WisDOT contract 20250708004 bid tabulation
1130-67-72. Let by Wisconsin DOT on July 8, 2025, Outagamie. 5 bids received; low bid $88,118,615 by Zignego Company, Inc..
- Owner
- Wisconsin DOT
- Letting
- 08 JUL 2025
- Pay items
- 483
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Zignego Company, Inc. | $88,118,615 | Low |
| 2 | Michels Road & Stone, Inc. | $88,787,857 | +1.0% |
| 3 | James Peterson Sons, Inc. | $91,470,378 | +4.0% |
| 4 | Hoffman Construction Company | $96,999,442 | +10% |
| 5 | Vinton Construction Company | $98,656,223 | +12% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Zignego Company, Inc. | 2. Michels Road & Stone, Inc. | 3. James Peterson Sons, Inc. | 4. Hoffman Construction Company | 5. Vinton Construction Company |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 544 | $342.88 | $462.89 | $342.88 | $342.88 | $342.88 |
| 2 | Grubbing (201.0205) | STA | 544 | $290.13 | $391.67 | $290.13 | $290.13 | $290.13 |
| 3 | Removing small pipe culverts (203.0100) | EACH | 16 | $1,100.00 | $525.00 | $571.00 | $806.25 | $806.25 |
| 4 | Removing structure (structure) 001. B-44-0159 (203.0220) | EACH | 1 | $375,000 | $250,000 | $425,000 | $375,000 | $375,000 |
| 5 | Removing structure (structure) 002. B-44-0160 (203.0220) | EACH | 1 | $375,000 | $250,000 | $375,000 | $375,000 | $375,000 |
| 6 | Removing structure (structure) 003. B-44-0074 (203.0220) | EACH | 1 | $200,000 | $200,000 | $200,000 | $200,000 | $200,000 |
| 7 | Removing structure (structure) 004. B-44-0073 (203.0220) | EACH | 1 | $250,000 | $200,000 | $250,000 | $250,000 | $250,000 |
| 8 | Removing structure (structure) 005. B-44-0071 (203.0220) | EACH | 1 | $250,000 | $200,000 | $250,000 | $250,000 | $250,000 |
| 9 | Removing structure (structure) 006. B-44-0072 (203.0220) | EACH | 1 | $250,000 | $200,000 | $200,000 | $200,000 | $200,000 |
| 10 | Removing structure over waterway minimal debris (structure) 001. B- 05-0053 (203.0260) | EACH | 1 | $250,000 | $250,000 | $200,000 | $200,000 | $200,000 |
| 11 | Removing structure over waterway minimal debris (structure) 002. B- 05-0080 (203.0260) | EACH | 1 | $230,000 | $250,000 | $230,000 | $230,000 | $230,000 |
| 12 | Removing concrete pavement (204.0100) | SY | 140,418 | $0.70 | $0.75 | $0.70 | $10.00 | $2.20 |
| 13 | Removing curb & gutter (204.0150) | LF | 3,996 | $2.50 | $3.00 | $2.50 | $5.00 | $5.00 |
| 14 | Removing guardrail (204.0165) | LF | 6,172 | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 |
| 15 | Removing fence (204.0170) | LF | 46,330 | $1.25 | $1.25 | $1.25 | $1.25 | $1.25 |
| 16 | Removing delineators and markers (204.0180) | EACH | 281 | $32.00 | $32.00 | $32.00 | $32.00 | $32.00 |
| 17 | Removing concrete bases (204.0195) | EACH | 6 | $200.00 | $200.00 | $200.00 | $200.00 | $200.00 |
| 18 | Removing manholes (204.0210) | EACH | 10 | $600.00 | $425.00 | $600.00 | $555.00 | $555.00 |
| 19 | Removing inlets (204.0220) | EACH | 46 | $300.00 | $350.00 | $400.00 | $356.09 | $356.09 |
| 20 | Removing storm sewer (size) 001. 12-inch (204.0245) | LF | 176 | $22.20 | $18.00 | $23.85 | $16.86 | $16.86 |
| 21 | Removing storm sewer (size) 002. 15-inch (204.0245) | LF | 114 | $23.90 | $18.00 | $28.96 | $16.94 | $16.94 |
| 22 | Removing storm sewer (size) 003. 18-inch (204.0245) | LF | 1,751 | $25.60 | $20.00 | $31.92 | $16.92 | $16.92 |
| 23 | Removing storm sewer (size) 004. 21-inch (204.0245) | LF | 110 | $29.60 | $21.00 | $44.39 | $17.05 | $17.05 |
| 24 | Removing storm sewer (size) 005. 24-inch (204.0245) | LF | 2,843 | $31.70 | $21.00 | $41.48 | $19.57 | $19.57 |
| 25 | Removing storm sewer (size) 006. 30-inch (204.0245) | LF | 1,342 | $34.60 | $22.00 | $43.90 | $24.37 | $24.37 |
| 26 | Removing storm sewer (size) 007. 36-inch (204.0245) | LF | 895 | $42.50 | $26.00 | $52.34 | $25.19 | $25.19 |
| 27 | Removing storm sewer (size) 008. 29X45-inch (204.0245) | LF | 29 | $45.30 | $30.00 | $35.00 | $29.58 | $29.58 |
| 28 | Abandoning culvert pipes 001. 30- inch (204.0270) | EACH | 1 | $750.00 | $1,100.00 | $12,600 | $2,700.00 | $2,700.00 |
| 29 | Removing (item description) 001. removing billboard sign (204.9060.S) | EACH | 1 | $8,500.00 | $8,500.00 | $8,500.00 | $8,500.00 | $25,000 |
| 30 | Removing (item description) 002. removing communication vault (204.9060.S) | EACH | 17 | $250.00 | $250.00 | $250.00 | $250.00 | $250.00 |
| 31 | Removing (item description) 003. removing retaining wall R-44-10 (204.9060.S) | EACH | 1 | $66,000 | $27,000 | $66,000 | $50,000 | $30,000 |
| 32 | Removing (item description) 004. removing retaining wall R-44-11 (204.9060.S) | EACH | 1 | $66,000 | $21,000 | $66,000 | $50,000 | $30,000 |
| 33 | Removing (item description) 005. anchor bolt cover shroud (204.9060.S) | EACH | 3 | $175.00 | $175.00 | $175.00 | $175.00 | $175.00 |
| 34 | Excavation common (205.0100) | CY | 598,110 | $9.48 | $9.15 | $9.48 | $13.50 | $11.60 |
| 35 | Excavation for structures bridges (structure) 001. B-44-0341 (206.1001) | EACH | 1 | $50,000 | $59,000 | $50,000 | $100,000 | $48,000 |
| 36 | Excavation for structures bridges (structure) 002. B-44-0342 (206.1001) | EACH | 1 | $50,000 | $58,000 | $86,960 | $3,100,000 | $48,000 |
| 37 | Excavation for structures bridges (structure) 003. B-44-0343 (206.1001) | EACH | 1 | $68,000 | $97,000 | $68,000 | $150,000 | $82,000 |
| 38 | Excavation for structures bridges (structure) 004. B-44-0344 (206.1001) | EACH | 1 | $70,000 | $97,000 | $162,500 | $3,150,000 | $82,000 |
| 39 | Excavation for structures bridges (structure) 005. B-44-0345 (206.1001) | EACH | 1 | $80,000 | $83,000 | $80,000 | $250,000 | $130,000 |
| 40 | Excavation for structures bridges (structure) 006. B-44-0346 (206.1001) | EACH | 1 | $65,000 | $66,000 | $113,600 | $3,150,000 | $130,000 |
| 41 | Excavation for structures bridges (structure) 007. B-05-0694 (206.1001) | EACH | 1 | $55,000 | $24,000 | $155,000 | $3,050,000 | $18,000 |
| 42 | Excavation for structures bridges (structure) 008. B-05-0695 (206.1001) | EACH | 1 | $58,000 | $26,000 | $58,000 | $50,000 | $18,000 |
| 43 | Backfill structure type A (210.1500) | TON | 5,500 | $35.77 | $35.00 | $35.77 | $50.00 | $27.92 |
| 44 | Prepare foundation for asphaltic shoulders (211.0400) | STA | 6 | $725.00 | $725.00 | $725.00 | $350.00 | $725.00 |
| 45 | Finishing roadway (project) 001. 1130-67-72 (213.0100) | EACH | 1 | $1,000.00 | $2,000.00 | $5,000.00 | $100.00 | $5,000.00 |
| 46 | Finishing roadway (project) 002. 1130-67-76 (213.0100) | EACH | 1 | $1,000.00 | $2,000.00 | $3,500.00 | $100.00 | $5,000.00 |
| 47 | Finishing roadway (project) 003. 1130-67-86 (213.0100) | EACH | 1 | $1,000.00 | $2,000.00 | $2,000.00 | $100.00 | $5,000.00 |
| 48 | Obliterating old road (214.0100) | STA | 17 | $500.00 | $600.00 | $500.00 | $100.00 | $1,500.00 |
| 49 | Base aggregate dense 3/4-inch (305.0110) | TON | 11,837 | $24.75 | $23.60 | $27.58 | $0.13 | $30.71 |
| 50 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 213,938 | $7.00 | $11.40 | $13.92 | $0.01 | $13.10 |
| 51 | Base aggregate open-graded (310.0115) | CY | 351 | $35.00 | $75.00 | $35.00 | $62.37 | $75.00 |
| 52 | Select crushed material (312.0110) | TON | 537,723 | $10.00 | $11.40 | $17.08 | $0.01 | $18.95 |
| 53 | Concrete base 4-inch (320.0105) | SY | 6,130 | $34.62 | $60.58 | $37.10 | $37.10 | $52.39 |
| 54 | Coloring concrete wisdot red (405.0100) | CY | 750 | $100.00 | $100.00 | $70.48 | $70.48 | $85.00 |
| 55 | Coloring concrete custom (405.0200) | CY | 450 | $100.00 | $80.00 | $137.61 | $137.61 | $80.00 |
| 56 | Concrete pavement 9-inch (415.0090) | SY | 12,310 | $55.50 | $54.46 | $58.93 | $58.93 | $67.93 |
| 57 | Concrete pavement 9 1/2-inch (415.0095) | SY | 17,250 | $57.00 | $73.54 | $70.20 | $70.20 | $73.32 |
| 58 | Concrete pavement gaps (415.0210) | EACH | 11 | $1,000.00 | $750.00 | $749.94 | $749.94 | $0.01 |
| 59 | Concrete pavement approach slab (415.0410) | SY | 1,569 | $228.00 | $222.81 | $175.08 | $175.08 | $225.00 |
| 60 | Concrete truck apron 12-inch (415.2010) | SY | 2,045 | $95.00 | $90.00 | $115.59 | $115.59 | $89.28 |
| 61 | Concrete pavement joint filling (415.4100) | SY | 19,975 | $1.50 | $2.62 | $2.30 | $2.30 | $2.00 |
| 62 | HMA cold weather paving (450.4000) | TON | 1,140 | $4.90 | $4.90 | $4.90 | $4.90 | $4.90 |
| 63 | Tack coat (455.0605) | GAL | 14,231 | $3.25 | $3.25 | $3.25 | $3.25 | $3.25 |
| 64 | Incentive density HMA pavement (460.2000) | DOL | 16,260 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 65 | HMA pavement 3 LT 58-28 S (460.5223) | TON | 12,510 | $95.20 | $95.20 | $95.20 | $95.20 | $95.20 |
| 66 | HMA pavement 4 LT 58-28 S (460.5224) | TON | 7,576 | $105.80 | $105.80 | $105.80 | $105.80 | $105.80 |
| 67 | Asphaltic surface (465.0105) | TON | 2,576 | $124.90 | $124.90 | $124.90 | $124.90 | $124.90 |
| 68 | Asphaltic surface driveways and field entrances (465.0120) | TON | 108 | $175.00 | $175.00 | $175.00 | $175.00 | $175.00 |
| 69 | Asphaltic surface temporary (465.0125) | TON | 7,732 | $124.90 | $124.90 | $124.90 | $124.90 | $124.90 |
| 70 | Asphaltic flumes (465.0315) | SY | 102 | $75.00 | $75.00 | $75.00 | $75.00 | $75.00 |
| 71 | Ice hot weather concreting (501.1000.S) | LB | 55,646 | $0.01 | $0.79 | $0.01 | $0.01 | $0.01 |
| 72 | Concrete masonry bridges (502.0100) | CY | 2,714 | $500.00 | $815.00 | $500.00 | $500.00 | $500.00 |
| 73 | Protective surface treatment (502.3200) | SY | 13,169 | $2.00 | $4.00 | $2.00 | $2.00 | $2.00 |
| 74 | Pigmented surface sealer (502.3210) | SY | 1,972 | $5.00 | $12.00 | $5.00 | $5.00 | $5.00 |
| 75 | Prestressed girder type I 36W-inch (503.0137) | LF | 2,022 | $350.00 | $245.00 | $350.00 | $350.00 | $350.00 |
| 76 | Prestressed girder type I 45W-inch (503.0146) | LF | 8,345 | $400.00 | $215.00 | $400.00 | $400.00 | $400.00 |
| 77 | Prestressed girder type I 72W-inch (503.0172) | LF | 2,380 | $500.00 | $270.00 | $500.00 | $500.00 | $500.00 |
| 78 | Bar steel reinforcement HS structures (505.0400) | LB | 120,490 | $0.98 | $1.10 | $0.98 | $0.98 | $0.98 |
| 79 | Bar steel reinforcement HS coated structures (505.0600) | LB | 1,251,345 | $1.05 | $1.30 | $1.05 | $1.05 | $1.05 |
| 80 | Bar steel reinforcement HS stainless structures (505.0800.S) | LB | 18,030 | $3.40 | $3.25 | $3.40 | $3.40 | $3.40 |
| 81 | Bar couplers no. 4 (505.0904) | EACH | 872 | $20.63 | $35.00 | $20.63 | $20.63 | $20.63 |
| 82 | Bar couplers no. 5 (505.0905) | EACH | 84 | $31.61 | $42.00 | $31.61 | $31.61 | $31.61 |
| 83 | Bar couplers no. 6 (505.0906) | EACH | 35 | $35.08 | $52.00 | $35.08 | $35.08 | $35.08 |
| 84 | Bar couplers no. 8 (505.0908) | EACH | 24 | $80.03 | $125.00 | $80.03 | $80.03 | $80.03 |
| 85 | Bearing pads elastomeric non- laminated (506.2605) | EACH | 286 | $150.00 | $110.00 | $150.00 | $150.00 | $150.00 |
| 86 | Steel diaphragms (structure) 001. B-44-0341 (506.4000) | EACH | 15 | $1,500.00 | $1,000.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 87 | Steel diaphragms (structure) 002. B-44-0342 (506.4000) | EACH | 15 | $1,500.00 | $1,000.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 88 | Steel diaphragms (structure) 003. B-44-0343 (506.4000) | EACH | 24 | $750.00 | $1,000.00 | $750.00 | $750.00 | $750.00 |
| 89 | Steel diaphragms (structure) 004. B-44-0344 (506.4000) | EACH | 24 | $750.00 | $1,000.00 | $750.00 | $750.00 | $750.00 |
| 90 | Steel diaphragms (structure) 005. B-44-0345 (506.4000) | EACH | 52 | $750.00 | $1,000.00 | $750.00 | $750.00 | $750.00 |
| 91 | Steel diaphragms (structure) 006. B-44-0346 (506.4000) | EACH | 36 | $750.00 | $1,000.00 | $750.00 | $750.00 | $750.00 |
| 92 | Steel diaphragms (structure) 007. B-05-0694 (506.4000) | EACH | 14 | $2,500.00 | $1,900.00 | $2,500.00 | $2,500.00 | $2,500.00 |
| 93 | Steel diaphragms (structure) 008. B-05-695 (506.4000) | EACH | 16 | $2,500.00 | $1,900.00 | $2,500.00 | $2,500.00 | $2,500.00 |
| 94 | Temporary shoring (511.1100) | SF | 600 | $30.00 | $1.00 | $50.00 | $0.01 | $0.01 |
| 95 | Temporary shoring (structure) 001. B-44-0342 (511.1200) | SF | 1,020 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 96 | Temporary shoring (structure) 002. B-44-0344 (511.1200) | SF | 2,036 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 97 | Temporary shoring (structure) 003. B-44-0345 (511.1200) | SF | 1,850 | $0.01 | $100.00 | $0.01 | $0.01 | $0.01 |
| 98 | Temporary shoring (structure) 004. B-05-0694 (511.1200) | SF | 390 | $0.01 | $70.00 | $0.01 | $0.01 | $0.01 |
| 99 | Rubberized membrane waterproofing (516.0500) | SY | 274 | $25.00 | $55.00 | $25.00 | $25.00 | $25.00 |
| 100 | Concrete staining (structure) 001. B-44-0341 (517.1010.S) | SF | 5,876 | $1.75 | $1.98 | $1.75 | $1.75 | $1.75 |
| 101 | Concrete staining (structure) 002. B-44-0342 (517.1010.S) | SF | 5,876 | $1.75 | $1.98 | $1.75 | $1.75 | $1.75 |
| 102 | Concrete staining (structure) 003. B-44-0343 (517.1010.S) | SF | 5,859 | $1.75 | $1.98 | $1.75 | $1.75 | $1.75 |
| 103 | Concrete staining (structure) 004. B-44-0344 (517.1010.S) | SF | 5,922 | $1.75 | $1.98 | $1.75 | $1.75 | $1.75 |
| 104 | Concrete staining (structure) 005. B-44-0345 (517.1010.S) | SF | 7,023 | $1.75 | $1.98 | $1.75 | $1.75 | $1.75 |
| 105 | Concrete staining (structure) 006. B-44-0346 (517.1010.S) | SF | 6,047 | $1.75 | $1.98 | $1.75 | $1.75 | $1.75 |
| 106 | Culvert pipe reinforced concrete class III 24-inch (522.0124) | LF | 144 | $101.00 | $151.00 | $188.73 | $118.96 | $118.96 |
| 107 | Culvert pipe reinforced concrete class III 30-inch (522.0130) | LF | 168 | $139.00 | $180.00 | $148.65 | $145.03 | $145.03 |
| 108 | Culvert pipe reinforced concrete class III 36-inch (522.0136) | LF | 330 | $177.00 | $200.00 | $213.05 | $184.59 | $184.59 |
| 109 | Culvert pipe reinforced concrete class IV 18-inch (522.0418) | LF | 278 | $99.00 | $132.00 | $86.84 | $93.00 | $93.00 |
| 110 | Culvert pipe reinforced concrete class IV 24-inch (522.0424) | LF | 588 | $131.00 | $134.00 | $120.15 | $117.16 | $117.16 |
| 111 | Culvert pipe reinforced concrete class IV 30-inch (522.0430) | LF | 752 | $146.00 | $167.00 | $197.49 | $161.98 | $161.98 |
| 112 | Culvert pipe reinforced concrete class IV 36-inch (522.0436) | LF | 331 | $188.00 | $231.00 | $222.16 | $201.07 | $201.07 |
| 113 | Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012) | EACH | 1 | $1,455.00 | $1,178.00 | $1,325.43 | $1,220.00 | $1,220.00 |
| 114 | Apron endwalls for culvert pipe reinforced concrete 15-inch (522.1015) | EACH | 29 | $1,785.00 | $1,276.00 | $1,387.59 | $1,276.38 | $1,276.38 |
| 115 | Apron endwalls for culvert pipe reinforced concrete 18-inch (522.1018) | EACH | 93 | $2,025.00 | $1,406.00 | $1,524.57 | $1,452.08 | $1,452.08 |
| 116 | Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024) | EACH | 47 | $2,485.00 | $1,620.00 | $1,750.61 | $1,765.96 | $1,765.96 |
