WisDOT contract 20250513025 bid tabulation

T Poygan, Quigley Road; Lake Poygan Tributary Bridge (LOC STR, Winnebago County T Poygan, Quigley Road). Let by Wisconsin DOT on May 13, 2025, Winnebago. 3 bids received.

Owner
Wisconsin DOT
Letting
13 MAY 2025
Pay items
57
Data through
10 NOV 2026

2 of the 3 bids matched their published totals to within a dollar and are shown; the others are left out.

Bidders

RankBidderTotal bidAgainst the low bid
2Radtke Contractors Inc.$434,232+1.0%
3Lunda Construction Company$446,850+4.0%
WisDOT contract 20250513025: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Radtke Contractors Inc.2. Lunda Construction Company
1Grubbing (201.0205)STA2$200.00$200.00
2Removing structure over waterway remove debris (structure) 01. P-70- 903 (203.0250)EACH1$50,000$135,000
3Excavation common (205.0100)CY119$26.00$26.00
4Excavation for structures bridges (structure) 01. B-70-330 (206.1001)EACH1$22,889$7,500.00
5Cofferdams (structure) 01. B-70-330 (206.5001)EACH1$50,000$26,400
6Backfill structure type A (210.1500)TON200$29.00$29.00
7Finishing roadway (project) 01. 6445-00-01 (213.0100)EACH1$650.00$650.00
8Base aggregate dense 3/4-inch (305.0110)TON10$60.00$60.00
9Base aggregate dense 1 1/4-inch (305.0120)TON140$17.13$17.13
10Tack coat (455.0605)GAL20$15.75$15.75
11Asphaltic surface (465.0105)TON60$160.00$160.00
12Concrete masonry bridges (502.0100)CY141$781.68$750.00
13Protective surface treatment (502.3200)SY110$3.59$2.00
14Pigmented surface sealer (502.3210)SY60$9.70$3.00
15Bar steel reinforcement HS structures (505.0400)LB3,460$1.25$0.99
16Bar steel reinforcement HS coated structures (505.0600)LB17,540$1.34$1.09
17Rubberized membrane waterproofing (516.0500)SY20$68.87$25.00
18Pile points (550.0500)EACH10$105.00$150.00
19Piling steel HP 10-inch X 42 LB (550.1100)LF550$35.45$44.65
20Riprap light (606.0100)CY54$90.00$90.00
21Riprap heavy (606.0300)CY108$90.00$90.00
22Pipe underdrain wrapped 6-inch (612.0406)LF140$5.00$5.00
23Mobilization (619.1000)EACH1$51,666$43,955
24Water (624.0100)MGAL4$1.00$1.00
25Topsoil (625.0100)SY110$11.00$11.00
26Silt fence (628.1504)LF110$3.50$3.50
27Silt fence maintenance (628.1520)LF220$0.01$0.01
28Mobilizations erosion control (628.1905)EACH5$300.00$300.00
29Mobilizations emergency erosion control (628.1910)EACH3$150.00$150.00
30Erosion mat urban class I type B (628.2008)SY110$3.00$3.00
31Turbidity barriers (628.6005)SY180$60.00$60.00
32Fertilizer type B (629.0210)CWT1$150.00$150.00
33Seeding mixture no. 20 (630.0120)LB3$30.00$30.00
34Seed water (630.0500)MGAL3$5.00$5.00
35Posts wood 4X6-inch X 12-FT (634.0612)EACH4$100.00$100.00
36Signs type II reflective F (637.2230)SF12$35.00$35.00
37Removing signs type II (638.2602)EACH4$40.00$40.00
38Removing small sign supports (638.3000)EACH4$40.00$40.00
39Field office type B (642.5001)EACH1$1,594.78$2,000.00
40Traffic control barricades type III (643.0420)DAY1,206$0.75$0.80
41Traffic control warning lights type A (643.0705)DAY1,608$0.25$0.25
42Traffic control signs (643.0900)DAY670$0.75$0.45
43Traffic control (643.5000)EACH1$1,500.00$3,750.00
44Geotextile type DF schedule A (645.0111)SY50$5.00$5.00
45Geotextile type HR (645.0120)SY221$6.00$6.00
46Geotextile type R (645.0130)SY120$6.00$6.00
47Construction staking subgrade (650.4500)LF100$8.35$8.35
48Construction staking base (650.5000)LF100$3.00$3.00
49Construction staking structure layout (structure) 01. B-70-330 (650.6501)EACH1$2,612.76$2,612.76
50Construction staking supplemental control (project) 01. 6445-00-01 (650.9911)EACH1$422.81$422.81
51Construction staking slope stakes (650.9920)LF100$3.00$3.00
52Sawing asphalt (690.0150)LF40$5.00$5.00
53Incentive strength concrete structures (715.0502)DOL846$1.00$1.00
54On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS600$5.00$5.00
55On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS600$5.00$5.00
56Special 01. temporary bypass pumping sta 10+00 (SPV.0060)EACH1$24,000$1,500.00
57Special 01. select crushed material for travel corridor (SPV.0195)TON50$36.00$36.00
WisDOT contract 20250513025: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of May 13, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy