WisDOT contract 20250909008 bid tabulation

Wales - Hartford; Perkins Road to Glacier Pass (STH 083, Waukesha County Wales - Hartford). Let by Wisconsin DOT on September 9, 2025, Waukesha. 3 bids received; low bid $2,608,972 by Payne and Dolan, Inc.

Owner
Wisconsin DOT
Letting
09 SEP 2025
Pay items
120
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Payne and Dolan, Inc$2,608,972Low
2Rock Road Companies, Inc.$2,812,907+8.0%
3Stark Pavement Corporation$3,399,908+30%
WisDOT contract 20250909008: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Payne and Dolan, Inc2. Rock Road Companies, Inc.3. Stark Pavement Corporation
1Removing asphaltic surface (204.0110)SY1,142$16.48$16.48$33.35
2Removing asphaltic surface butt joints (204.0115)SY200$0.01$10.06$13.00
3Removing asphaltic surface milling (204.0125)TON14,645$0.01$14.51$26.00
4Removing curb (204.0130)LF41$20.00$20.00$56.00
5Removing curb & gutter (204.0150)LF2,973$7.75$7.75$13.50
6Removing concrete sidewalk (204.0155)SY2,437$3.00$3.00$11.00
7Removing inlets (204.0220)EACH1$178.62$400.00$1,000.00
8Removing storm sewer (size) 01. 12-inch (204.0245)LF27$13.23$41.20$39.00
9Excavation common (205.0100)CY574$43.17$43.17$62.00
10Prepare foundation for asphaltic paving (project) 01. 1330-34-70 (211.0101)EACH1$14,214$0.01$7,920.00
11Finishing roadway (project) 01. 1330-34-70 (213.0100)EACH1$142.14$5,391.15$7,900.00
12Base aggregate dense 3/4-inch (305.0110)TON362$44.00$61.33$51.00
13Base aggregate dense 1 1/4-inch (305.0120)TON1,137$24.00$24.00$31.65
14Tack coat (455.0605)GAL9,320$3.00$2.38$3.00
15Incentive density HMA pavement (460.2000)DOL9,580$1.00$1.00$1.00
16HMA pavement 4 MT 58-28 H (460.6424)TON14,958$80.60$79.50$89.95
17Asphaltic surface (465.0105)TON80$430.00$222.84$325.00
18Asphaltic surface driveways and field entrances (465.0120)TON246$80.60$145.38$92.40
19Pigmented surface sealer reseal (502.3205)SY129$18.00$18.00$18.00
20Polymer overlay (509.5100.S)SY978$43.92$43.92$43.92
21Concrete collars for pipe (520.8000)EACH1$454.55$850.00$1,337.00
22Cleaning culvert pipes (520.8700)EACH5$1,638.30$1,800.00$1,800.00
23Concrete curb type J (601.0120)LF42$37.65$37.65$70.00
24Concrete curb & gutter 18-inch type D (601.0407)LF93$56.72$56.72$70.00
25Concrete curb & gutter 30-inch type D (601.0411)LF2,053$62.58$62.58$70.00
26Concrete curb & gutter 6-inch sloped 30-inch type J (601.0415)LF311$65.07$65.07$70.00
27Concrete curb & gutter 4-inch sloped 36-inch type D (601.0553)LF507$70.57$70.57$70.00
28Concrete curb pedestrian (601.0600)LF582$25.29$25.29$50.00
29Concrete sidewalk 5-inch (602.0410)SF21,154$8.91$8.91$10.50
30Curb ramp detectable warning field natural patina (602.0515)SF1,320$43.00$43.00$55.00
31Curb ramp detectable warning field radial natural patina (602.0615)SF689$48.00$48.00$58.00
32Concrete driveway 7-inch (602.0815)SY2$125.00$125.00$500.00
33Riprap heavy (606.0300)CY70$116.16$207.42$150.00
34Storm sewer pipe reinforced concrete class III 12-inch (608.0312)LF27$103.70$220.35$174.00