| 117 | Apron endwalls for culvert pipe reinforced concrete 30-inch (522.1030) | EACH | 21 | $3,220.00 | $1,930.00 | $2,018.13 | $2,218.33 | $2,218.33 |
| 118 | Apron endwalls for culvert pipe reinforced concrete 36-inch (522.1036) | EACH | 14 | $4,195.00 | $2,667.00 | $2,758.85 | $2,928.93 | $2,928.93 |
| 119 | Culvert pipe reinforced concrete horizontal elliptical class HE-IV 24X38-inch (522.2424) | LF | 44 | $301.00 | $207.00 | $210.91 | $207.22 | $207.22 |
| 120 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 14X23-inch (522.2614) | EACH | 6 | $1,520.00 | $1,451.00 | $1,676.33 | $1,491.67 | $1,491.67 |
| 121 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 19X30-inch (522.2619) | EACH | 4 | $2,085.00 | $1,716.00 | $1,978.09 | $1,877.50 | $1,877.50 |
| 122 | Concrete masonry ancillary structures type NS (531.1100) | CY | 46.20 | $900.00 | $900.00 | $900.00 | $900.00 | $900.00 |
| 123 | Steel reinforcement HS ancillary structures type NS (531.1140) | LB | 4,980 | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 |
| 124 | Steel reinforcement HS coated ancillary structures type NS (531.1160) | LB | 1,880 | $4.00 | $4.00 | $4.00 | $4.00 | $4.00 |
| 125 | Drilling shaft 24-inch (531.2024) | LF | 175 | $75.00 | $75.00 | $75.00 | $75.00 | $75.00 |
| 126 | Drilling shaft 30-inch (531.2030) | LF | 94 | $175.00 | $175.00 | $175.00 | $175.00 | $175.00 |
| 127 | Drilling shaft 36-inch (531.2036) | LF | 116 | $192.25 | $192.25 | $450.00 | $192.24 | $192.24 |
| 128 | Drilling shaft 42-inch (531.2042) | LF | 92 | $200.00 | $200.00 | $200.00 | $200.00 | $200.00 |
| 129 | Drilling shaft 48-inch (531.2048) | LF | 191 | $200.00 | $200.00 | $200.00 | $200.00 | $200.00 |
| 130 | Foundation camera pole 50-FT (531.4050) | EACH | 2 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 |
| 131 | Foundation single-shaft type TC-III (structure) 001. S-44-0344 (531.5330) | EACH | 1 | $13,270 | $13,270 | $13,270 | $13,270 | $13,270 |
| 132 | Foundation single-shaft type TC-IV (structure) 001. S-44-0340 (531.5340) | EACH | 1 | $16,130 | $16,130 | $16,130 | $16,130 | $16,130 |
| 133 | Foundation single-shaft type TC-IV (structure) 002. S-44-0341 (531.5340) | EACH | 1 | $16,130 | $16,130 | $16,130 | $16,130 | $16,130 |
| 134 | Foundation single-shaft type TC-IV (structure) 003. S-05-0425 (531.5340) | EACH | 1 | $16,130 | $16,130 | $16,130 | $16,130 | $16,130 |
| 135 | Foundation single-shaft type TC-IV (structure) 004. S-44-0345 (531.5340) | EACH | 1 | $16,130 | $16,130 | $16,130 | $16,130 | $16,130 |
| 136 | Foundation single-shaft type TC-IV (structure) 005. S-44-0399 (531.5340) | EACH | 1 | $16,130 | $16,130 | $16,130 | $16,130 | $16,130 |
| 137 | Foundation single-shaft type TC-IV (structure) 006. S-44-0400 (531.5340) | EACH | 1 | $16,130 | $16,130 | $16,130 | $16,130 | $16,130 |
| 138 | Foundation single-shaft type TF-I (structure) 001. S-44-0346 (531.5410) | EACH | 2 | $4,100.00 | $4,100.00 | $4,100.00 | $4,100.00 | $4,100.00 |
| 139 | Foundation two-shaft type FC-II (structure) 001. S-44-0342 (531.6020) | EACH | 1 | $17,370 | $17,370 | $17,370 | $17,370 | $17,370 |
| 140 | Foundation two-shaft type FC-II (structure) 002. S-44-0343 (531.6020) | EACH | 1 | $17,370 | $17,370 | $17,370 | $17,370 | $17,370 |
| 141 | Foundation two-shaft type FC-II (structure) 003. S-44-0398 (531.6020) | EACH | 1 | $17,370 | $17,370 | $17,370 | $17,370 | $17,370 |
| 142 | Foundation two-shaft type FF-III (structure) 004. S-44-0397 (531.6130) | EACH | 2 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 143 | Butterfly 2-chord NS (structure) 001. S-44-0396 (532.5020) | EACH | 1 | $33,505 | $33,505 | $33,505 | $33,505 | $33,505 |
| 144 | Butterfly 2-chord NS (structure) 002. S-05-0426 (532.5020) | EACH | 1 | $33,475 | $33,475 | $33,475 | $33,475 | $33,475 |
| 145 | Truss cantilever 2-chord type III (structure) 001. S-44-0344 (532.5330) | EACH | 1 | $43,900 | $43,900 | $43,900 | $43,900 | $43,900 |
| 146 | Truss cantilever 2-chord type IV (structure) 001. S-44-0340 (532.5340) | EACH | 1 | $47,165 | $47,165 | $47,165 | $47,165 | $47,165 |
| 147 | Truss cantilever 2-chord type IV (structure) 002. S-44-0341 (532.5340) | EACH | 1 | $47,265 | $47,265 | $47,265 | $47,265 | $47,265 |
| 148 | Truss cantilever 2-chord type IV (structure) 003. S-44-0345 (532.5340) | EACH | 1 | $50,025 | $50,025 | $50,025 | $50,025 | $50,025 |
| 149 | Truss cantilever 2-chord type IV (structure) 004. S-44-0399 (532.5340) | EACH | 1 | $53,420 | $53,420 | $53,420 | $53,420 | $53,420 |
| 150 | Truss cantilever 2-chord type IV (structure) 005. S-44-0400 (532.5340) | EACH | 1 | $39,765 | $39,765 | $39,765 | $39,765 | $39,765 |
| 151 | Truss cantilever 2-chord type IV (structure) 006. S-05-0425 (532.5340) | EACH | 1 | $47,245 | $47,245 | $47,245 | $47,245 | $47,245 |
| 152 | Truss full span 2-chord type I (structure) 001. S-44-0346 (532.5410) | EACH | 1 | $68,100 | $68,100 | $68,100 | $68,100 | $68,100 |
| 153 | Truss cantilever 4-chord type II (structure) 001. S-44-0342 (532.6020) | EACH | 1 | $58,450 | $58,450 | $58,450 | $58,450 | $58,450 |
| 154 | Truss cantilever 4-chord type II (structure) 002. S-44-0343 (532.6020) | EACH | 1 | $53,480 | $53,840 | $53,840 | $53,840 | $53,840 |
| 155 | Truss cantilever 4-chord type II (structure) 003. S-44-0398 (532.6020) | EACH | 1 | $58,385 | $58,385 | $58,385 | $58,385 | $58,385 |
| 156 | Truss full span 4-chord type III (structure) 004. S-44-0397 (532.6130) | EACH | 1 | $108,510 | $108,510 | $108,510 | $108,510 | $108,510 |
| 157 | Noise barriers double-sided sound absorptive (structure) 001. N-44- 0021 (541.0300.S) | SF | 21,076 | $65.00 | $77.00 | $66.00 | $65.00 | $65.00 |
| 158 | Pile points (550.0500) | EACH | 140 | $150.00 | $117.00 | $150.00 | $150.00 | $150.00 |
| 159 | Piling steel HP 10-inch X 42 LB (550.1100) | LF | 4,070 | $36.38 | $57.00 | $36.38 | $36.38 | $36.38 |
| 160 | Piling steel HP 12-inch X 53 LB (550.1120) | LF | 33,820 | $43.72 | $67.00 | $43.72 | $43.72 | $43.72 |
| 161 | Concrete curb & gutter 18-inch type A (601.0405) | LF | 720 | $20.00 | $22.50 | $34.16 | $34.16 | $22.50 |
| 162 | Concrete curb & gutter 18-inch type D (601.0407) | LF | 230 | $20.00 | $22.50 | $41.90 | $41.90 | $22.50 |
| 163 | Concrete curb & gutter 30-inch type A (601.0409) | LF | 5,520 | $28.00 | $19.95 | $22.39 | $22.39 | $19.95 |
| 164 | Concrete curb & gutter 4-inch sloped 36-inch type A (601.0551) | LF | 850 | $30.00 | $24.55 | $48.55 | $48.55 | $24.55 |
| 165 | Concrete curb & gutter 6-inch sloped 36-inch type A (601.0555) | LF | 990 | $30.00 | $24.55 | $30.07 | $30.07 | $24.55 |
| 166 | Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557) | LF | 2,710 | $30.00 | $23.20 | $26.94 | $26.94 | $23.20 |
| 167 | Concrete curb & gutter 4-inch sloped 30-inch type J (601.0576) | LF | 3,361 | $28.00 | $20.55 | $33.03 | $33.03 | $20.55 |
| 168 | Concrete curb & gutter 3-inch sloped 30-inch type R (601.0578) | LF | 1,025 | $28.00 | $23.50 | $44.25 | $44.25 | $23.50 |
| 169 | Concrete curb & gutter 4-inch sloped 30-inch type TBT (601.0584) | LF | 42 | $100.00 | $45.00 | $120.29 | $120.29 | $45.00 |
| 170 | Concrete curb pedestrian (601.0600) | LF | 220 | $100.00 | $45.00 | $109.28 | $109.28 | $45.00 |
| 171 | Concrete sidewalk 4-inch (602.0405) | SF | 81,592 | $6.72 | $6.35 | $5.32 | $5.32 | $6.65 |
| 172 | Curb ramp detectable warning field yellow (602.0505) | SF | 568 | $50.00 | $55.00 | $57.37 | $57.37 | $55.00 |
| 173 | Curb ramp detectable warning field radial yellow (602.0605) | SF | 167 | $100.00 | $32.00 | $87.93 | $87.93 | $32.00 |
| 174 | Concrete surface drains (602.3010) | CY | 42 | $500.00 | $850.00 | $747.15 | $747.15 | $850.00 |
| 175 | Concrete rumble strips, shoulder divided roadway (602.3210) | LF | 68,554 | $0.75 | $0.75 | $0.75 | $0.84 | $0.75 |
| 176 | Concrete barrier transition type S42 to S56 (603.3559) | EACH | 2 | $15,000 | $14,487 | $10,545 | $10,555 | $7,500.00 |
| 177 | Concrete barrier temporary precast delivered (603.8000) | LF | 127,710 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 178 | Concrete barrier temporary precast installed (603.8125) | LF | 127,710 | $8.00 | $14.00 | $8.00 | $8.00 | $8.00 |
| 179 | Anchoring concrete barrier temporary precast (603.8500) | LF | 1,405 | $10.00 | $6.50 | $10.00 | $10.00 | $10.00 |
| 180 | Anchoring concrete barrier temporary precast on bridge decks (603.8505) | LF | 135 | $20.00 | $14.00 | $20.00 | $20.00 | $20.00 |
| 181 | Slope paving concrete (604.0400) | SY | 5,078 | $50.00 | $50.00 | $50.00 | $50.00 | $50.00 |
| 182 | Riprap medium (606.0200) | CY | 3,987 | $98.00 | $100.00 | $98.00 | $120.00 | $86.56 |
| 183 | Riprap heavy (606.0300) | CY | 1,372 | $120.00 | $90.00 | $120.00 | $110.00 | $93.65 |
| 184 | Storm sewer pipe reinforced concrete class III 12-inch (608.0312) | LF | 92 | $65.10 | $74.00 | $138.59 | $81.70 | $81.70 |
| 185 | Storm sewer pipe reinforced concrete class III 15-inch (608.0315) | LF | 714 | $73.20 | $83.75 | $101.69 | $84.45 | $84.45 |
| 186 | Storm sewer pipe reinforced concrete class III 18-inch (608.0318) | LF | 2,105 | $82.10 | $84.50 | $104.07 | $88.79 | $88.79 |
| 187 | Storm sewer pipe reinforced concrete class III 24-inch (608.0324) | LF | 2,872 | $99.00 | $109.00 | $121.31 | $106.32 | $106.32 |
| 188 | Storm sewer pipe reinforced concrete class III 30-inch (608.0330) | LF | 991 | $136.00 | $149.00 | $147.09 | $148.13 | $148.13 |
| 189 | Storm sewer pipe reinforced concrete class III 36-inch (608.0336) | LF | 1,202 | $178.40 | $181.00 | $195.58 | $181.39 | $181.39 |
| 190 | Storm sewer pipe reinforced concrete class IV 12-inch (608.0412) | LF | 272 | $65.10 | $70.00 | $109.54 | $76.51 | $76.51 |
| 191 | Storm sewer pipe reinforced concrete class IV 15-inch (608.0415) | LF | 2,405 | $73.20 | $75.50 | $102.21 | $79.89 | $79.89 |
| 192 | Storm sewer pipe reinforced concrete class IV 18-inch (608.0418) | LF | 7,737 | $85.50 | $79.00 | $104.18 | $86.83 | $86.83 |
| 193 | Storm sewer pipe reinforced concrete class IV 24-inch (608.0424) | LF | 2,818 | $113.80 | $110.00 | $113.88 | $110.02 | $110.02 |
| 194 | Storm sewer pipe reinforced concrete class IV 30-inch (608.0430) | LF | 1,117 | $137.90 | $149.00 | $164.63 | $157.61 | $157.61 |
| 195 | Storm sewer pipe reinforced concrete class IV 36-inch (608.0436) | LF | 1,240 | $175.90 | $192.00 | $219.22 | $203.71 | $203.71 |
| 196 | Storm sewer pipe reinforced concrete class V 15-inch (608.0515) | LF | 25 | $75.90 | $75.50 | $148.03 | $97.40 | $97.40 |
| 197 | Storm sewer pipe reinforced concrete class V 18-inch (608.0518) | LF | 317 | $88.50 | $81.00 | $100.93 | $95.97 | $95.97 |
| 198 | Storm sewer pipe reinforced concrete class V 24-inch (608.0524) | LF | 115 | $114.50 | $118.00 | $124.88 | $130.93 | $130.93 |
| 199 | Storm sewer pipe reinforced concrete horizontal elliptical class HE-IV 14X23-inch (608.2414) | LF | 166 | $117.70 | $137.00 | $202.61 | $139.48 | $139.48 |
| 200 | Storm sewer pipe reinforced concrete horizontal elliptical class HE-IV 19X30-inch (608.2419) | LF | 292 | $142.60 | $157.00 | $156.97 | $159.80 | $159.80 |
| 201 | Storm sewer pipe reinforced concrete horizontal elliptical class HE-IV 29X45-inch (608.2429) | LF | 189 | $243.80 | $239.00 | $289.88 | $256.69 | $256.69 |
| 202 | Reconstructing manholes (611.0420) | EACH | 85 | $2,160.00 | $1,000.00 | $3,353.66 | $1,425.88 | $1,425.88 |
| 203 | Reconstructing inlets (611.0430) | EACH | 27 | $1,225.00 | $772.00 | $2,479.05 | $1,400.00 | $1,400.00 |
| 204 | Manhole covers type J (611.0530) | EACH | 10 | $510.00 | $481.00 | $1,210.99 | $493.00 | $493.00 |
| 205 | Manhole covers type L (611.0545) | EACH | 2 | $390.00 | $354.00 | $1,054.19 | $381.00 | $381.00 |
| 206 | Inlet covers type B-A (611.0609) | EACH | 3 | $945.00 | $933.00 | $1,766.79 | $890.00 | $890.00 |
| 207 | Inlet covers type BW (611.0610) | EACH | 8 | $755.00 | $739.00 | $1,642.32 | $720.00 | $720.00 |
| 208 | Inlet covers type C (611.0612) | EACH | 4 | $800.00 | $506.00 | $1,241.79 | $515.00 | $515.00 |
| 209 | Inlet covers type H (611.0624) | EACH | 40 | $740.00 | $723.00 | $1,621.32 | $705.00 | $705.00 |
| 210 | Inlet covers type HM (611.0627) | EACH | 15 | $740.00 | $722.00 | $1,621.32 | $705.00 | $705.00 |
| 211 | Inlet covers type HM-GJ (611.0630) | EACH | 3 | $835.00 | $722.00 | $1,621.32 | $705.00 | $705.00 |
| 212 | Inlet covers type HM-S (611.0636) | EACH | 9 | $740.00 | $722.00 | $1,621.32 | $705.00 | $705.00 |
| 213 | Inlet covers type H-S (611.0639) | EACH | 40 | $740.00 | $722.00 | $1,621.32 | $705.00 | $705.00 |
| 214 | Inlet covers type MS (611.0642) | EACH | 50 | $525.00 | $494.00 | $565.60 | $504.00 | $504.00 |
| 215 | Inlet covers type T (611.0652) | EACH | 12 | $995.00 | $992.00 | $1,953.12 | $942.00 | $942.00 |
| 216 | Inlet covers type VV-B (611.0656) | EACH | 392 | $1,725.00 | $1,730.00 | $2,860.32 | $1,588.24 | $1,588.24 |
| 217 | Manholes 4-FT diameter (611.2004) | EACH | 3 | $3,585.00 | $3,072.00 | $2,363.59 | $3,705.83 | $3,705.83 |
| 218 | Manholes 5-FT diameter (611.2005) | EACH | 367 | $5,515.00 | $5,108.00 | $4,622.37 | $5,415.02 | $5,415.02 |
| 219 | Manholes 6-FT diameter (611.2006) | EACH | 26 | $8,895.00 | $7,315.00 | $4,171.19 | $7,489.04 | $7,489.04 |
| 220 | Manholes 7-FT diameter (611.2007) | EACH | 7 | $14,360 | $10,350 | $10,499 | $11,541 | $11,541 |
| 221 | Inlets 3-FT diameter (611.3003) | EACH | 10 | $2,965.00 | $2,600.00 | $1,749.15 | $2,654.20 | $2,654.20 |
| 222 | Inlets 4-FT diameter (611.3004) | EACH | 56 | $5,080.00 | $3,200.00 | $2,665.35 | $3,924.75 | $3,924.75 |
| 223 | Inlets 2X2.5-FT (611.3225) | EACH | 2 | $2,720.00 | $2,330.00 | $1,524.34 | $2,611.50 | $2,611.50 |
| 224 | Inlets 2X3-FT (611.3230) | EACH | 63 | $2,825.00 | $2,638.00 | $1,966.18 | $2,818.48 | $2,818.48 |
| 225 | Inlets median 1 grate (611.3901) | EACH | 14 | $3,965.00 | $3,100.00 | $2,604.28 | $3,411.57 | $3,411.57 |
| 226 | Inlets median 2 grate (611.3902) | EACH | 18 | $5,925.00 | $3,702.00 | $2,766.16 | $4,018.06 | $4,018.06 |
| 227 | Adjusting manhole covers (611.8110) | EACH | 3 | $500.00 | $454.00 | $1,910.79 | $560.00 | $560.00 |
| 228 | Cover plates temporary (611.8120.S) | EACH | 151 | $195.00 | $203.00 | $150.00 | $380.79 | $380.79 |
| 229 | Pipe grates (size) 001. 24-inch (611.9850.S) | EACH | 4 | $905.00 | $813.00 | $2,405.20 | $2,268.75 | $2,268.75 |
| 230 | Pipe underdrain 6-inch (612.0106) | LF | 5,170 | $15.00 | $12.00 | $11.00 | $24.89 | $12.00 |
| 231 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 4,160 | $15.00 | $7.00 | $4.00 | $5.00 | $7.00 |
| 232 | Anchor assemblies for steel plate beam guard (614.0150) | EACH | 8 | $175.00 | $300.00 | $175.00 | $175.00 | $175.00 |
| 233 | Crash cushions permanent (614.0800) | EACH | 3 | $45,308 | $29,890 | $29,890 | $45,308 | $31,750 |
| 234 | Crash cushions temporary (614.0905) | EACH | 23 | $3,606.17 | $4,850.00 | $10,150 | $8,406.17 | $8,000.00 |
| 235 | MGS guardrail 3 (614.2300) | LF | 1,075.50 | $30.00 | $30.00 | $30.00 | $30.00 | $30.00 |
| 236 | MGS thrie beam transition (614.2500) | LF | 394.40 | $94.00 | $94.00 | $94.00 | $94.00 | $94.00 |
| 237 | MGS guardrail terminal eat (614.2610) | EACH | 13 | $4,800.00 | $4,800.00 | $4,800.00 | $4,800.00 | $4,800.00 |
| 238 | MGS guardrail terminal type 2 (614.2620) | EACH | 3 | $4,000.00 | $4,000.00 | $4,000.00 | $4,000.00 | $4,000.00 |
| 239 | Fence chain link 6-FT (616.0206) | LF | 9,214 | $23.00 | $23.00 | $23.00 | $23.00 | $23.00 |
| 240 | Fence safety (616.0700.S) | LF | 500 | $9.00 | $9.00 | $9.00 | $9.00 | $9.00 |
| 241 | Maintenance and repair of haul roads (project) 001. 1130-67-72 (618.0100) | EACH | 1 | $1.00 | $2,000.00 | $1,000.00 | $100.00 | $0.01 |
| 242 | Maintenance and repair of haul roads (project) 002. 1130-67-76 (618.0100) | EACH | 1 | $1.00 | $2,000.00 | $1,000.00 | $100.00 | $0.01 |
| 243 | Maintenance and repair of haul roads (project) 003. 1130-67-86 (618.0100) | EACH | 1 | $1.00 | $2,000.00 | $1,000.00 | $100.00 | $0.01 |
| 244 | Mobilization (619.1000) | EACH | 1 | $7,930,000 | $5,825,514 | $5,490,408 | $7,006,703 | $9,200,000 |
| 245 | Concrete median blunt nose (620.0200) | SF | 200 | $20.00 | $14.00 | $12.14 | $12.14 | $14.00 |
| 246 | Concrete median sloped nose (620.0300) | SF | 1,098 | $15.00 | $14.00 | $13.20 | $13.20 | $14.00 |
| 247 | Dust control surface treatment (623.0200) | SY | 417,440 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 248 | Water (624.0100) | MGAL | 3,561 | $36.00 | $50.00 | $15.00 | $0.01 | $0.01 |
| 249 | Topsoil (625.0100) | SY | 620 | $10.00 | $33.00 | $33.00 | $20.00 | $10.00 |
| 250 | Salvaged topsoil (625.0500) | SY | 423,410 | $1.07 | $1.60 | $1.07 | $0.03 | $0.01 |
| 251 | Mulching (627.0200) | SY | 16,345 | $0.50 | $0.50 | $0.50 | $0.50 | $0.50 |
| 252 | Silt fence (628.1504) | LF | 12,118 | $2.10 | $2.10 | $2.10 | $2.10 | $2.10 |
| 253 | Silt fence maintenance (628.1520) | LF | 38,037 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 254 | Mobilizations erosion control (628.1905) | EACH | 30 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 255 | Mobilizations emergency erosion control (628.1910) | EACH | 14 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 256 | Erosion mat class I type A (628.2002) | SY | 134,400 | $1.10 | $1.10 | $1.10 | $1.10 | $1.10 |
| 257 | Erosion mat class I type B (628.2004) | SY | 293,429 | $1.10 | $1.10 | $1.10 | $1.10 | $1.10 |
| 258 | Erosion mat class II type A (628.2021) | SY | 3,000 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 |
| 259 | Erosion mat class III type D (628.2039) | SY | 340 | $20.00 | $20.00 | $20.00 | $20.00 | $20.00 |
| 260 | Turbidity barriers (628.6005) | SY | 1,215 | $20.00 | $20.00 | $20.00 | $20.00 | $20.00 |
| 261 | Inlet protection type A (628.7005) | EACH | 130 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 262 | Inlet protection type B (628.7010) | EACH | 510 | $75.00 | $75.00 | $75.00 | $75.00 | $75.00 |
| 263 | Inlet protection type C (628.7015) | EACH | 78 | $75.00 | $75.00 | $75.00 | $75.00 | $75.00 |
| 264 | Inlet protection type D (628.7020) | EACH | 35 | $150.00 | $150.00 | $150.00 | $150.00 | $150.00 |
| 265 | Temporary ditch checks (628.7504) | LF | 5,971 | $4.00 | $4.00 | $4.00 | $4.00 | $4.00 |
| 266 | Stone ditch checks (628.7515.S) | CY | 484 | $35.00 | $35.00 | $35.00 | $35.00 | $35.00 |
| 267 | Culvert pipe checks (628.7555) | EACH | 207 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 |
| 268 | Tracking pads (628.7560) | EACH | 26 | $1,982.00 | $3,000.00 | $1,982.00 | $100.00 | $0.01 |
| 269 | Rock bags (628.7570) | EACH | 396 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 |
| 270 | Fertilizer type B (629.0210) | CWT | 301.40 | $115.00 | $115.00 | $115.00 | $115.00 | $115.00 |
| 271 | Seeding mixture no. 20 (630.0120) | LB | 441 | $7.90 | $7.90 | $7.90 | $7.90 | $7.90 |
| 272 | Seeding mixture no. 30 (630.0130) | LB | 17,548 | $7.90 | $7.90 | $7.90 | $7.90 | $7.90 |
| 273 | Seeding temporary (630.0200) | LB | 4,711 | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 |
| 274 | Seed water (630.0500) | MGAL | 11,467 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 275 | Sod water (631.0300) | MGAL | 70 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 276 | Sod lawn (631.1000) | SY | 2,990 | $12.00 | $12.00 | $12.00 | $12.00 | $12.00 |
| 277 | Trees (species, root, size) 001. cole'S select serviceberry, B&B, 5- FT (632.0101) | EACH | 9 | $200.00 | $200.00 | $200.00 | $200.00 | $200.00 |
| 278 | Shrubs (species, root, size) 001. hydrangea, "limelight", cont, 3-FT (632.0201) | EACH | 27 | $25.00 | $25.00 | $25.00 | $25.00 | $25.00 |
| 279 | Shrubs (species, root, size) 002. black weigela, "verweig", cont, 3- FT (632.0201) | EACH | 63 | $25.00 | $25.00 | $25.00 | $25.00 | $25.00 |
| 280 | Landscape planting surveillance and care cycles (632.9101) | EACH | 18 | $500.00 | $500.00 | $500.00 | $500.00 | $500.00 |
| 281 | Delineator posts steel (633.0100) | EACH | 29 | $75.00 | $75.00 | $75.00 | $75.00 | $75.00 |
| 282 | Delineators flexible (633.0200) | EACH | 581 | $68.00 | $68.00 | $68.00 | $68.00 | $68.00 |
| 283 | Delineator reflectors (633.0500) | EACH | 29 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 |
| 284 | Delineators barrier wall (633.1000) | EACH | 13 | $95.00 | $95.00 | $95.00 | $95.00 | $95.00 |
| 285 | Delineators temporary (633.1100) | EACH | 394 | $50.00 | $21.25 | $21.25 | $50.00 | $21.25 |
| 286 | Markers culvert end (633.5200) | EACH | 162 | $75.00 | $75.00 | $75.00 | $75.00 | $75.00 |
| 287 | Markers permanent flexible (633.5350) | EACH | 14 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 288 | Posts wood 4X6-inch X 12-FT (634.0612) | EACH | 22 | $125.00 | $125.00 | $125.00 | $125.00 | $125.00 |
| 289 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 58 | $125.00 | $125.00 | $125.00 | $125.00 | $125.00 |
| 290 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 98 | $135.00 | $135.00 | $135.00 | $135.00 | $135.00 |
| 291 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 46 | $155.00 | $155.00 | $155.00 | $155.00 | $155.00 |
| 292 | Posts wood 4X6-inch X 20-FT (634.0620) | EACH | 4 | $175.00 | $175.00 | $175.00 | $175.00 | $175.00 |
| 293 | Posts wood 4X6-inch X 22-FT (634.0622) | EACH | 2 | $200.00 | $200.00 | $200.00 | $200.00 | $200.00 |
| 294 | Posts wood 4X6-inch X 24-FT (634.0624) | EACH | 3 | $300.00 | $300.00 | $300.00 | $300.00 | $300.00 |
| 295 | Sign supports structural steel HS (635.0200) | LB | 11,000 | $6.00 | $6.00 | $6.00 | $6.00 | $6.00 |
| 296 | Signs type I reflective SH (637.1220) | SF | 2,731.50 | $27.00 | $27.00 | $27.00 | $27.00 | $27.00 |
| 297 | Signs type II reflective H (637.2210) | SF | 1,755.90 | $24.00 | $24.00 | $24.00 | $24.00 | $24.00 |
| 298 | Signs type II reflective H folding (637.2215) | SF | 20 | $40.00 | $40.00 | $40.00 | $40.00 | $40.00 |
| 299 | Signs type II reflective F (637.2230) | SF | 330.39 | $26.00 | $26.00 | $26.00 | $26.00 | $26.00 |
| 300 | Moving signs type II (638.2102) | EACH | 2 | $300.00 | $300.00 | $300.00 | $300.00 | $300.00 |
| 301 | Removing signs type I (638.2601) | EACH | 10 | $500.00 | $500.00 | $500.00 | $500.00 | $500.00 |
| 302 | Removing signs type II (638.2602) | EACH | 202 | $50.00 | $50.00 | $50.00 | $50.00 | $50.00 |
