WisDOT contract 20250708001 bid tabulation
Monroe - Beloit; CTH T Intersection (STH 081, Rock County Monroe - Beloit). Let by Wisconsin DOT on July 8, 2025, Rock. 5 bids received; low bid $1,719,136 by Rock Road Companies, Inc..
- Owner
- Wisconsin DOT
- Letting
- 08 JUL 2025
- Pay items
- 118
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rock Road Companies, Inc. | $1,719,136 | Low |
| 2 | Parisi Construction, LLC | $1,870,994 | +9.0% |
| 3 | Zignego Company, Inc. | $1,900,980 | +11% |
| 4 | James Peterson Sons, Inc. | $1,946,301 | +13% |
| 5 | Lalonde Contractors Incorporated | $2,015,115 | +17% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rock Road Companies, Inc. | 2. Parisi Construction, LLC | 3. Zignego Company, Inc. | 4. James Peterson Sons, Inc. | 5. Lalonde Contractors Incorporated |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 6 | $750.00 | $780.00 | $50.00 | $949.50 | $50.00 |
| 2 | Grubbing (201.0205) | STA | 6 | $125.00 | $240.00 | $50.00 | $316.50 | $50.00 |
| 3 | Removing small pipe culverts (203.0100) | EACH | 3 | $356.77 | $650.00 | $400.00 | $750.00 | $400.00 |
| 4 | Removing concrete pavement (204.0100) | SY | 2,940 | $4.87 | $7.25 | $0.01 | $2.84 | $0.01 |
| 5 | Removing asphaltic surface (204.0110) | SY | 69 | $8.51 | $16.50 | $10.00 | $20.00 | $10.00 |
| 6 | Removing curb & gutter (204.0150) | LF | 80 | $7.21 | $9.50 | $10.00 | $10.00 | $10.00 |
| 7 | Excavation common (205.0100) | CY | 11,900 | $8.94 | $13.50 | $10.25 | $11.98 | $10.25 |
| 8 | Finishing roadway (project) 01. 5340-00-74 (213.0100) | EACH | 1 | $5,185.94 | $500.00 | $750.00 | $2,500.00 | $2,880.00 |
| 9 | Base aggregate dense 3/4-inch (305.0110) | TON | 340 | $33.69 | $30.00 | $23.50 | $31.00 | $23.50 |
| 10 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 8,350 | $14.36 | $17.25 | $16.75 | $19.42 | $16.75 |
| 11 | Select crushed material (312.0110) | TON | 12,200 | $13.53 | $17.75 | $16.75 | $16.11 | $16.75 |
| 12 | Coloring concrete wisdot red (405.0100) | CY | 165 | $74.39 | $103.50 | $100.00 | $100.00 | $144.90 |
| 13 | Concrete pavement 8-inch (415.0080) | SY | 4,640 | $74.56 | $88.00 | $85.00 | $85.50 | $80.38 |
| 14 | Concrete truck apron 12-inch (415.2010) | SY | 485 | $102.01 | $101.00 | $100.00 | $115.65 | $100.96 |
| 15 | Concrete pavement joint filling (415.4100) | SY | 6,270 | $2.05 | $2.10 | $1.50 | $2.05 | $2.05 |
| 16 | Rout and seal (415.6000.S) | LF | 915 | $4.25 | $4.40 | $2.28 | $4.25 | $4.25 |
| 17 | Tack coat (455.0605) | GAL | 315 | $3.12 | $2.10 | $2.00 | $3.12 | $2.00 |
| 18 | Incentive density HMA pavement (460.2000) | DOL | 850 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 19 | HMA pavement 4 MT 58-28 H (460.6424) | TON | 1,330 | $89.37 | $100.00 | $100.00 | $89.37 | $100.00 |
| 20 | Asphaltic surface (465.0105) | TON | 12 | $149.64 | $100.00 | $100.00 | $149.64 | $100.00 |
| 21 | Asphaltic flumes (465.0315) | SY | 56 | $70.03 | $57.00 | $55.00 | $70.03 | $55.00 |
| 22 | Culvert pipe reinforced concrete class IV 24-inch (522.0424) | LF | 340 | $118.81 | $99.00 | $88.00 | $142.00 | $88.00 |
| 23 | Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012) | EACH | 5 | $938.15 | $1,700.00 | $1,400.00 | $1,217.00 | $1,400.00 |
| 24 | Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024) | EACH | 6 | $1,239.54 | $2,100.00 | $1,650.00 | $1,476.00 | $1,650.00 |
| 25 | Concrete curb & gutter 18-inch type A (601.0405) | LF | 230 | $57.89 | $33.00 | $60.00 | $26.60 | $52.44 |
| 26 | Concrete curb & gutter 30-inch type A (601.0409) | LF | 2,132 | $23.80 | $23.50 | $37.00 | $25.50 | $38.17 |
| 27 | Concrete curb & gutter 4-inch sloped 36-inch type A (601.0551) | LF | 1,099 | $34.94 | $32.50 | $38.00 | $32.15 | $43.27 |
| 28 | Concrete curb & gutter 4-inch sloped 36-inch type R (601.0580) | LF | 318 | $50.07 | $40.00 | $60.00 | $32.15 | $47.36 |
| 29 | Concrete sidewalk 4-inch (602.0405) | SF | 7,385 | $5.22 | $6.00 | $8.00 | $6.15 | $7.04 |
| 30 | Riprap medium (606.0200) | CY | 25 | $66.80 | $120.00 | $85.00 | $150.00 | $85.00 |
| 31 | Storm sewer pipe reinforced concrete class IV 12-inch (608.0412) | LF | 293 | $107.81 | $74.00 | $66.45 | $148.90 | $66.45 |
| 32 | Inlet covers type H (611.0624) | EACH | 2 | $1,183.62 | $960.00 | $950.00 | $950.00 | $950.00 |
| 33 | Inlet covers type HM (611.0627) | EACH | 2 | $1,183.62 | $960.00 | $950.00 | $950.00 | $950.00 |
| 34 | Inlet covers type HM-S (611.0636) | EACH | 3 | $1,183.62 | $970.00 | $950.00 | $950.00 | $950.00 |
| 35 | Inlet covers type H-S (611.0639) | EACH | 3 | $1,183.62 | $970.00 | $950.00 | $950.00 | $950.00 |
| 36 | Inlet covers type T (611.0652) | EACH | 2 | $1,454.52 | $1,300.00 | $1,200.00 | $1,320.00 | $1,200.00 |
| 37 | Inlets 2X2.5-FT (611.3225) | EACH | 2 | $2,264.54 | $2,500.00 | $1,840.00 | $2,020.00 | $1,840.00 |
| 38 | Inlets 2X3-FT (611.3230) | EACH | 10 | $2,491.58 | $2,500.00 | $1,800.00 | $2,250.00 | $1,800.00 |
| 39 | Pipe underdrain 6-inch (612.0106) | LF | 1,350 | $21.34 | $14.00 | $9.90 | $12.87 | $9.90 |
| 40 | Apron endwalls for underdrain reinforced concrete 6-inch (612.0806) | EACH | 2 | $419.44 | $430.00 | $850.00 | $250.00 | $850.00 |
| 41 | Maintenance and repair of haul roads (project) 01. 5340-00-74 (618.0100) | EACH | 1 | $0.01 | $550.00 | $1.00 | $100.00 | $1.00 |
| 42 | Mobilization (619.1000) | EACH | 1 | $107,000 | $26,500 | $132,000 | $124,458 | $258,499 |
| 43 | Concrete median sloped nose (620.0300) | SF | 622 | $13.79 | $11.00 | $20.00 | $15.00 | $16.86 |
| 44 | Water (624.0100) | MGAL | 300 | $0.01 | $33.25 | $0.01 | $60.00 | $0.01 |
| 45 | Salvaged topsoil (625.0500) | SY | 11,800 | $2.12 | $2.00 | $2.25 | $1.62 | $2.25 |
| 46 | Mulching (627.0200) | SY | 7,090 | $0.45 | $0.45 | $0.55 | $0.45 | $0.55 |
| 47 | Silt fence (628.1504) | LF | 1,890 | $2.25 | $2.40 | $2.05 | $2.25 | $2.05 |
| 48 | Silt fence maintenance (628.1520) | LF | 1,890 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 49 | Mobilizations erosion control (628.1905) | EACH | 5 | $100.00 | $100.00 | $150.00 | $100.00 | $150.00 |
| 50 | Mobilizations emergency erosion control (628.1910) | EACH | 3 | $100.00 | $100.00 | $150.00 | $100.00 | $150.00 |
| 51 | Erosion mat class I type B (628.2004) | SY | 4,670 | $1.10 | $1.20 | $1.10 | $1.10 | $1.10 |
| 52 | Inlet protection type A (628.7005) | EACH | 12 | $95.00 | $99.00 | $105.00 | $95.00 | $105.00 |
| 53 | Inlet protection type C (628.7015) | EACH | 12 | $60.00 | $63.00 | $65.00 | $60.00 | $65.00 |
| 54 | Temporary ditch checks (628.7504) | LF | 150 | $9.00 | $9.40 | $6.75 | $9.00 | $6.75 |
| 55 | Culvert pipe checks (628.7555) | EACH | 11 | $25.00 | $26.00 | $25.00 | $25.00 | $25.00 |
| 56 | Tracking pads (628.7560) | EACH | 2 | $750.00 | $670.00 | $100.00 | $3,000.00 | $100.00 |
| 57 | Fertilizer type B (629.0210) | CWT | 5 | $90.00 | $94.00 | $90.00 | $90.00 | $90.00 |
| 58 | Seeding mixture no. 20 (630.0120) | LB | 550 | $8.25 | $8.60 | $7.95 | $8.25 | $7.95 |
| 59 | Seeding mixture no. 40 (630.0140) | LB | 26 | $15.00 | $15.75 | $12.75 | $15.00 | $12.75 |
| 60 | Seeding temporary (630.0200) | LB | 350 | $4.00 | $4.20 | $3.45 | $4.00 | $3.45 |
| 61 | Seed water (630.0500) | MGAL | 290 | $10.00 | $10.50 | $12.00 | $10.00 | $12.00 |
| 62 | Markers row (633.5100) | EACH | 12 | $70.00 | $73.00 | $65.00 | $70.00 | $65.00 |
| 63 | Markers culvert end (633.5200) | EACH | 11 | $65.00 | $68.00 | $65.00 | $65.00 | $65.00 |
| 64 | Posts wood 4X6-inch X 12-FT (634.0612) | EACH | 8 | $75.00 | $78.00 | $90.00 | $75.00 | $90.00 |
| 65 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 17 | $80.00 | $84.00 | $95.00 | $80.00 | $95.00 |
| 66 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 4 | $90.00 | $94.00 | $100.00 | $90.00 | $100.00 |
| 67 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 13 | $95.00 | $99.00 | $120.00 | $95.00 | $120.00 |
| 68 | Posts tubular steel 2X2-inch X 14- FT (634.0814) | EACH | 10 | $200.00 | $210.00 | $210.00 | $200.00 | $210.00 |
| 69 | Signs type II reflective H (637.2210) | SF | 370 | $20.00 | $21.00 | $21.00 | $20.00 | $21.00 |
| 70 | Signs type II reflective F (637.2230) | SF | 54.12 | $22.00 | $23.00 | $25.00 | $22.00 | $25.00 |
| 71 | Moving signs type II (638.2102) | EACH | 16 | $200.00 | $210.00 | $110.00 | $200.00 | $110.00 |
| 72 | Removing signs type II (638.2602) | EACH | 12 | $35.00 | $36.50 | $35.00 | $35.00 | $35.00 |
| 73 | Removing small sign supports (638.3000) | EACH | 18 | $35.00 | $36.50 | $35.00 | $35.00 | $35.00 |
| 74 | Moving small sign supports (638.4000) | EACH | 10 | $150.00 | $160.00 | $80.00 | $150.00 | $80.00 |
| 75 | Field office type C (642.5201) | EACH | 1 | $5,000.00 | $11,100 | $20,000 | $12,000 | $13,510 |
| 76 | Traffic control drums (643.0300) | DAY | 80 | $2.50 | $2.60 | $2.50 | $2.25 | $0.23 |
| 77 | Traffic control barricades type III (643.0420) | DAY | 4,809 | $0.55 | $0.55 | $0.55 | $0.55 | $0.63 |
| 78 | Traffic control warning lights type A (643.0705) | DAY | 6,343 | $0.15 | $0.15 | $0.15 | $0.20 | $0.19 |
| 79 | Traffic control signs (643.0900) | DAY | 15,857 | $0.19 | $0.20 | $0.19 | $0.22 | $0.35 |
| 80 | Traffic control covering signs type II (643.0920) | EACH | 7 | $95.00 | $99.00 | $95.00 | $50.00 | $66.03 |
| 81 | Traffic control signs PCMS (643.1050) | DAY | 14 | $45.00 | $47.00 | $45.00 | $50.00 | $80.00 |
| 82 | Traffic control (643.5000) | EACH | 1 | $16,350 | $17,100 | $16,350 | $3,457.59 | $11,458 |
| 83 | Geotextile type HR (645.0120) | SY | 85 | $2.29 | $4.10 | $5.00 | $10.00 | $5.00 |
| 84 | Marking line epoxy 6-inch (646.2020) | LF | 5,645 | $0.58 | $0.60 | $0.58 | $1.20 | $1.20 |
| 85 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 6,191 | $1.60 | $1.70 | $1.60 | $2.15 | $2.15 |
| 86 | Marking line epoxy 10-inch (646.4020) | LF | 270 | $1.20 | $1.30 | $1.20 | $2.30 | $2.30 |
| 87 | Marking outfall epoxy (646.5520) | EACH | 2 | $50.00 | $52.00 | $50.00 | $80.00 | $80.00 |
| 88 | Marking dotted extension epoxy 18-inch (646.6320) | LF | 66 | $15.00 | $15.75 | $15.00 | $15.00 | $15.00 |
| 89 | Marking diagonal epoxy 12-inch (646.7120) | LF | 255 | $14.50 | $15.25 | $14.50 | $14.75 | $14.75 |
| 90 | Marking curb epoxy (646.8120) | LF | 306 | $7.00 | $7.30 | $7.00 | $12.00 | $12.00 |
| 91 | Marking island nose epoxy (646.8220) | EACH | 4 | $275.00 | $290.00 | $275.00 | $250.00 | $250.00 |
| 92 | Marking removal line 4-inch (646.9000) | LF | 70 | $3.00 | $3.10 | $3.00 | $1.25 | $1.25 |
| 93 | Construction staking storm sewer (650.4000) | EACH | 17 | $50.00 | $260.00 | $250.00 | $250.00 | $250.00 |
| 94 | Construction staking subgrade (650.4500) | LF | 949 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 95 | Construction staking base (650.5000) | LF | 949 | $0.01 | $1.00 | $1.00 | $1.00 | $1.00 |
| 96 | Construction staking pipe culverts (650.6000) | EACH | 3 | $100.00 | $210.00 | $200.00 | $200.00 | $200.00 |
| 97 | Construction staking electrical installations (project) 01. 5340-00- 74 (650.8501) | EACH | 1 | $3,500.00 | $2,100.00 | $2,000.00 | $2,000.00 | $2,000.00 |
| 98 | Construction staking supplemental control (project) 01. 5340-00-74 (650.9911) | EACH | 1 | $3,500.00 | $1,600.00 | $1,500.00 | $2,000.00 | $1,500.00 |
| 99 | Construction staking slope stakes (650.9920) | LF | 1,025 | $0.11 | $1.00 | $1.00 | $1.00 | $1.00 |
| 100 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 1,790 | $6.53 | $6.80 | $6.53 | $9.00 | $6.53 |
| 101 | Conduit rigid nonmetallic schedule 40 3-inch (652.0235) | LF | 102 | $8.46 | $8.80 | $8.46 | $12.00 | $8.46 |
| 102 | Conduit rigid nonmetallic schedule 80 2-inch (652.0325) | LF | 453 | $7.34 | $7.70 | $7.34 | $12.00 | $7.34 |
| 103 | Pull boxes non-conductive 24X42- inch (653.0164) | EACH | 13 | $2,280.60 | $2,400.00 | $2,280.60 | $1,950.00 | $2,280.60 |
| 104 | Concrete bases type 5 (654.0105) | EACH | 16 | $1,055.19 | $1,100.00 | $1,055.19 | $1,150.00 | $1,055.19 |
| 105 | Concrete control cabinet bases type L30 (654.0230) | EACH | 1 | $1,037.99 | $1,100.00 | $1,037.99 | $2,000.00 | $1,037.99 |
| 106 | Electrical wire lighting 12 AWG (655.0610) | LF | 14,025 | $0.90 | $0.95 | $0.90 | $1.00 | $0.90 |
| 107 | Electrical service meter breaker pedestal (location) 01. sta. 106+53 'EB', 42.6' RT (656.0201) | EACH | 1 | $1,483.28 | $1,500.00 | $1,483.28 | $2,000.00 | $1,483.28 |
| 108 | Transformer bases breakaway 11 1/2-inch bolt circle (657.0255) | EACH | 16 | $668.30 | $700.00 | $668.30 | $575.00 | $668.30 |
| 109 | Poles type 5-aluminum (657.0322) | EACH | 16 | $2,077.76 | $2,200.00 | $2,077.76 | $2,172.00 | $2,077.76 |
| 110 | Luminaire arms truss type 4 1/2- inch clamp 12-FT (657.0710) | EACH | 16 | $761.79 | $800.00 | $761.79 | $640.00 | $761.79 |
| 111 | Luminaires utility LED B (659.1120) | EACH | 16 | $339.30 | $350.00 | $339.30 | $225.00 | $339.30 |
| 112 | Lighting control cabinets 120/240 30-inch (659.2130) | EACH | 1 | $9,396.52 | $9,800.00 | $9,396.52 | $8,200.00 | $9,396.52 |
| 113 | Sawing asphalt (690.0150) | LF | 290 | $1.20 | $2.00 | $1.89 | $1.95 | $1.20 |
| 114 | Sawing concrete (690.0250) | LF | 48 | $3.25 | $3.10 | $3.25 | $2.95 | $3.25 |
| 115 | Incentive compressive strength concrete pavement (715.0720) | DOL | 1,538 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 116 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,000 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 117 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 1,320 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 118 | Special 01. construction roundabout staking (SPV.0060) | EACH | 1 | $5,000.00 | $20,900 | $20,000 | $20,000 | $20,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of July 8, 2025. Compiled by Mirage Metrics.