35Inlets 2X3-FT (611.3230)EACH1$2,250.90$2,841.00$3,407.00
36Adjusting inlet covers (611.8115)EACH1$714.59$600.00$1,432.00
37Salvaged inlet covers (611.9710)EACH1$71.45$475.00$668.00
38Maintenance and repair of haul roads (project) 01. 1330-34-70 (618.0100)EACH1$1.00$0.01$3,500.00
39Mobilization (619.1000)EACH1$31,887$101,765$122,000
40Concrete median sloped nose (620.0300)SF34$30.00$30.00$68.00
41Topsoil (625.0100)SY650$18.00$10.69$15.90
42Salvaged topsoil (625.0500)SY1,300$18.00$5.43$15.90
43Mulching (627.0200)SY400$1.50$1.10$1.10
44Silt fence (628.1504)LF2,200$2.25$1.99$1.99
45Silt fence maintenance (628.1520)LF2,200$0.01$0.10$0.10
46Mobilizations erosion control (628.1905)EACH6$100.00$250.00$250.00
47Mobilizations emergency erosion control (628.1910)EACH3$100.00$150.00$150.00
48Erosion mat urban class I type B (628.2008)SY1,300$2.25$1.89$1.89
49Inlet protection type B (628.7010)EACH40$55.00$41.00$41.00
50Inlet protection type C (628.7015)EACH170$60.00$38.00$38.00
51Inlet protection type D (628.7020)EACH20$120.00$88.10$88.10
52Culvert pipe checks (628.7555)EACH60$19.00$45.00$45.00
53Fertilizer type B (629.0210)CWT0.90$250.00$100.00$100.00
54Seeding mixture no. 30 (630.0130)LB60$11.00$15.50$15.50
55Seeding temporary (630.0200)LB35$5.00$10.00$10.00
56Seed water (630.0500)MGAL30$10.00$25.00$25.00
57Posts wood 4X6-inch X 18-FT (634.0618)EACH45$95.00$95.00$95.00
58Posts tubular steel 2X2-inch X 16- FT (634.0816)EACH5$210.00$175.00$175.00
59Signs type II reflective H (637.2210)SF122.76$22.00$19.10$19.10
60Signs type II reflective F (637.2230)SF443$22.00$18.50$18.50
61Moving signs type II (638.2102)EACH47$150.00$100.00$100.00
62Removing signs type II (638.2602)EACH51$35.00$22.00$22.00
63Removing small sign supports (638.3000)EACH22$35.00$22.00$22.00
64Field office type C (642.5201)EACH1$18,718$8,750.00$16,000
65Traffic control drums (643.0300)DAY58,294$0.08$0.08$0.08
66Traffic control barricades type III (643.0420)DAY5,535$0.60$0.60$0.60
67Traffic control warning lights type A (643.0705)DAY5,390$0.08$0.08$0.08
68Traffic control warning lights type C (643.0715)DAY2,879$0.08$0.08$0.08
69Traffic control signs (643.0900)DAY10,958$0.45$0.45$0.45
70Traffic control covering signs type I (643.0910)EACH2$175.00$175.00$175.00
71Traffic control covering signs type II (643.0920)EACH6$40.00$40.00$40.00
72Traffic control signs fixed message (643.1000)SF72$16.00$16.00$16.00
73Traffic control signs PCMS (643.1050)DAY98$30.00$30.00$30.00
74Traffic control cones 42-inch (643.1070)DAY85,380$0.12$0.12$0.12
75Temporary marking line paint 4- inch (643.3105)LF8,896$0.30$0.30$0.30
76Temporary marking line paint 8- inch (643.3205)LF1,993$1.00$1.00$1.00
77Temporary marking line paint 10- inch (643.3265)LF291$2.00$2.00$2.00
78Temporary marking crosswalk paint 6-inch (643.3305)LF2,310$0.65$0.65$0.65
79Temporary marking arrow paint (643.3505)EACH32$45.00$45.00$45.00
80Traffic control (643.5000)EACH1$56,291$56,291$56,291