| 303 | Removing small sign supports (638.3000) | EACH | 230 | $50.00 | $50.00 | $50.00 | $50.00 | $50.00 |
| 304 | Removing structural steel sign supports (638.3100) | EACH | 20 | $500.00 | $500.00 | $500.00 | $500.00 | $500.00 |
| 305 | Pond liner clay (640.1303.S) | CY | 9,220 | $17.66 | $21.00 | $17.66 | $13.50 | $10.98 |
| 306 | Traffic control drums (643.0300) | DAY | 404,621 | $0.27 | $0.13 | $0.13 | $0.27 | $0.13 |
| 307 | Traffic control barricades type III (643.0420) | DAY | 28,631 | $0.63 | $0.45 | $0.45 | $0.63 | $0.45 |
| 308 | Traffic control warning lights type A (643.0705) | DAY | 57,262 | $0.19 | $0.10 | $0.10 | $0.19 | $0.10 |
| 309 | Traffic control warning lights type C (643.0715) | DAY | 267,644 | $0.05 | $0.06 | $0.06 | $0.05 | $0.06 |
| 310 | Traffic control arrow boards (643.0800) | DAY | 405 | $16.06 | $7.50 | $7.50 | $16.06 | $7.50 |
| 311 | Connected arrow board (643.0810.S) | DAY | 195 | $25.39 | $18.50 | $18.50 | $25.39 | $18.50 |
| 312 | Traffic control signs (643.0900) | DAY | 196,827 | $0.32 | $0.18 | $0.18 | $0.32 | $0.18 |
| 313 | Traffic control covering signs type I (643.0910) | EACH | 1 | $750.00 | $325.00 | $325.00 | $750.00 | $325.00 |
| 314 | Traffic control covering signs type II (643.0920) | EACH | 16 | $82.64 | $135.00 | $135.00 | $82.64 | $135.00 |
| 315 | Traffic control signs fixed message (643.1000) | SF | 264 | $40.42 | $14.25 | $14.25 | $40.42 | $14.25 |
| 316 | Traffic control signs PCMS (643.1050) | DAY | 516 | $50.00 | $15.00 | $15.00 | $50.00 | $15.00 |
| 317 | Connected work zone start and end location markers (643.1220.S) | DAY | 2,840 | $4.65 | $5.25 | $5.25 | $4.65 | $5.25 |
| 318 | Temporary marking line removable tape 4-inch (643.3150) | LF | 6,736 | $3.85 | $1.55 | $1.55 | $3.85 | $1.55 |
| 319 | Temporary marking line paint 6- inch (643.3165) | LF | 399,376 | $0.18 | $0.25 | $0.25 | $0.18 | $0.25 |
| 320 | Temporary marking line epoxy 6- inch (643.3170) | LF | 165,640 | $0.50 | $0.59 | $0.59 | $0.50 | $0.59 |
| 321 | Temporary marking line paint 10- inch (643.3265) | LF | 16,435 | $0.30 | $0.45 | $0.45 | $0.30 | $0.45 |
| 322 | Temporary marking line epoxy 10- inch (643.3270) | LF | 6,041 | $1.00 | $1.05 | $1.05 | $1.00 | $1.05 |
| 323 | Temporary marking raised pavement marker type I (643.3760) | EACH | 1,947 | $6.34 | $10.00 | $10.00 | $6.34 | $10.00 |
| 324 | Traffic control (643.5000) | EACH | 1 | $360,578 | $495,000 | $525,000 | $360,578 | $495,000 |
| 325 | Geotextile type DF schedule A (645.0111) | SY | 3,152 | $3.25 | $6.00 | $3.25 | $3.97 | $6.00 |
| 326 | Geotextile type HR (645.0120) | SY | 10,049 | $3.10 | $5.00 | $3.10 | $3.50 | $4.00 |
| 327 | Geotextile type R (645.0130) | SY | 952 | $4.00 | $10.00 | $10.00 | $10.00 | $10.00 |
| 328 | Geotextile type sas (645.0140) | SY | 19,590 | $2.15 | $4.00 | $2.15 | $2.00 | $3.00 |
| 329 | Geogrid type SR (645.0220) | SY | 19,590 | $4.00 | $4.00 | $2.15 | $2.00 | $3.00 |
| 330 | Marking line epoxy 4-inch (646.1020) | LF | 1,873 | $0.65 | $0.34 | $0.34 | $0.65 | $0.34 |
| 331 | Marking line epoxy 6-inch (646.2020) | LF | 191,604 | $0.67 | $0.48 | $0.48 | $0.67 | $0.48 |
| 332 | Marking line grooved black epoxy 6-inch (646.2025) | LF | 177 | $2.00 | $0.85 | $0.85 | $2.00 | $0.85 |
| 333 | Marking line grooved permanent tape 6-inch (646.2050) | LF | 177 | $8.00 | $7.37 | $7.37 | $8.00 | $7.37 |
| 334 | Marking line epoxy 8-inch (646.3020) | LF | 174 | $1.20 | $0.92 | $0.92 | $1.20 | $0.92 |
| 335 | Marking line epoxy 10-inch (646.4020) | LF | 4,879 | $1.30 | $1.05 | $1.05 | $1.30 | $1.05 |
| 336 | Marking line grooved black epoxy 10-inch (646.4025) | LF | 1,082 | $2.40 | $1.88 | $1.88 | $2.40 | $1.88 |
| 337 | Marking line grooved wet ref epoxy 10-inch (646.4040) | LF | 9,642 | $4.00 | $2.80 | $2.80 | $4.00 | $2.80 |
| 338 | Marking line grooved permanent tape 10-inch (646.4050) | LF | 1,082 | $20.00 | $13.14 | $13.14 | $20.00 | $13.14 |
| 339 | Marking arrow epoxy (646.5020) | EACH | 36 | $280.00 | $250.21 | $250.21 | $280.00 | $250.21 |
| 340 | Marking word epoxy (646.5120) | EACH | 4 | $340.00 | $377.61 | $377.61 | $340.00 | $377.61 |
| 341 | Marking railroad crossing epoxy (646.5320) | EACH | 2 | $1,100.00 | $3,658.74 | $3,658.74 | $1,100.00 | $3,658.74 |
| 342 | Marking stop line epoxy 18-inch (646.6120) | LF | 321 | $16.00 | $15.65 | $15.65 | $16.00 | $15.65 |
| 343 | Marking dotted extension epoxy 18-inch (646.6320) | LF | 260 | $14.00 | $15.65 | $15.65 | $14.00 | $15.65 |
| 344 | Marking diagonal epoxy 6-inch (646.7020) | LF | 242 | $7.00 | $11.50 | $11.50 | $7.00 | $11.50 |
| 345 | Marking diagonal epoxy 12-inch (646.7120) | LF | 840 | $8.00 | $11.91 | $11.91 | $8.00 | $11.91 |
| 346 | Marking chevron epoxy 24-inch (646.7220) | LF | 744 | $14.00 | $25.68 | $25.68 | $14.00 | $25.68 |
| 347 | Marking chevron epoxy 12-inch (646.7320) | LF | 90 | $11.00 | $24.86 | $24.86 | $11.00 | $24.86 |
| 348 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 1,262 | $12.00 | $11.50 | $11.50 | $12.00 | $11.50 |
| 349 | Marking curb epoxy (646.8120) | LF | 64 | $7.00 | $7.48 | $7.48 | $7.00 | $7.48 |
| 350 | Marking island nose epoxy (646.8220) | EACH | 4 | $320.00 | $281.68 | $281.68 | $320.00 | $281.68 |
| 351 | Marking removal line 4-inch (646.9000) | LF | 1,351 | $0.50 | $1.85 | $1.85 | $0.50 | $1.85 |
| 352 | Conduit rigid metallic 2-inch (652.0125) | LF | 172 | $475.00 | $475.00 | $475.00 | $475.00 | $475.00 |
| 353 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 37,805 | $11.00 | $11.00 | $11.00 | $11.00 | $11.00 |
| 354 | Conduit rigid nonmetallic schedule 40 3-inch (652.0235) | LF | 3,537 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 |
| 355 | Conduit rigid nonmetallic schedule 80 3-inch (652.0335) | LF | 3,210 | $17.00 | $17.00 | $17.00 | $17.00 | $17.00 |
| 356 | Conduit special 3-inch (652.0615) | LF | 245 | $32.00 | $32.00 | $32.00 | $32.00 | $32.00 |
| 357 | Install conduit into existing item (652.0700.S) | EACH | 8 | $275.00 | $275.00 | $275.00 | $275.00 | $275.00 |
| 358 | Pull boxes non-conductive 24X36- inch (653.0154) | EACH | 5 | $2,200.00 | $2,200.00 | $2,200.00 | $2,200.00 | $2,200.00 |
| 359 | Pull boxes non-conductive 24X42- inch (653.0164) | EACH | 94 | $2,400.00 | $2,400.00 | $2,400.00 | $2,400.00 | $2,400.00 |
| 360 | Junction boxes 18X12X6-inch (653.0222) | EACH | 2 | $2,950.00 | $2,950.00 | $2,950.00 | $2,950.00 | $2,950.00 |
| 361 | Adjusting pull boxes (653.0900) | EACH | 5 | $875.00 | $875.00 | $875.00 | $875.00 | $875.00 |
| 362 | Removing pull boxes (653.0905) | EACH | 3 | $75.00 | $75.00 | $75.00 | $75.00 | $75.00 |
| 363 | Concrete bases type 5 (654.0105) | EACH | 65 | $1,575.00 | $1,575.00 | $1,575.00 | $1,575.00 | $1,575.00 |
| 364 | Concrete bases type 7 (654.0107) | EACH | 16 | $1,750.00 | $1,750.00 | $1,750.00 | $1,750.00 | $1,750.00 |
| 365 | Concrete control cabinet bases type L30 (654.0230) | EACH | 3 | $2,400.00 | $2,400.00 | $2,400.00 | $2,400.00 | $2,400.00 |
| 366 | Electrical wire lighting 12 AWG (655.0610) | LF | 64,443 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 367 | Electrical wire lighting 8 AWG (655.0620) | LF | 34,959 | $1.45 | $1.45 | $1.45 | $1.45 | $1.45 |
| 368 | Electrical wire lighting 6 AWG (655.0625) | LF | 46,228 | $2.10 | $2.10 | $2.10 | $2.10 | $2.10 |
| 369 | Electrical wire lighting 4 AWG (655.0630) | LF | 39,600 | $2.50 | $2.50 | $2.50 | $2.50 | $2.50 |
| 370 | Electrical service meter breaker pedestal (location) 002. CB1900 (656.0201) | EACH | 1 | $1,950.00 | $1,950.00 | $1,950.00 | $1,950.00 | $1,950.00 |
| 371 | Electrical service meter breaker pedestal (location) 003. CB300 (656.0201) | EACH | 1 | $1,950.00 | $1,950.00 | $1,950.00 | $1,950.00 | $1,950.00 |
| 372 | Electrical service meter breaker pedestal (location) 004. MB9-2 (656.0201) | EACH | 1 | $1,950.00 | $1,950.00 | $1,950.00 | $1,950.00 | $1,950.00 |
| 373 | Electrical service breaker disconnect box (location) 001. CB9- 2 (656.0501) | EACH | 1 | $900.00 | $900.00 | $900.00 | $900.00 | $900.00 |
| 374 | Electrical service breaker disconnect box (location) 002. CB10-1 (656.0501) | EACH | 1 | $900.00 | $900.00 | $900.00 | $900.00 | $900.00 |
| 375 | Transformer bases breakaway 15- 17 inch bolt circle (657.0210) | EACH | 16 | $800.00 | $800.00 | $800.00 | $800.00 | $800.00 |
| 376 | Transformer bases breakaway 11 1/2-inch bolt circle (657.0255) | EACH | 65 | $675.00 | $675.00 | $675.00 | $675.00 | $675.00 |
| 377 | Poles type 5-aluminum (657.0322) | EACH | 62 | $2,025.00 | $2,025.00 | $2,025.00 | $2,025.00 | $2,025.00 |
| 378 | Poles type 17-aluminum (657.0337) | EACH | 16 | $3,975.00 | $3,975.00 | $3,975.00 | $3,975.00 | $3,975.00 |
| 379 | Luminaire arms single member 6- inch clamp 4-FT (657.0620) | EACH | 16 | $385.00 | $385.00 | $385.00 | $385.00 | $385.00 |
| 380 | Luminaire arms truss type 4-inch clamp 12-FT (657.0709) | EACH | 1 | $775.00 | $775.00 | $775.00 | $775.00 | $775.00 |
| 381 | Luminaire arms truss type 4 1/2- inch clamp 12-FT (657.0710) | EACH | 62 | $755.00 | $755.00 | $755.00 | $755.00 | $755.00 |
| 382 | Underdeck lighting (structure) 001. B-44-0341 (659.0601) | EACH | 1 | $24,300 | $24,300 | $24,300 | $24,300 | $24,300 |
| 383 | Underdeck lighting (structure) 002. B-44-0342 (659.0601) | EACH | 1 | $17,300 | $17,300 | $17,300 | $17,300 | $17,300 |
| 384 | Underdeck lighting (structure) 003. B-44-0343 (659.0601) | EACH | 1 | $23,775 | $23,775 | $23,775 | $23,775 | $23,775 |
| 385 | Underdeck lighting (structure) 004. B-44-0344 (659.0601) | EACH | 1 | $30,600 | $30,600 | $30,600 | $30,600 | $30,600 |
| 386 | Underdeck lighting (structure) 005. B-44-0345 (659.0601) | EACH | 1 | $12,825 | $12,825 | $12,825 | $12,825 | $12,825 |
| 387 | Underdeck lighting (structure) 006. B-44-0346 (659.0601) | EACH | 1 | $12,825 | $12,825 | $12,825 | $12,825 | $12,825 |
| 388 | Luminaires utility LED B (659.1120) | EACH | 63 | $380.00 | $380.00 | $380.00 | $380.00 | $380.00 |
| 389 | Luminaires utility LED C (659.1125) | EACH | 16 | $410.00 | $410.00 | $410.00 | $410.00 | $410.00 |
| 390 | Luminaires underdeck LED B (659.1210) | EACH | 12 | $585.00 | $585.00 | $585.00 | $585.00 | $585.00 |
| 391 | Lighting control cabinets 120/240 30-inch (659.2130) | EACH | 2 | $8,575.00 | $8,575.00 | $8,575.00 | $8,575.00 | $8,575.00 |
| 392 | Ramp closure gates 26-FT (662.1026.S) | EACH | 1 | $27,075 | $27,075 | $27,075 | $27,075 | $27,075 |
| 393 | Ramp closure gates 30-FT (662.1030.S) | EACH | 1 | $27,075 | $27,075 | $27,075 | $27,075 | $27,075 |
| 394 | Ramp closure gates 40-FT (662.1040.S) | EACH | 1 | $28,145 | $28,145 | $27,145 | $28,145 | $28,145 |
| 395 | Field system integrator (670.0101) | EACH | 1 | $38,000 | $38,000 | $38,000 | $38,000 | $38,000 |
| 396 | ITS documentation (670.0201) | EACH | 1 | $6,500.00 | $6,500.00 | $6,500.00 | $6,500.00 | $6,500.00 |
| 397 | Conduit HDPE 3-duct 2-inch (671.0132) | LF | 20,764 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 |
| 398 | Conduit HDPE directional bore 3- duct 2-inch (671.0232) | LF | 2,809 | $38.00 | $38.00 | $38.00 | $38.00 | $38.00 |
| 399 | Fiber optic cable marker (671.0300) | EACH | 60 | $75.00 | $75.00 | $75.00 | $75.00 | $75.00 |
| 400 | Communication vault type 1 (673.0105) | EACH | 18 | $2,450.00 | $2,450.00 | $2,450.00 | $2,450.00 | $2,450.00 |
| 401 | Tracer wire marker posts (673.0200) | EACH | 38 | $125.00 | $125.00 | $125.00 | $125.00 | $125.00 |
| 402 | Install pole mounted cabinet (673.1225.S) | EACH | 6 | $2,875.00 | $2,875.00 | $2,875.00 | $2,875.00 | $2,875.00 |
| 403 | Cable microwave detector (674.0200) | LF | 5,374 | $4.00 | $4.00 | $4.00 | $4.00 | $4.00 |
| 404 | Remove cable (674.0300) | LF | 23,642 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 |
| 405 | Install mounted controller microwave detector assembly (675.0300) | EACH | 6 | $3,400.00 | $3,400.00 | $3,400.00 | $3,400.00 | $3,400.00 |
| 406 | Install camera pole 50-FT (677.0150) | EACH | 2 | $4,325.00 | $4,325.00 | $4,325.00 | $4,325.00 | $4,325.00 |
| 407 | Install camera assembly (677.0200) | EACH | 2 | $2,705.00 | $2,705.00 | $2,705.00 | $2,705.00 | $2,705.00 |
| 408 | Removing 50-FT camera pole (677.9051.S) | EACH | 2 | $2,870.00 | $2,870.00 | $2,870.00 | $2,870.00 | $2,870.00 |
| 409 | Install fiber optic cable outdoor plant 12-CT (678.0012) | LF | 2,436 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 |
| 410 | Install fiber optic cable outdoor plant 72-CT (678.0072) | LF | 24,776 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 |
| 411 | Fiber optic splice enclosure (678.0200) | EACH | 5 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 412 | Fiber optic splice (678.0300) | EACH | 160 | $50.00 | $50.00 | $50.00 | $50.00 | $50.00 |
| 413 | Fiber optic termination (678.0400) | EACH | 8 | $225.00 | $225.00 | $225.00 | $225.00 | $225.00 |
| 414 | Communication system testing (678.0501) | EACH | 1 | $6,500.00 | $6,500.00 | $6,500.00 | $6,500.00 | $6,500.00 |
| 415 | Install ethernet switches (678.0600) | EACH | 2 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 416 | Sawing asphalt (690.0150) | LF | 3,124 | $1.75 | $1.75 | $1.75 | $1.69 | $1.75 |
| 417 | Sawing concrete (690.0250) | LF | 1,700 | $2.35 | $2.35 | $2.35 | $3.50 | $2.35 |
| 418 | Incentive strength concrete structures (715.0502) | DOL | 16,284 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 419 | Incentive strength concrete barrier (715.0603) | DOL | 40,629 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 420 | Incentive flexural strength concrete pavement (715.0715) | DOL | 114,074 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 421 | Incentive iri ride (740.0440) | DOL | 58,750 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 422 | Installing and maintaining bird deterrent system (station) 001. 1251NB+00 (999.2000.S) | EACH | 1 | $500.00 | $1.00 | $500.00 | $500.00 | $500.00 |
| 423 | Installing and maintaining bird deterrent system (station) 002. 1251SB+00 (999.2000.S) | EACH | 1 | $500.00 | $1.00 | $500.00 | $500.00 | $500.00 |
| 424 | Installing and maintaining bird deterrent system (station) 003. 1323NB+00 (999.2000.S) | EACH | 1 | $500.00 | $1.00 | $500.00 | $500.00 | $500.00 |
| 425 | Installing and maintaining bird deterrent system (station) 004. 1322SB+00 (999.2000.S) | EACH | 1 | $500.00 | $1.00 | $500.00 | $500.00 | $500.00 |
| 426 | Installing and maintaining bird deterrent system (station) 005. 1411NB+00 (999.2000.S) | EACH | 1 | $500.00 | $1.00 | $500.00 | $500.00 | $500.00 |
| 427 | Installing and maintaining bird deterrent system (station) 006. 1411SB+00 (999.2000.S) | EACH | 1 | $500.00 | $1.00 | $500.00 | $500.00 | $500.00 |
| 428 | Installing and maintaining bird deterrent system (station) 007. 1437NB+00 (999.2000.S) | EACH | 1 | $500.00 | $1.00 | $500.00 | $500.00 | $500.00 |
| 429 | Installing and maintaining bird deterrent system (station) 008. 1436SB+00 (999.2000.S) | EACH | 1 | $500.00 | $1.00 | $500.00 | $500.00 | $500.00 |
| 430 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,100 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 431 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 5,760 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 432 | Special 001. roadway embankment (SPV.0035) | CY | 144,555 | $0.01 | $0.01 | $0.01 | $13.50 | $0.01 |
| 433 | Special 002. HPC masonry structures (SPV.0035) | CY | 5,504 | $500.00 | $930.00 | $500.00 | $500.00 | $500.00 |
| 434 | Special 001. incentive iri ride PCC surfaces (SPV.0055) | DOL | 162,300 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 435 | Special 001. baseline CMP progress schedule (SPV.0060) | EACH | 1 | $1,000.00 | $3,000.00 | $55,300 | $1.00 | $5,000.00 |
| 436 | Special 002. CMP progress schedule and accepted revisions (SPV.0060) | EACH | 1 | $1,000.00 | $2,500.00 | $10,000 | $1.00 | $2,500.00 |
| 437 | Special 003. salvaging ramp gate system (SPV.0060) | EACH | 2 | $1,750.00 | $1,750.00 | $1,750.00 | $1,750.00 | $1,750.00 |
| 438 | Special 004. removing storm sewer plug (SPV.0060) | EACH | 2 | $300.00 | $170.00 | $817.00 | $368.50 | $368.50 |
| 439 | Special 005. reconnect storm sewer (SPV.0060) | EACH | 89 | $1,170.00 | $575.00 | $1,317.00 | $1,308.99 | $1,308.99 |
| 440 | Special 006. storm sewer plug (SPV.0060) | EACH | 51 | $850.00 | $500.00 | $250.00 | $649.41 | $649.41 |
| 441 | Special 007. median inlet cover type Y (SPV.0060) | EACH | 25 | $605.00 | $629.00 | $981.39 | $579.00 | $579.00 |
| 442 | Special 008. structure lids (SPV.0060) | EACH | 28 | $1,545.00 | $1,070.00 | $1,884.43 | $1,639.29 | $1,639.29 |
| 443 | Special 009. sealing storm structure (SPV.0060) | EACH | 18 | $600.00 | $525.00 | $758.50 | $780.56 | $780.56 |
| 444 | Special 010. fastening sewer access covers (SPV.0060) | EACH | 4 | $175.00 | $125.00 | $219.45 | $675.00 | $675.00 |
| 445 | Special 011. pond 67-1320-LT outlet storm sewer structure (SPV.0060) | EACH | 1 | $19,550 | $21,886 | $22,914 | $17,910 | $17,910 |
| 446 | Special 012. pond 67-1363-LT outlet storm sewer structure (SPV.0060) | EACH | 1 | $19,550 | $21,886 | $16,260 | $17,910 | $17,910 |
| 447 | Special 013. pond 67-1391-LT outlet storm sewer structure (SPV.0060) | EACH | 1 | $19,550 | $21,886 | $19,020 | $17,910 | $17,910 |
| 448 | Special 014. pond 67-1435-LT outlet storm sewer structure (SPV.0060) | EACH | 1 | $19,550 | $21,886 | $18,405 | $17,910 | $17,910 |
| 449 | Special 015. detention pond anti seep collar (SPV.0060) | EACH | 4 | $1,100.00 | $900.00 | $1,000.00 | $1,225.00 | $1,225.00 |
| 450 | Special 016. removing cover plates (SPV.0060) | EACH | 52 | $100.00 | $0.01 | $50.00 | $375.96 | $375.96 |
| 451 | Special 017. fixed message sign portable support (SPV.0060) | EACH | 6 | $825.19 | $550.00 | $550.00 | $825.19 | $550.00 |
| 452 | Special 018. fire hydrant sign mounting (SPV.0060) | EACH | 2 | $500.00 | $500.00 | $500.00 | $500.00 | $500.00 |
| 453 | Special 019. anchor bolt cover shroud (SPV.0060) | EACH | 61 | $525.00 | $525.00 | $525.00 | $525.00 | $525.00 |
| 454 | Special 020. concrete bases type 7 tall (SPV.0060) | EACH | 58 | $3,275.00 | $3,275.00 | $3,275.00 | $3,275.00 | $3,275.00 |
| 455 | Special 021. lighting control cabinets 277/480 30-inch 3-phase (SPV.0060) | EACH | 1 | $11,250 | $11,250 | $11,250 | $11,250 | $11,250 |
| 456 | Special 022. electrical service main lugs only meter pedestal 3-phase 600V (SPV.0060) | EACH | 1 | $2,400.00 | $2,400.00 | $2,400.00 | $2,400.00 | $2,400.00 |
| 457 | Special 023. concrete transformer pad (SPV.0060) | EACH | 1 | $4,000.00 | $4,000.00 | $4,000.00 | $4,000.00 | $4,000.00 |
| 458 | Special 024. electrical service meter breaker pedestal special (SPV.0060) | EACH | 2 | $5,800.00 | $5,800.00 | $5,800.00 | $5,800.00 | $5,800.00 |
| 459 | Special 025. install ethernet extender (SPV.0060) | EACH | 8 | $500.00 | $500.00 | $500.00 | $500.00 | $500.00 |
| 460 | Special 026. temporary concrete barrier gate, 24-FT (SPV.0060) | EACH | 1 | $26,263 | $10,850 | $10,850 | $26,263 | $10,850 |
| 461 | Special 027. emergency response to traffic involving concrete barrier temporary (SPV.0060) | EACH | 10 | $3,000.00 | $2,850.00 | $350.00 | $4,633.87 | $500.00 |
| 462 | Special 028. emergency response to traffic involving crash cushion temporary (SPV.0060) | EACH | 10 | $1,633.87 | $350.00 | $350.00 | $1,983.87 | $350.00 |
| 463 | Special 029. crash cushions temporary left in place (SPV.0060) | EACH | 4 | $4,114.68 | $10,000 | $10,000 | $4,114.68 | $10,000 |
| 464 | Special 030. construction staking project 1130-67-72 (SPV.0060) | EACH | 1 | $232,400 | $375,000 | $450,000 | $375,000 | $450,000 |
| 465 | Special 031. construction staking project 1130-67-76 (SPV.0060) | EACH | 1 | $232,400 | $75,000 | $100,000 | $75,000 | $100,000 |
| 466 | Special 032. construction staking project 1130-67-86 (SPV.0060) | EACH | 1 | $232,400 | $50,000 | $50,000 | $50,000 | $50,000 |
| 467 | Special 033. maintain and remove crash cushions temporary left in place (SPV.0060) | EACH | 3 | $2,062.97 | $1,050.00 | $1,050.00 | $2,062.97 | $1,050.00 |
| 468 | Special 034. inlet marker (SPV.0060) | EACH | 363 | $60.00 | $60.00 | $60.00 | $60.00 | $60.00 |
| 469 | Special 035. temporary bridge widening B-44-0072 (SPV.0060) | EACH | 1 | $400,000 | $350,000 | $400,000 | $400,000 | $400,000 |
| 470 | Special 036. temporary bridge widening B-44-0074 (SPV.0060) | EACH | 1 | $400,000 | $350,000 | $400,000 | $400,000 | $400,000 |
| 471 | Special 001. street sweeping (SPV.0075) | HRS | 740 | $210.00 | $225.00 | $125.00 | $200.00 | $0.01 |
| 472 | Special 002. animal carcass removal (SPV.0075) | HRS | 240 | $100.00 | $35.00 | $170.00 | $150.00 | $600.00 |
| 473 | Special 001. HMA longitudinal joint repair (SPV.0090) | LF | 8,774 | $10.25 | $10.25 | $10.25 | $10.25 | $10.25 |
| 474 | Special 002. removing existing piling steel (SPV.0090) | LF | 3,728 | $3.00 | $20.00 | $1.00 | $1.00 | $1.00 |
| 475 | Special 003. concrete barrier type S42 special (SPV.0090) | LF | 34,843 | $64.50 | $70.60 | $52.32 | $52.32 | $71.86 |
| 476 | Special 004. concrete barrier type S56 special (SPV.0090) | LF | 38,966 | $77.54 | $77.42 | $55.39 | $55.39 | $78.55 |
| 477 | Special 005. concrete curb and gutter 36-inch special (SPV.0090) | LF | 4,640 | $30.00 | $24.60 | $27.52 | $27.52 | $24.60 |
| 478 | Special 006. concrete barrier temporary precast left in place (SPV.0090) | LF | 4,200 | $0.01 | $15.00 | $25.00 | $25.00 | $25.00 |
| 479 | Special 007. maintain and remove concrete barrier temporary precast left in place (SPV.0090) | LF | 27,190 | $0.01 | $1.00 | $3.00 | $3.00 | $3.00 |
| 480 | Special 008. glare screens temporary (SPV.0090) | LF | 2,070 | $11.94 | $7.75 | $7.75 | $11.94 | $7.75 |
| 481 | Special 001. longitudinal grooving bridge deck (SPV.0165) | SF | 111,369 | $0.77 | $0.60 | $0.62 | $0.57 | $0.57 |
| 482 | Special 001. concrete pavement 10 1/2-inch special (SPV.0180) | SY | 316,379 | $52.64 | $47.29 | $55.25 | $55.25 | $59.42 |
| 483 | Special 002. double shredded hardwood mulch (SPV.0180) | SY | 620 | $12.00 | $12.00 | $12.00 | $12.00 | $12.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of July 8, 2025. Compiled by Mirage Metrics.