WisDOT contract 20250408032 bid tabulation
9835-04-70. Let by Wisconsin DOT on April 8, 2025, Langlade. 4 bids received; low bid $888,308 by James Peterson Sons, Inc..
- Owner
- Wisconsin DOT
- Letting
- 08 APR 2025
- Pay items
- 62
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | James Peterson Sons, Inc. | $888,308 | Low |
| 2 | Relyco Plus, LLC | $911,786 | +3.0% |
| 3 | Musson Bros., Inc. | $959,406 | +8.0% |
| 4 | RC Pavers LLC | $1,049,526 | +18% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. James Peterson Sons, Inc. | 2. Relyco Plus, LLC | 3. Musson Bros., Inc. | 4. RC Pavers LLC |
|---|---|---|---|---|---|---|---|
| 1 | Removing concrete pavement (204.0100) | SY | 820 | $1.00 | $4.30 | $2.99 | $7.00 |
| 2 | Removing curb & gutter (204.0150) | LF | 4,360 | $1.00 | $3.10 | $2.23 | $3.45 |
| 3 | Removing concrete sidewalk (204.0155) | SY | 380 | $10.00 | $5.00 | $3.76 | $7.25 |
| 4 | Excavation common (205.0100) | CY | 5,844 | $15.35 | $15.88 | $13.69 | $10.25 |
| 5 | Finishing roadway (project) 01. 9835-04-70 (213.0100) | EACH | 1 | $2,000.00 | $1,000.00 | $100.00 | $2,900.00 |
| 6 | Finishing roadway (project) 02. 9835-05-70 (213.0100) | EACH | 1 | $1,500.00 | $1,000.00 | $100.00 | $2,900.00 |
| 7 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 6,950 | $14.40 | $12.89 | $16.44 | $20.15 |
| 8 | Breaker run (311.0110) | TON | 801 | $19.87 | $14.90 | $20.00 | $25.00 |
| 9 | Pulverize and relay (325.0100) | SY | 1,660 | $3.50 | $1.00 | $0.60 | $2.25 |
| 10 | Concrete pavement 7-inch (415.0070) | SY | 655 | $73.12 | $73.12 | $73.12 | $69.00 |
| 11 | Drilled tie bars (416.0610) | EACH | 44 | $11.29 | $11.29 | $11.29 | $8.00 |
| 12 | Tack coat (455.0605) | GAL | 782 | $3.00 | $3.00 | $4.20 | $4.00 |
| 13 | Incentive density HMA pavement (460.2000) | DOL | 1,460 | $1.00 | $1.00 | $1.00 | $1.00 |
| 14 | HMA pavement 4 LT 58-34 S (460.5244) | TON | 1,308 | $76.15 | $85.70 | $89.90 | $108.69 |
| 15 | HMA pavement 5 LT 58-34 S (460.5245) | TON | 982 | $84.55 | $94.10 | $97.05 | $129.00 |
| 16 | Concrete curb & gutter integral 18- inch (601.0342) | LF | 1,072 | $9.77 | $9.77 | $9.77 | $21.00 |
| 17 | Concrete curb & gutter 30-inch type A (601.0409) | LF | 1,110 | $20.44 | $20.44 | $20.44 | $19.90 |
| 18 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 3,138 | $20.86 | $20.86 | $20.86 | $19.90 |
| 19 | Concrete curb pedestrian (601.0600) | LF | 85 | $54.16 | $54.16 | $54.16 | $65.00 |
| 20 | Concrete sidewalk 4-inch (602.0405) | SF | 2,050 | $5.47 | $5.77 | $5.47 | $7.80 |
| 21 | Concrete sidewalk 6-inch (602.0415) | SF | 4,250 | $7.71 | $8.01 | $7.71 | $7.90 |
| 22 | Curb ramp detectable warning field yellow (602.0505) | SF | 380 | $53.44 | $53.44 | $53.44 | $48.00 |
| 23 | Concrete driveway 6-inch (602.0810) | SY | 365 | $60.90 | $60.90 | $60.90 | $71.10 |
| 24 | Inlet covers type S (611.0651) | EACH | 1 | $1,200.00 | $1,500.00 | $1,520.08 | $1,400.00 |
| 25 | Adjusting manhole covers (611.8110) | EACH | 23 | $500.00 | $190.00 | $713.44 | $1,200.00 |
| 26 | Adjusting inlet covers (611.8115) | EACH | 22 | $500.00 | $250.00 | $414.41 | $1,200.00 |
| 27 | Mobilization (619.1000) | EACH | 1 | $84,462 | $106,700 | $145,000 | $76,800 |
| 28 | Water (624.0100) | MGAL | 120 | $40.00 | $0.01 | $1.00 | $30.00 |
| 29 | Topsoil (625.0100) | SY | 1,990 | $10.50 | $10.97 | $2.00 | $5.00 |
| 30 | Mobilizations erosion control (628.1905) | EACH | 4 | $300.00 | $300.00 | $300.00 | $300.00 |
| 31 | Mobilizations emergency erosion control (628.1910) | EACH | 4 | $300.00 | $300.00 | $300.00 | $300.00 |
| 32 | Erosion mat urban class I type A (628.2006) | SY | 1,990 | $1.95 | $1.95 | $1.95 | $1.95 |
| 33 | Inlet protection type D (628.7020) | EACH | 23 | $125.00 | $125.00 | $125.00 | $125.00 |
| 34 | Fertilizer type A (629.0205) | CWT | 2 | $100.00 | $100.00 | $100.00 | $100.00 |
| 35 | Seeding mixture no. 40 (630.0140) | LB | 90 | $5.00 | $5.00 | $5.00 | $5.00 |
| 36 | Seed water (630.0500) | MGAL | 45 | $20.00 | $20.00 | $20.00 | $20.00 |
| 37 | Field office type C (642.5201) | EACH | 1 | $4,500.00 | $9,000.00 | $7,500.00 | $15,000 |
| 38 | Traffic control barricades type II (643.0410) | DAY | 2,047 | $0.35 | $0.35 | $0.35 | $0.35 |
| 39 | Traffic control barricades type III (643.0420) | DAY | 3,649 | $0.55 | $0.55 | $0.55 | $0.55 |
| 40 | Traffic control warning lights type A (643.0705) | DAY | 3,649 | $0.10 | $0.10 | $0.10 | $0.10 |
| 41 | Traffic control signs (643.0900) | DAY | 2,403 | $0.55 | $0.55 | $0.55 | $0.55 |
| 42 | Traffic control (643.5000) | EACH | 1 | $2,175.00 | $2,175.00 | $2,300.00 | $6,584.95 |
| 43 | Geogrid type SR (645.0220) | SY | 9,599 | $1.70 | $1.40 | $1.50 | $1.75 |
| 44 | Marking stop line paint 18-inch (646.6105) | LF | 250 | $13.50 | $13.50 | $13.50 | $13.50 |
| 45 | Marking crosswalk paint transverse line 6-inch (646.7405) | LF | 1,330 | $12.50 | $12.50 | $12.50 | $12.50 |
| 46 | Construction staking subgrade (650.4500) | LF | 2,711 | $0.01 | $0.01 | $0.01 | $0.45 |
| 47 | Construction staking base (650.5000) | LF | 2,711 | $0.65 | $0.65 | $0.65 | $1.35 |
| 48 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 5,268 | $0.73 | $0.73 | $0.73 | $0.95 |
| 49 | Construction staking curb ramps (650.9000) | EACH | 38 | $105.34 | $105.34 | $105.34 | $165.00 |
| 50 | Construction staking sidewalk (project) 01. 9835-04-70 (650.9500) | EACH | 1 | $459.90 | $459.90 | $459.90 | $250.00 |
| 51 | Construction staking sidewalk (project) 02. 9835-05-70 (650.9500) | EACH | 1 | $459.90 | $459.90 | $459.90 | $250.00 |
| 52 | Construction staking supplemental control (project) 01. 9835-04-70 (650.9911) | EACH | 1 | $633.96 | $633.96 | $633.96 | $2,100.00 |
| 53 | Construction staking supplemental control (project) 02. 9835-05-70 (650.9911) | EACH | 1 | $633.96 | $633.96 | $633.96 | $2,100.00 |
| 54 | Sawing asphalt (690.0150) | LF | 520 | $1.40 | $1.40 | $3.00 | $1.95 |
| 55 | Sawing concrete (690.0250) | LF | 190 | $2.25 | $2.25 | $6.00 | $2.95 |
| 56 | Incentive compressive strength concrete pavement (715.0720) | DOL | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 57 | Incentive iri ride (740.0440) | DOL | 850 | $1.00 | $1.00 | $1.00 | $1.00 |
| 58 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 300 | $5.00 | $5.00 | $5.00 | $5.00 |
| 59 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 600 | $5.00 | $5.00 | $5.00 | $5.00 |
| 60 | Special 01. adjust valve box cover (SPV.0060) | EACH | 17 | $250.00 | $250.00 | $297.16 | $350.00 |
| 61 | Special 02. external sanitary manhole seal (SPV.0060) | EACH | 12 | $750.00 | $550.00 | $814.59 | $800.00 |
| 62 | Special 03. grading and shaping curb ramps (SPV.0060) | EACH | 38 | $400.00 | $440.00 | $194.58 | $200.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of April 8, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.