81Temporary pedestrian surface matting (644.1440)SF1,845$5.00$5.00$5.00
82Temporary pedestrian curb ramp (644.1601)DAY612$6.00$6.00$6.00
83Temporary pedestrian detectable warning field (644.1605)SF150$6.00$6.00$6.00
84Temporary pedestrian barricade (644.1810)LF1,620$4.50$4.50$4.50
85Geotextile type HR (645.0120)SY155$2.46$3.05$6.00
86Marking line epoxy 4-inch (646.1020)LF12,601$0.32$0.32$0.65
87Marking line epoxy 6-inch (646.2020)LF340$0.44$0.44$0.95
88Marking line grooved black epoxy 6-inch (646.2025)LF3,048$0.80$0.80$1.10
89Marking line grooved wet ref epoxy 6-inch (646.2040)LF63,835$1.30$1.30$1.32
90Marking line epoxy 8-inch (646.3020)LF401$0.85$0.85$1.10
91Marking line epoxy 10-inch (646.4020)LF696$0.97$0.97$1.30
92Marking line grooved black epoxy 10-inch (646.4025)LF190$1.76$1.76$2.50
93Marking line grooved wet ref epoxy 10-inch (646.4040)LF10,485$2.60$2.60$3.05
94Marking arrow epoxy (646.5020)EACH68$235.96$235.96$220.00
95Marking word epoxy (646.5120)EACH28$285.07$285.07$240.00
96Marking stop line epoxy 18-inch (646.6120)LF473$13.37$13.37$13.00
97Marking dotted extension epoxy 18-inch (646.6320)LF270$14.60$14.60$16.50
98Marking diagonal epoxy 12-inch (646.7120)LF642$14.22$14.22$9.75
99Marking chevron epoxy 12-inch (646.7320)LF260$23.21$23.21$10.00
100Marking crosswalk epoxy transverse line 6-inch (646.7420)LF3,437$11.60$11.60$10.50
101Marking corrugated median epoxy (646.8020)SF444$8.23$8.23$9.00
102Marking curb epoxy (646.8120)LF887$6.99$6.99$8.00
103Marking island nose epoxy (646.8220)EACH41$262.25$262.25$270.00
104Marking removal line 8-inch (646.9100)LF435$1.25$1.25$1.25
105Marking removal special marking (646.9300)EACH10$100.00$100.00$100.00
106Construction staking curb gutter and curb & gutter (650.5500)LF3,588$2.01$1.00$2.01
107Construction staking curb ramps (650.9000)EACH97$227.27$100.00$227.25
108Construction staking sidewalk (project) 01. 1330-34-70 (650.9500)EACH1$1.01$1,500.00$1.01
109Construction staking supplemental control (project) 01. 1330-34-70 (650.9911)EACH1$3,813.13$1,500.00$3,812.75
110Sawing asphalt (690.0150)LF3,586$1.39$1.39$1.39
111Sawing concrete (690.0250)LF1,737$1.85$1.85$1.85
112Incentive iri ride (740.0440)DOL21,106$1.00$1.00$1.00
113On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS800$5.00$5.00$5.00
114On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS2,280$5.00$5.00$5.00
115Special 01. repair and regrout structure pipe holes (SPV.0060)EACH11$714.58$279.55$572.00
116Special 02. cleaning inlets (SPV.0060)EACH2$297.33$400.00$750.00
117Special 03. reset and retie end section (SPV.0060)EACH1$1,429.15$1,376.50$1,131.00
118Special 04. cleaning storm sewer outfall (SPV.0060)EACH2$714.58$706.25$1,000.00
119Special 05. vegetation removal outfall (SPV.0060)EACH3$303.03$600.00$700.00
120Special 01. asphaltic repair (SPV.0195)TON292$175.00$148.01$207.00
WisDOT contract 20250909008: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of September 9, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy