WisDOT contract 20250408024 bid tabulation
Arkansaw - Ncl; Eau Galle River Bridge B-46-0058 (CTH D, Pepin County Arkansaw - NCL). Let by Wisconsin DOT on April 8, 2025, Pepin. 3 bids received; low bid $913,094 by Radtke Contractors Inc..
- Owner
- Wisconsin DOT
- Letting
- 08 APR 2025
- Pay items
- 65
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Radtke Contractors Inc. | $913,094 | Low |
| 2 | Lunda Construction Company | $931,537 | +2.0% |
| 3 | Janke General Contractors, Inc. | $1,050,592 | +15% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Radtke Contractors Inc. | 2. Lunda Construction Company | 3. Janke General Contractors, Inc. |
|---|---|---|---|---|---|---|
| 1 | Removing structure over waterway minimal debris (structure) 01. P-46- 0912 (203.0260) | EACH | 1 | $71,549 | $125,000 | $38,525 |
| 2 | Removing guardrail (204.0165) | LF | 153 | $4.50 | $4.50 | $4.00 |
| 3 | Excavation common (205.0100) | CY | 554 | $17.05 | $17.05 | $31.00 |
| 4 | Excavation for structures bridges (structure) 01. B-46-0058 (206.1001) | EACH | 1 | $45,704 | $50,000 | $18,275 |
| 5 | Cofferdams (structure) 01. B-46- 0058 (206.5001) | EACH | 1 | $35,988 | $50,000 | $27,600 |
| 6 | Backfill structure type A (210.1500) | TON | 340 | $45.41 | $19.95 | $38.00 |
| 7 | Finishing roadway (project) 01. 7873-03-72 (213.0100) | EACH | 1 | $685.00 | $685.00 | $365.00 |
| 8 | Base aggregate dense 3/4-inch (305.0110) | TON | 95 | $31.90 | $31.90 | $47.00 |
| 9 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 615 | $24.45 | $24.45 | $30.00 |
| 10 | Tack coat (455.0605) | GAL | 65 | $12.51 | $12.51 | $12.51 |
| 11 | Asphaltic surface (465.0105) | TON | 210 | $141.46 | $141.46 | $141.46 |
| 12 | Concrete masonry bridges (502.0100) | CY | 315 | $601.75 | $700.00 | $862.00 |
| 13 | Protective surface treatment (502.3200) | SY | 430 | $3.75 | $3.00 | $4.45 |
| 14 | Underwater substructure inspection (structure) 01. B-46-0058 (502.9000.S) | EACH | 1 | $1.00 | $5,100.00 | $4,400.00 |
| 15 | Bar steel reinforcement HS structures (505.0400) | LB | 6,730 | $1.41 | $1.17 | $1.84 |
| 16 | Bar steel reinforcement HS coated structures (505.0600) | LB | 50,910 | $1.22 | $1.20 | $1.80 |
| 17 | Railing tubular type M (513.4061) | LF | 206 | $278.48 | $300.00 | $372.00 |
| 18 | Rubberized membrane waterproofing (516.0500) | SY | 14 | $74.42 | $20.00 | $37.00 |
| 19 | Apron endwalls for culvert pipe 12- inch (520.1012) | EACH | 2 | $365.00 | $365.00 | $442.00 |
| 20 | Culvert pipe class III-A 12-inch (520.3312) | LF | 28 | $30.25 | $30.25 | $110.00 |
| 21 | Piling cip concrete 12 3/4 X 0.50- inch (550.2128) | LF | 1,760 | $63.72 | $75.00 | $127.50 |
| 22 | Riprap heavy (606.0300) | CY | 260 | $74.08 | $60.00 | $78.00 |
| 23 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 200 | $4.20 | $7.45 | $10.00 |
| 24 | MGS thrie beam transition (614.2500) | LF | 160 | $91.90 | $91.90 | $97.00 |
| 25 | MGS guardrail terminal eat (614.2610) | EACH | 4 | $3,475.00 | $3,475.00 | $4,100.00 |
| 26 | Maintenance and repair of haul roads (project) 01. 7873-03-72 (618.0100) | EACH | 1 | $250.00 | $0.01 | $366.00 |
| 27 | Mobilization (619.1000) | EACH | 1 | $151,179 | $64,684 | $69,000 |
| 28 | Water (624.0100) | MGAL | 26 | $18.25 | $18.25 | $24.00 |
| 29 | Topsoil (625.0100) | SY | 655 | $1.95 | $1.95 | $8.46 |
| 30 | Mulching (627.0200) | SY | 1,045 | $0.50 | $0.50 | $0.56 |
| 31 | Silt fence (628.1504) | LF | 1,070 | $2.25 | $2.25 | $2.20 |
| 32 | Silt fence maintenance (628.1520) | LF | 2,135 | $0.01 | $0.01 | $0.01 |
| 33 | Mobilizations erosion control (628.1905) | EACH | 4 | $75.00 | $75.00 | $400.00 |
| 34 | Mobilizations emergency erosion control (628.1910) | EACH | 4 | $75.00 | $75.00 | $200.00 |
| 35 | Erosion mat class II type C (628.2027) | SY | 40 | $5.00 | $5.00 | $4.00 |
| 36 | Turbidity barriers (628.6005) | SY | 40 | $56.00 | $56.00 | $55.00 |
| 37 | Temporary ditch checks (628.7504) | LF | 50 | $8.25 | $8.25 | $9.00 |
| 38 | Culvert pipe checks (628.7555) | EACH | 2 | $40.00 | $40.00 | $15.00 |
| 39 | Fertilizer type B (629.0210) | CWT | 0.90 | $150.00 | $150.00 | $80.00 |
| 40 | Seeding mixture no. 20 (630.0120) | LB | 61 | $8.30 | $8.30 | $8.80 |
| 41 | Seeding temporary (630.0200) | LB | 29 | $6.00 | $6.00 | $4.00 |
| 42 | Seed water (630.0500) | MGAL | 31 | $3.00 | $3.00 | $1.00 |
| 43 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 4 | $109.00 | $109.00 | $77.00 |
| 44 | Signs type II reflective F (637.2230) | SF | 12 | $28.75 | $28.75 | $24.80 |
| 45 | Removing signs type II (638.2602) | EACH | 4 | $27.00 | $27.00 | $20.00 |
| 46 | Removing small sign supports (638.3000) | EACH | 4 | $27.00 | $27.00 | $20.00 |
| 47 | Field office type B (642.5001) | EACH | 1 | $3,484.34 | $3,500.00 | $5,800.00 |
| 48 | Traffic control barricades type III (643.0420) | DAY | 2,160 | $0.40 | $0.40 | $0.40 |
| 49 | Traffic control warning lights type A (643.0705) | DAY | 2,880 | $0.10 | $0.10 | $0.10 |
| 50 | Traffic control signs (643.0900) | DAY | 1,680 | $0.40 | $0.40 | $0.40 |
| 51 | Traffic control (643.5000) | EACH | 1 | $2,412.00 | $2,412.00 | $2,412.00 |
| 52 | Geotextile type DF schedule A (645.0111) | SY | 110 | $4.93 | $4.00 | $4.10 |
| 53 | Geotextile type HR (645.0120) | SY | 480 | $5.38 | $5.00 | $4.20 |
| 54 | Marking line epoxy 4-inch (646.1020) | LF | 1,600 | $3.15 | $3.15 | $3.15 |
| 55 | Construction staking subgrade (650.4500) | LF | 300 | $0.01 | $0.01 | $0.01 |
| 56 | Construction staking base (650.5000) | LF | 300 | $0.01 | $0.01 | $0.01 |
| 57 | Construction staking structure layout (structure) 01. B-46-0058 (650.6501) | EACH | 1 | $2,460.00 | $3,000.00 | $2,460.00 |
| 58 | Construction staking supplemental control (project) 01. 7873-03-72 (650.9911) | EACH | 1 | $369.00 | $500.00 | $369.00 |
| 59 | Construction staking slope stakes (650.9920) | LF | 300 | $0.75 | $2.00 | $0.75 |
| 60 | Sawing asphalt (690.0150) | LF | 44 | $2.35 | $2.35 | $4.00 |
| 61 | Incentive strength concrete structures (715.0502) | DOL | 1,890 | $1.00 | $1.00 | $1.00 |
| 62 | Maintaining bird deterrent system (station) 01. 10+00 (999.2005.S) | EACH | 1 | $0.01 | $0.01 | $4,705.00 |
| 63 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 300 | $5.00 | $5.00 | $5.00 |
| 64 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 300 | $5.00 | $5.00 | $5.00 |
| 65 | Special 01. removing existing steel piling (SPV.0090) | LF | 720 | $22.08 | $5.00 | $34.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of April 8, 2025. Compiled by Mirage Metrics.