725.00 |
| 68 | MGS guardrail terminal type 2 (614.2620) | EACH | 2 | $3,675.00 | $3,675.00 |
| 69 | Maintenance and repair of haul roads (project) 01. 1020-00-80 (618.0100) | EACH | 1 | $0.01 | $1.00 |
| 70 | Mobilization (619.1000) | EACH | 1 | $2,444,024 | $1,180,000 |
| 71 | Topsoil (625.0100) | SY | 1,615 | $5.80 | $5.80 |
| 72 | Silt fence (628.1504) | LF | 1,975 | $2.45 | $2.45 |
| 73 | Silt fence maintenance (628.1520) | LF | 1,975 | $0.01 | $0.01 |
| 74 | Mobilizations erosion control (628.1905) | EACH | 1 | $380.00 | $380.00 |
| 75 | Mobilizations emergency erosion control (628.1910) | EACH | 3 | $380.00 | $380.00 |
| 76 | Erosion mat urban class I type B (628.2008) | SY | 400 | $2.10 | $2.10 |
| 77 | Inlet protection type B (628.7010) | EACH | 40 | $53.00 | $53.00 |
| 78 | Rock bags (628.7570) | EACH | 260 | $12.00 | $12.00 |
| 79 | Fertilizer type A (629.0205) | CWT | 1.20 | $190.00 | $190.00 |
| 80 | Seeding mixture no. 20 (630.0120) | LB | 72 | $12.30 | $12.30 |
| 81 | Seeding temporary (630.0200) | LB | 23 | $4.00 | $4.00 |
| 82 | Seed water (630.0500) | MGAL | 38 | $25.00 | $25.00 |
| 83 | Delineators temporary (633.1100) | EACH | 20 | $35.00 | $40.21 |
| 84 | Moving signs type II (638.2102) | EACH | 1 | $140.00 | $140.00 |
| 85 | Moving small sign supports (638.4000) | EACH | 1 | $68.00 | $68.00 |
| 86 | Field office type B (642.5001) | EACH | 1 | $15,000 | $25,000 |
| 87 | Traffic control drums (643.0300) | DAY | 45,175 | $0.21 | $0.21 |
| 88 | Traffic control barricades type III (643.0420) | DAY | 1,150 | $1.45 | $1.45 |
| 89 | Traffic control flexible tubular marker posts (643.0500) | EACH | 440 | $7.58 | $7.58 |
| 90 | Traffic control flexible tubular marker bases (643.0600) | EACH | 440 | $19.97 | $19.97 |
| 91 | Traffic channelizing curb system (643.0650.S) | LF | 825 | $32.62 | $32.62 |
| 92 | Traffic control warning lights type A (643.0705) | DAY | 1,695 | $0.80 | $0.80 |
| 93 | Traffic control warning lights type C (643.0715) | DAY | 5,640 | $0.25 | $0.25 |
| 94 | Traffic control arrow boards (643.0800) | DAY | 204 | $15.00 | $15.00 |
| 95 | Traffic control signs (643.0900) | DAY | 21,490 | $0.26 | $0.26 |
| 96 | Traffic control covering signs type I (643.0910) | EACH | 6 | $74.08 | $74.08 |
| 97 | Traffic control covering signs type II (643.0920) | EACH | 7 | $63.52 | $63.52 |
| 98 | Traffic control signs fixed message (643.1000) | SF | 357 | $25.47 | $25.47 |
| 99 | Traffic control signs PCMS (643.1050) | DAY | 400 | $50.00 | $50.00 |
| 100 | Basic traffic queue warning system (643.1205.S) | DAY | 400 | $97.12 | $97.12 |
| 101 | Temporary marking line removable tape 4-inch (643.3150) | LF | 1,181 | $2.36 | $2.36 |
| 102 | Temporary marking line paint 6- inch (643.3165) | LF | 70,758 | $0.50 | $0.50 |
| 103 | Temporary marking line removable tape 6-inch (643.3180) | LF | 40,151 | $2.50 | $2.50 |
| 104 | Temporary marking line paint 10- inch (643.3265) | LF | 6,108 | $1.10 | $1.10 |
| 105 | Temporary marking line removable tape 10-inch (643.3280) | LF | 3,443 | $4.40 | $4.40 |
| 106 | Traffic control (643.5000) | EACH | 1 | $53,554 | $53.55 |
| 107 | Temporary pedestrian barricade (644.1810) | LF | 20 | $14.84 | $14.84 |
| 108 | Geotextile type DF schedule A (645.0111) | SY | 1,090 | $4.00 | $4.00 |
| 109 | Marking line epoxy 6-inch (646.2020) | LF | 16,520 | $1.05 | $0.50 |
| 110 | Marking line grooved black epoxy 6-inch (646.2025) | LF | 3,870 | $1.50 | $2.15 |
| 111 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 14,210 | $2.20 | $1.32 |
| 112 | Marking replace line wet reflective epoxy 6-inch (646.2041.S) | LF | 4,966 | $1.80 | $1.65 |
| 113 | Marking line grooved permanent tape 6-inch (646.2050) | LF | 3,870 | $10.25 | $10.00 |
| 114 | Marking line epoxy 10-inch (646.4020) | LF | 3,364 | $2.00 | $1.05 |
| 115 | Marking line grooved black epoxy 10-inch (646.4025) | LF | 1,239 | $3.00 | $4.00 |
| 116 | Marking line grooved wet ref epoxy 10-inch (646.4040) | LF | 2,257 | $3.75 | $2.70 |
| 117 | Marking line grooved permanent tape 10-inch (646.4050) | LF | 1,239 | $17.50 | $15.00 |
| 118 | Marking chevron epoxy 24-inch (646.7220) | LF | 460 | $11.00 | $21.80 |
| 119 | Marking removal line water blasting 4-inch (646.9010) | LF | 18,194 | $0.48 | $0.48 |
| 120 | Marking removal line water blasting 6-inch (646.9012) | LF | 4,453 | $0.67 | $0.67 |
| 121 | Marking removal line water blasting 8-inch (646.9110) | LF | 4,696 | $0.96 | $0.96 |
| 122 | Marking removal line water blasting 10-inch (646.9112) | LF | 2,031 | $1.56 | $1.56 |
| 123 | Construction staking base (650.5000) | LF | 1,550 | $0.50 | $0.50 |
| 124 | Construction staking structure layout (structure) 01. R-55-29 (650.6501) | EACH | 1 | $2,000.00 | $2,000.00 |
| 125 | Construction staking concrete barrier (650.7500) | LF | 1,789 | $0.60 | $0.60 |
| 126 | Construction staking supplemental control (project) 01. 1020-00-80 (650.9911) | EACH | 1 | $750.00 | $750.00 |
| 127 | Construction staking slope stakes (650.9920) | LF | 850 | $1.00 | $1.00 |
| 128 | Conduit rigid nonmetallic schedule 40 1-inch (652.0210) | LF | 26 | $49.60 | $49.60 |
| 129 | Conduit rigid nonmetallic schedule 40 1 1/2-inch (652.0220) | LF | 80 | $42.40 | $42.40 |
| 130 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 80 | $48.60 | $48.60 |
| 131 | Sawing asphalt (690.0150) | LF | 10,530 | $1.95 | $1.95 |
| 132 | Sawing concrete (690.0250) | LF | 521 | $2.75 | $2.75 |
| 133 | Incentive strength concrete structures (715.0502) | DOL | 1,464 | $1.00 | $1.00 |
| 134 | Incentive compressive strength concrete pavement (715.0720) | DOL | 500 | $1.00 | $1.00 |
| 135 | Installing and maintaining bird deterrent system (station) 01. sta 636+10WB (999.2000.S) | EACH | 1 | $0.01 | $10,000 |
| 136 | Installing and maintaining bird deterrent system (station) 02. sta 636+10EB (999.2000.S) | EACH | 1 | $0.01 | $10,000 |
| 137 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,400 | $5.00 | $5.00 |
| 138 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 2,000 | $5.00 | $5.00 |
| 139 | Special 01. pedestrian shuttle service (SPV.0060) | EACH | 1 | $10,000 | $200,000 |
| 140 | Special 02. lighting repair (SPV.0060) | EACH | 8 | $16,020 | $16,020 |
| 141 | Special 03. cleaning and painting bearings B-55-61 (SPV.0060) | EACH | 12 | $1,000.00 | $1,000.00 |
| 142 | Special 04. cleaning and painting bearings B-55-126 (SPV.0060) | EACH | 14 | $1,000.00 | $1,000.00 |
| 143 | Special 05. removing and resetting railing R-55-29 (SPV.0060) | EACH | 1 | $26,625 | $26,625 |
| 144 | Special 01. glare screens temporary (SPV.0090) | LF | 12,700 | $2.86 | $2.86 |
| 145 | Special 02. remove, store, and reinstall DOT owned concrete barrier precast (SPV.0090) | LF | 1,789 | $13.66 | $10.00 |
| 146 | Special 03. fill and restore existing concrete rumble strips (SPV.0090) | LF | 7,556 | $5.95 | $8.95 |
| 147 | Special 04. marking line grooved wet reflective contrast tape 10- inch (SPV.0090) | LF | 2,031 | $21.00 | $16.50 |
| 148 | Special 05. marking replace line contrast permanent tape 4-inch (SPV.0090) | LF | 1,180 | $11.00 | $12.00 |
| 149 | Special 01. wall modular block mechanically stabilized earth R-55- 29 (SPV.0165) | SF | 3,450 | $135.60 | $135.60 |
| 150 | Special 02. wall modular block gravity R-55-29 (SPV.0165) | SF | 835 | $135.60 | $135.60 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of April 8, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.