WisDOT contract 20250513016 bid tabulation

4824-05-70. Let by Wisconsin DOT on May 13, 2025, Washington. 2 bids received; low bid $423,155 by Zenith Tech., Inc. - Waukesha.

Owner
Wisconsin DOT
Letting
13 MAY 2025
Pay items
63
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Zenith Tech., Inc. - Waukesha$423,155Low
2Stark Pavement Corporation$614,651+45%
WisDOT contract 20250513016: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Zenith Tech., Inc. - Waukesha2. Stark Pavement Corporation
1Removing asphaltic surface (204.0110)SY90$30.00$53.00
2Removing asphaltic surface butt joints (204.0115)SY50$5.00$45.00
3Removing asphaltic surface milling (204.0120)SY16,391$2.85$4.00
4Removing curb & gutter (204.0150)LF414$10.00$20.00
5Removing concrete sidewalk (204.0155)SY195$12.00$50.00
6Prepare foundation for asphaltic paving (project) 01. 4824-05-70 (211.0101)EACH1$1,150.00$5,000.00
7Prepare foundation for asphaltic paving (project) 02. 4824-06-70 (211.0101)EACH1$575.00$5,000.00
8Finishing roadway (project) 01. 4824-05-70 (213.0100)EACH1$1,292.86$5,000.00
9Finishing roadway (project) 02. 4824-06-70 (213.0100)EACH1$1,292.86$5,000.00
10Base aggregate dense 1 1/4-inch (305.0120)TON25$100.00$210.00
11Tack coat (455.0605)GAL1,151$2.30$3.00
12Incentive density HMA pavement (460.2000)DOL1,178$1.00$1.00
13HMA pavement 4 LT 58-28 S (460.5224)TON1,841$89.65$86.80
14Asphaltic surface (465.0105)TON20$149.00$345.00
15Concrete curb & gutter 30-inch type D (601.0411)LF171$82.78$75.50
16Concrete curb pedestrian (601.0600)LF22$42.88$68.00
17Concrete sidewalk 5-inch (602.0410)SF2,081$19.96$15.50
18Curb ramp detectable warning field yellow (602.0505)SF130$40.09$71.00
19Curb ramp detectable warning field radial yellow (602.0605)SF18$58.71$80.00
20Adjusting manhole covers (611.8110)EACH2$2,100.00$2,200.00
21Adjusting inlet covers (611.8115)EACH1$2,100.00$2,150.00
22Maintenance and repair of haul roads (project) 01. 4824-05-70 (618.0100)EACH1$1.00$1,000.00
23Maintenance and repair of haul roads (project) 02. 4824-06-70 (618.0100)EACH1$1.00$1,000.00
24Mobilization (619.1000)EACH1$22,336$143,285
25Salvaged topsoil (625.0500)SY200$8.00$15.00
26Silt fence (628.1504)LF95$8.00$6.30
27Silt fence maintenance (628.1520)LF95$1.00$0.01
28Mobilizations erosion control (628.1905)EACH2$500.00$52.50
29Mobilizations emergency erosion control (628.1910)EACH2$1.00$52.50
30Erosion mat urban class I type A (628.2006)SY200$5.00$6.30
31Inlet protection type C (628.7015)EACH18$115.00$75.60
32Fertilizer type A (629.0205)CWT2$200.00$105.00
33Seeding mixture no. 20 (630.0120)LB8.80$25.00$31.50
34Seeding temporary (630.0200)LB5.30$15.00$4.20
35Seed water (630.0500)MGAL4.50$200.00$52.50
36Moving signs type II (638.2102)EACH1$50.00$157.50
37Moving small sign supports (638.4000)EACH1$100.00$84.00
38Field office type B (642.5001)EACH1$8,135.51$8,250.00
39Traffic control signs (643.0900)DAY540$2.50$1.26
40Traffic control signs PCMS (643.1050)DAY14$25.00$105.00
41Temporary marking crosswalk removable tape 6-inch (643.3350)LF200$2.60$3.15
42Traffic control (643.5000)EACH1$6,637.35$16,262
43Temporary pedestrian curb ramp (644.1601)DAY60$35.00$21.00
44Temporary pedestrian detectable warning field (644.1605)SF80$8.00$16.80
45Temporary pedestrian barricade (644.1810)LF1,600$3.00$5.25
46Marking line epoxy 4-inch (646.1020)LF10$3.40$3.57
47Marking line epoxy 6-inch (646.2020)LF5,100$1.15$1.21
48Marking crosswalk epoxy transverse line 6-inch (646.7420)LF240$10.50$11.03
49Marking curb epoxy (646.8120)LF316$6.00$6.30
50Marking parking stall epoxy (646.8320)LF643$5.00$5.25
51Construction staking curb gutter and curb & gutter (650.5500)LF390$6.00$5.25
52Construction staking resurfacing reference (650.8000)LF3,502$0.30$0.32
53Construction staking curb ramps (650.9000)EACH14$187.15$241.50
54Construction staking sidewalk (project) 01. 4824-05-70 (650.9500)EACH1$568.00$1,050.00
55Construction staking sidewalk (project) 02. 4824-06-70 (650.9500)EACH1$568.00$1,050.00
56Construction staking supplemental control (project) 01. 4824-05-70 (650.9911)EACH1$446.98$2,625.00
57Construction staking supplemental control (project) 02. 4824-06-70 (650.9911)EACH1$446.98$3,150.00
58Sawing asphalt (690.0150)LF654$1.15$2.00
59Sawing concrete (690.0250)LF172$2.15$3.00
60Incentive iri ride (740.0440)DOL2,060$1.00$1.00
61Special 01. adjusting water valve box (SPV.0060)EACH11$750.00$400.00
62Special 02. adjusting sanitary manhole covers (SPV.0060)EACH6$2,100.00$2,600.00
63Special 01. concrete curb and gutter 24-inch type D (SPV.0090)LF243$75.70$82.50
WisDOT contract 20250513016: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of May 13, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy