WisDOT contract 20250408025 bid tabulation

CTH Cc - Plum City; CTH Cc to 145th Avenue (CTH U, Pierce County CTH U - Plum City). Let by Wisconsin DOT on April 8, 2025, Pierce. 1 bid received; low bid $1,492,590 by Monarch Paving Company.

Owner
Wisconsin DOT
Letting
08 APR 2025
Pay items
39
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Monarch Paving Company$1,492,590Low
WisDOT contract 20250408025: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Monarch Paving Company
1Removing asphaltic surface butt joints (204.0115)SY1,423$1.95
2Grading and shaping intersection (location) 01. 133RD street (205.9011.S)EACH1$1,050.00
3Grading and shaping intersection (location) 02. 120TH street (205.9011.S)EACH1$1,050.00
4Grading and shaping intersection (location) 03. 90TH street (205.9011.S)EACH1$1,050.00
5Prepare foundation for asphaltic paving (project) 01. 7899-03-72 (211.0101)EACH1$37,000
6Prepare foundation for asphaltic shoulders (211.0400)STA30$125.00
7Finishing roadway (project) 01. 7899-03-72 (213.0100)EACH1$2,900.00
8Base aggregate dense 3/4-inch (305.0110)TON2,625$36.00
9Base aggregate dense 1 1/4-inch (305.0120)TON2,415$27.20
10Pulverize and relay (325.0100)SY44,380$1.42
11QMP pulverize and relay compaction (374.1020.S)SY43,800$0.20
12Tack coat (455.0605)GAL2,265$3.60
13Incentive density HMA pavement (460.2000)DOL6,880$1.00
14HMA pavement 3 LT 58-28 S (460.5223)TON6,075$86.67
15HMA pavement 4 LT 58-34 S (460.5244)TON4,675$94.99
16Salvaged guardrail end treatments (614.0925)EACH12$625.00
17Maintenance and repair of haul roads (project) 01. 7899-03-72 (618.0100)EACH1$1.00
18Mobilization (619.1000)EACH1$86,000
19Water (624.0100)MGAL230$41.00
20Field office type B (642.5001)EACH1$20,600
21Traffic control drums (643.0300)DAY7,400$0.21
22Traffic control barricades type III (643.0420)DAY1,480$0.80
23Traffic control warning lights type A (643.0705)DAY2,960$0.21
24Traffic control signs (643.0900)DAY3,614$0.32
25Traffic control signs fixed message (643.1000)SF36$30.00
26Temporary marking line paint 4- inch (643.3105)LF1,175$4.00
27Traffic control (643.5000)EACH1$5,600.00
28Marking line epoxy 4-inch (646.1020)LF57,901$0.45
29Marking stop line epoxy 18-inch (646.6120)LF56$13.00
30Locating no-passing zones (648.0100)MI2.78$875.00
31Construction staking resurfacing reference (650.8000)LF14,640$0.16
32Construction staking supplemental control (project) 01. 7899-03-72 (650.9911)EACH1$470.00
33Sawing asphalt (690.0150)LF127$2.35
34Incentive iri ride (740.0440)DOL11,040$1.00
35On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS300$5.00
36On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS300$5.00
37Special 01. reestablishing section corner monuments (SPV.0060)EACH2$9.80
38Special 02. installing salvaged guardrail end treatments (SPV.0060)EACH12$860.00
39Special 01. remove, salvage, and reinstall guardrail (SPV.0090)LF2,169$13.50
WisDOT contract 20250408025: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of April 8, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy