WisDOT contract 20250513004 bid tabulation

Reedsburg - Mauston (CTH K); Sauk County Line to CTH O (CTH K, Juneau County Reedsburg - Mauston (CTH K)). Let by Wisconsin DOT on May 13, 2025, Juneau. 2 bids received; low bid $3,366,019 by D L Gasser Construction.

Owner
Wisconsin DOT
Letting
13 MAY 2025
Pay items
53
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1D L Gasser Construction$3,366,019Low
2Rock Road Companies, Inc.$3,686,675+10%
WisDOT contract 20250513004: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. D L Gasser Construction2. Rock Road Companies, Inc.
1Removing concrete pavement (204.0100)SY93$33.00$18.19
2Removing asphaltic surface (204.0110)SY480$0.01$16.04
3Removing asphaltic surface butt joints (204.0115)SY1,751$5.00$6.01
4Removing asphaltic surface milling (204.0120)SY1,990$9.00$6.47
5Excavation common (205.0100)CY5,925$8.50$21.36
6Prepare foundation for concrete pavement (project) 01. 5809-00-74 (211.0201)EACH1$4,000.00$500.00
7Prepare foundation for asphaltic shoulders (211.0400)STA888$1.25$0.01
8Finishing roadway (project) 01. 5809-00-74 (213.0100)EACH1$3,000.00$4,696.58
9Base aggregate dense 3/4-inch (305.0110)TON1,101$39.50$63.77
10Pulverize and relay (325.0100)SY150,070$0.70$1.15
11QMP pulverize and relay compaction (374.1020.S)SY150,070$0.01$0.23
12Concrete pavement 9-inch (415.0090)SY93$121.20$222.29
13Tack coat (455.0605)GAL10,550$2.20$3.03
14HMA percent within limits (PWL) test strip volumetrics (460.0105.S)EACH2$2,000.00$3,500.00
15HMA percent within limits (PWL) test strip density (460.0110.S)EACH2$2,000.00$3,500.00
16Incentive density PWL HMA pavement (460.2005)DOL27,350$1.00$1.00
17Incentive density HMA pavement longitudinal joints (460.2007)DOL17,770$1.00$1.00
18Incentive air voids HMA pavement (460.2010)DOL38,660$1.00$1.00
19HMA pavement 3 MT 58-28 S (460.6223)TON21,680$68.46$70.00
20HMA pavement 4 MT 58-28 S (460.6224)TON16,978$68.62$73.24
21Material transfer vehicle (460.9000.S)EACH1$13,000$0.01
22Asphaltic surface driveways and field entrances (465.0120)TON40$135.00$127.70
23Asphaltic flumes (465.0315)SY23$95.00$59.37
24Concrete rumble strips, transverse (602.3280)SY100$131.30$53.38
25Adjusting steel plate beam guard (614.0400)LF820$15.00$16.00
26Maintenance and repair of haul roads (project) 01. 5809-00-74 (618.0100)EACH1$1.00$0.01
27Mobilization (619.1000)EACH1$51,697$50,000
28Water (624.0100)MGAL918$4.00$0.01
29Posts wood 4X6-inch X 14-FT (634.0614)EACH2$150.00$113.00
30Posts wood 4X6-inch X 16-FT (634.0616)EACH2$150.00$120.00
31Moving signs type II (638.2102)EACH4$150.00$135.00
32Field office type B (642.5001)EACH1$7,500.00$6,600.00
33Traffic control drums (643.0300)DAY325$2.50$2.50
34Traffic control barricades type III (643.0420)DAY5$10.00$10.00
35Traffic control warning lights type C (643.0715)DAY60$1.00$1.00
36Traffic control signs (643.0900)DAY3,135$1.00$1.00
37Traffic control signs PCMS (643.1050)DAY14$50.00$50.00
38Temporary marking line paint 4- inch (643.3105)LF161,725$0.26$0.26
39Temporary marking line removable tape 4-inch (643.3150)LF3,896$1.30$1.30
40Temporary marking stop line removable tape 18-inch (643.3850)LF24$7.25$7.25
41Traffic control (643.5000)EACH1$9,835.00$9,835.00
42Marking line epoxy 6-inch (646.2020)LF165,910$0.48$0.48
43Marking stop line epoxy 18-inch (646.6120)LF23$13.50$13.50
44Locating no-passing zones (648.0100)MI8.40$400.32$400.32
45Construction staking resurfacing reference (650.8000)LF44,405$0.07$0.01
46Construction staking supplemental control (project) 01. 5809-00-74 (650.9911)EACH1$2,000.00$2,500.00
47Sawing asphalt (690.0150)LF459$1.95$1.95
48Incentive iri ride (740.0440)DOL31,595$1.00$1.00
49On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS2,400$5.00$5.00
50On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS2,160$5.00$5.00
51Special 01. base repair for pulverized asphalt base layer (SPV.0035)CY500$45.00$62.85
52Special 01. temporary traffic signals (SPV.0060)EACH1$2,850.00$2,850.00
53Special 01. base aggregate dense 3/4-inch beam guard (SPV.0195)TON281$40.00$46.55
WisDOT contract 20250513004: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of May 13, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy