WisDOT contract 20250513013 bid tabulation
C Milwaukee - 16th Street; Over Menomonee River B40-550-14 (LOC STR, Milwaukee County C Milwaukee - 16th Street). Let by Wisconsin DOT on May 13, 2025, Milwaukee. 3 bids received; low bid $18,761,191 by Zenith Tech., Inc. - Waukesha.
- Owner
- Wisconsin DOT
- Letting
- 13 MAY 2025
- Pay items
- 93
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Zenith Tech., Inc. - Waukesha | $18,761,191 | Low |
| 2 | Kraemer North America, LLC | $25,605,307 | +36% |
| 3 | Lunda Construction Company | $25,688,128 | +37% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Zenith Tech., Inc. - Waukesha | 2. Kraemer North America, LLC | 3. Lunda Construction Company |
|---|---|---|---|---|---|---|
| 1 | Abatement of asbestos containing material (structure) 01. B-40-550-14 (203.0211.S) | EACH | 1 | $2,970.00 | $20,000 | $19,500 |
| 2 | Removing structure over waterway minimal debris (structure) 01. B-40- 550-14 (203.0260) | EACH | 1 | $1,100,000 | $1,693,124 | $3,200,000 |
| 3 | Debris containment (structure) 01. B-40-550-14 (203.0330) | EACH | 1 | $5,000.00 | $51,926 | $15,000 |
| 4 | Removing fence (204.0170) | LF | 70 | $20.00 | $5.50 | $20.00 |
| 5 | Excavation, hauling, and disposal of creosote contaminated soil (205.0506.S) | TON | 2 | $850.00 | $1,263.54 | $700.00 |
| 6 | Backfill structure type B (210.2500) | TON | 460 | $45.00 | $0.01 | $52.00 |
| 7 | Concrete masonry bridges (502.0100) | CY | 146 | $900.00 | $1,924.40 | $850.00 |
| 8 | Expansion device (502.3101) | LF | 346 | $320.00 | $401.41 | $305.00 |
| 9 | Protective surface treatment (502.3200) | SY | 3,223 | $4.00 | $5.63 | $6.50 |
| 10 | Adhesive anchors no. 5 bar (502.4205) | EACH | 508 | $30.00 | $47.52 | $25.00 |
| 11 | Adhesive anchors no. 6 bar (502.4206) | EACH | 132 | $37.00 | $60.24 | $28.00 |
| 12 | Protective coating clear (502.6500) | GAL | 8 | $500.00 | $0.02 | $250.00 |
| 13 | Bar steel reinforcement HS coated structures (505.0600) | LB | 231,800 | $1.66 | $1.79 | $1.59 |
| 14 | Welded stud shear connectors 7/8X5-inch (506.3010) | EACH | 7,108 | $7.18 | $15.53 | $6.50 |
| 15 | Bearing assemblies expansion (structure) 01. B-40-550-14 (506.6000) | EACH | 20 | $1,300.00 | $1,939.48 | $2,500.00 |
| 16 | Joint repair (509.1000) | SY | 41 | $1,500.00 | $1,945.80 | $1,050.00 |
| 17 | Concrete surface repair (509.1500) | SF | 119 | $225.00 | $277.95 | $168.00 |
| 18 | Epoxy injection crack repair (509.9025.S) | LF | 98 | $88.37 | $225.00 | $74.00 |
| 19 | Cored holes 2-inch diameter (509.9026.S) | EACH | 4 | $700.00 | $466.02 | $350.00 |
| 20 | Floor drains type H (514.0460) | EACH | 4 | $4,600.00 | $4,805.97 | $4,500.00 |
| 21 | Downspout 6-inch (514.2625) | LF | 323 | $230.00 | $129.62 | $310.00 |
| 22 | Painting epoxy system (structure) 01. B-40-550-14 (517.0601) | EACH | 1 | $1,592,639 | $74,357 | $1,552,000 |
| 23 | Preparation and coating of top flanges (structure) 01. B-40-550-14 (517.0901.S) | EACH | 1 | $27,000 | $15,000 | $25,000 |
| 24 | Structure repainting recycled abrasive (structure) 01. B-40-550- 14 (517.1801.S) | EACH | 1 | $820,000 | $500,000 | $801,000 |
| 25 | Negative pressure containment and collection of waste materials (structure) 01. B-40-550-14 (517.4501.S) | EACH | 1 | $328,000 | $350,000 | $402,000 |
| 26 | Portable decontamination facility (517.6001.S) | EACH | 1 | $1,000.00 | $2,500.00 | $2,000.00 |
| 27 | Anchor assemblies poles on structures (531.8990) | EACH | 5 | $1,035.54 | $1,200.00 | $1,379.08 |
| 28 | Concrete barrier temporary precast delivered (603.8000) | LF | 224 | $20.00 | $25.86 | $8.00 |
| 29 | Concrete barrier temporary precast installed (603.8125) | LF | 224 | $8.00 | $5.18 | $4.00 |
| 30 | Fence chain link 7-FT (616.0207) | LF | 50 | $108.84 | $116.00 | $125.00 |
| 31 | Fence chain link 8-FT (616.0208) | LF | 788 | $121.00 | $160.00 | $131.00 |
| 32 | Gates chain link (width) 01. 20-FT (616.0329) | EACH | 1 | $4,530.00 | $4,000.00 | $5,000.00 |
| 33 | Maintenance and repair of haul roads (project) 01. 2615-15-73 (618.0100) | EACH | 1 | $500.00 | $1,000.00 | $500.00 |
| 34 | Mobilization (619.1000) | EACH | 1 | $875,000 | $534,792 | $2,505,398 |
| 35 | Water (624.0100) | MGAL | 1 | $50.00 | $40.00 | $500.00 |
| 36 | Topsoil (625.0100) | SY | 70 | $100.00 | $6.00 | $50.00 |
| 37 | Mulching (627.0200) | SY | 70 | $2.00 | $0.90 | $20.00 |
| 38 | Inlet protection type B (628.7010) | EACH | 1 | $80.00 | $64.00 | $200.00 |
| 39 | Inlet protection type C (628.7015) | EACH | 4 | $80.00 | $67.00 | $200.00 |
| 40 | Fertilizer type A (629.0205) | CWT | 0.50 | $300.00 | $190.00 | $500.00 |
| 41 | Seeding mixture no. 40 (630.0140) | LB | 3 | $50.00 | $22.00 | $100.00 |
| 42 | Field office type C (642.5201) | EACH | 1 | $25,000 | $59,792 | $18,000 |
| 43 | Traffic control drums (643.0300) | DAY | 15,000 | $0.15 | $0.62 | $0.15 |
| 44 | Traffic control barricades type III (643.0420) | DAY | 3,600 | $0.68 | $0.90 | $0.68 |
| 45 | Traffic control signs (643.0900) | DAY | 56,400 | $0.25 | $0.65 | $0.25 |
| 46 | Traffic control (643.5000) | EACH | 1 | $14,380 | $20,000 | $14,380 |
| 47 | Temporary pedestrian barricade (644.1810) | LF | 64 | $8.00 | $8.00 | $8.00 |
| 48 | Marking line paint 4-inch (646.1005) | LF | 1,270 | $3.50 | $1.95 | $3.40 |
| 49 | Construction staking structure layout (structure) 01. B-40-550-14 (650.6501) | EACH | 1 | $15,000 | $55,000 | $34,800 |
| 50 | Conduit rigid metallic 2-inch (652.0125) | LF | 60 | $314.20 | $30.00 | $366.55 |
| 51 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 728 | $18.00 | $10.50 | $20.82 |
| 52 | Junction boxes 18X6X6-inch (653.0220) | EACH | 5 | $2,614.80 | $1,400.00 | $2,761.77 |
| 53 | Junction boxes 18X12X6-inch (653.0222) | EACH | 5 | $3,137.76 | $1,600.00 | $2,983.56 |
| 54 | Electrical wire lighting 12 AWG (655.0610) | LF | 500 | $4.59 | $0.95 | $1.41 |
| 55 | Poles type 5-aluminum (657.0322) | EACH | 5 | $3,216.91 | $1,600.00 | $2,631.78 |
| 56 | Luminaire arms single member 4 1/2-inch clamp 8-FT (657.0615) | EACH | 5 | $784.44 | $360.00 | $888.90 |
| 57 | Luminaires utility LED C (659.1125) | EACH | 5 | $784.44 | $400.00 | $850.53 |
| 58 | Lamp, ballast, LED, switch disposal by contractor (659.5000.S) | EACH | 6 | $150.00 | $35.00 | $138.71 |
| 59 | Incentive strength concrete structures (715.0502) | DOL | 6,528 | $1.00 | $1.00 | $1.00 |
| 60 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 7,000 | $5.00 | $5.00 | $5.00 |
| 61 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 13,500 | $5.00 | $5.00 | $5.00 |
| 62 | Special 502. waterline concrete surface repair (SPV.0025) | CF | 83 | $1,100.00 | $2,999.40 | $950.00 |
| 63 | Special 501. concrete masonry bridges lightweight (SPV.0035) | CY | 817 | $1,400.00 | $2,656.40 | $1,380.00 |
| 64 | Special 342. submersible multitap 3-port pre-insulated connector (SPV.0060) | EACH | 20 | $208.78 | $250.00 | $98.21 |
| 65 | Special 343. submersible multitap 4-port pre-insulated connector (SPV.0060) | EACH | 20 | $258.58 | $250.00 | $101.81 |
| 66 | Special 425. installing conduit into existing manhole (SPV.0060) | EACH | 2 | $3,000.00 | $5,000.00 | $5,320.47 |
| 67 | Special 430. underdeck utility structure B-40-550-14, city underground conduit (SPV.0060) | EACH | 1 | $42,604 | $75,000 | $254,140 |
| 68 | Special 508. temporary shoring of structure (SPV.0060) | EACH | 1 | $350,000 | $1,105,754 | $300,000 |
| 69 | Special 509. temporary support for utilities B-40-550-14 (SPV.0060) | EACH | 1 | $27,000 | $14,104 | $44,885 |
| 70 | Special 522. salvaging bascule gear set and constructing rack and pinion exhibits (SPV.0060) | EACH | 1 | $30,000 | $46,911 | $25,000 |
| 71 | Special 523. removing, repairing and reinstalling bridge operator'S house as an exhibit (SPV.0060) | EACH | 1 | $200,000 | $189,715 | $150,000 |
| 72 | Special 524. interpretive exhibit sign support (SPV.0060) | EACH | 1 | $12,000 | $7,990.24 | $3,500.00 |
| 73 | Special 525. install historical marker plaque (SPV.0060) | EACH | 2 | $1,000.00 | $1,990.63 | $500.00 |
| 74 | Special 526. connecting downspout to existing sewer (SPV.0060) | EACH | 2 | $1,500.00 | $824.44 | $2,500.00 |
| 75 | Special 527. floor drains type H modified (SPV.0060) | EACH | 4 | $4,600.00 | $6,293.12 | $4,500.00 |
| 76 | Special 544. center shear transfer device (SPV.0060) | EACH | 4 | $33,105 | $94,357 | $39,000 |
| 77 | Special 545. balancing bascule bridge leaf (SPV.0060) | EACH | 2 | $60,000 | $89,301 | $65,000 |
| 78 | Special 550. rivet replacement with high strength bolts (SPV.0060) | EACH | 1,930 | $66.00 | $253.33 | $85.00 |
| 79 | Special 566. trunnion shaft machining (SPV.0060) | EACH | 16 | $5,000.00 | $33,223 | $35,000 |
| 80 | Special 567. refurbish trunnions and trunnion bearings (SPV.0060) | EACH | 8 | $87,000 | $143,453 | $225,000 |
| 81 | Special 571. north operating machinery demolition (SPV.0060) | EACH | 1 | $50,000 | $317,732 | $245,000 |
| 82 | Special 572. south operating machinery demolition (SPV.0060) | EACH | 1 | $50,000 | $317,732 | $245,000 |
| 83 | Special 573. span lock machinery demolition (SPV.0060) | EACH | 1 | $20,000 | $29,557 | $90,000 |
| 84 | Special 574. electrical demolition (SPV.0060) | EACH | 1 | $53,000 | $200,000 | $167,173 |
| 85 | Special 587. remove timber fender systems B-40-550-14 (SPV.0060) | EACH | 2 | $25,000 | $118,183 | $180,000 |
| 86 | Special 588. remove timber dolphins B-40-550-14 (SPV.0060) | EACH | 4 | $25,000 | $64,267 | $70,000 |
| 87 | Special 597. protecting utilities (SPV.0060) | EACH | 1 | $6,000.00 | $35,807 | $34,000 |
| 88 | Special 881. inline 5A fast acting fuse with holder (SPV.0060) | EACH | 15 | $222.95 | $250.00 | $165.99 |
| 89 | Special 510. bridge structural steel (SPV.0085) | LB | 468,344 | $9.51 | $14.88 | $9.00 |
| 90 | Special 513. structural steel repair (SPV.0085) | LB | 223,613 | $19.50 | $18.65 | $20.10 |
| 91 | Special 550. non-structural steel ballast (SPV.0085) | LB | 499,923 | $0.50 | $2.52 | $1.25 |
| 92 | Special 305. electrical cable type 4#8/1#8 XLP (SPV.0090) | LF | 2,804 | $13.47 | $13.00 | $14.29 |
| 93 | Special 550. marine dock fender (SPV.0090) | LF | 253 | $500.00 | $701.97 | $650.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of May 13, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.