WisDOT contract 20250909009 bid tabulation
Newburg - Saukville; 0.6 Miles West of CTH I (STH 033, Ozaukee County Newburg - Saukville). Let by Wisconsin DOT on September 9, 2025, Ozaukee. 3 bids received; low bid $1,425,905 by Zenith Tech., Inc. - Waukesha.
- Owner
- Wisconsin DOT
- Letting
- 09 SEP 2025
- Pay items
- 80
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Zenith Tech., Inc. - Waukesha | $1,425,905 | Low |
| 2 | Highway Landscapers, Inc. | $1,541,734 | +8.0% |
| 3 | Lunda Construction Company | $1,953,746 | +37% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Zenith Tech., Inc. - Waukesha | 2. Highway Landscapers, Inc. | 3. Lunda Construction Company |
|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 7 | $3,515.00 | $3,000.00 | $1,065.00 |
| 2 | Grubbing (201.0205) | STA | 7 | $3,515.00 | $500.00 | $335.00 |
| 3 | Removing small pipe culverts (203.0100) | EACH | 1 | $650.00 | $500.00 | $650.00 |
| 4 | Removing structure (structure) 01. R-45-45 (203.0220) | EACH | 1 | $94,000 | $27,000 | $36,000 |
| 5 | Removing guardrail (204.0165) | LF | 700 | $2.50 | $3.00 | $2.50 |
| 6 | Excavation common (205.0100) | CY | 371 | $21.60 | $40.00 | $21.60 |
| 7 | Excavation for structures retaining walls (structure) 01. R-45-47 (206.3001) | EACH | 1 | $113,000 | $69,000 | $208,270 |
| 8 | Prepare foundation for asphaltic shoulders (211.0400) | STA | 9 | $90.00 | $250.00 | $90.00 |
| 9 | Prepare foundation for base aggregate (211.0500) | STA | 9 | $90.00 | $100.00 | $90.00 |
| 10 | Finishing roadway (project) 01. 1410-16-71 (213.0100) | EACH | 1 | $3,192.96 | $500.00 | $500.00 |
| 11 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 410 | $35.00 | $40.00 | $28.50 |
| 12 | Tack coat (455.0605) | GAL | 14 | $3.50 | $2.50 | $2.50 |
| 13 | Incentive density HMA pavement (460.2000) | DOL | 125 | $1.00 | $1.00 | $1.00 |
| 14 | HMA pavement 4 MT 58-28 S (460.6224) | TON | 193 | $152.40 | $188.00 | $188.00 |
| 15 | Asphaltic flumes (465.0315) | SY | 6 | $86.10 | $295.00 | $295.00 |
| 16 | Concrete masonry soldier pile footings (502.0110.S) | CY | 239 | $1,255.00 | $293.00 | $1,250.00 |
| 17 | Structural steel HS (506.0605) | LB | 148,900 | $0.82 | $1.93 | $3.00 |
| 18 | Painting epoxy system (structure) 01. R-45-47 (517.0601) | EACH | 1 | $41,000 | $60,000 | $10,000 |
| 19 | Apron endwalls for culvert pipe 18- inch (520.1018) | EACH | 1 | $415.00 | $700.00 | $415.00 |
| 20 | Concrete collars for pipe (520.8000) | EACH | 1 | $2,000.00 | $20,000 | $2,000.00 |
| 21 | Cleaning culvert pipes (520.8700) | EACH | 1 | $2,500.00 | $5,000.00 | $2,500.00 |
| 22 | Culvert pipe reinforced concrete class IV 30-inch (522.0430) | LF | 26 | $237.40 | $225.00 | $237.40 |
| 23 | Apron endwalls for culvert pipe reinforced concrete 30-inch (522.1030) | EACH | 1 | $1,950.00 | $2,325.00 | $1,950.00 |
| 24 | Concrete curb & gutter 4-inch sloped 36-inch type D (601.0553) | LF | 738 | $35.72 | $43.00 | $35.00 |
| 25 | Riprap extra-light (606.0050) | CY | 0.75 | $275.00 | $500.00 | $275.00 |
| 26 | Riprap medium (606.0200) | CY | 13 | $130.00 | $150.00 | $130.00 |
| 27 | Storm sewer pipe class III-A 12- inch (608.3012) | LF | 284 | $70.72 | $70.00 | $70.72 |
| 28 | Storm sewer pipe class III-A 18- inch (608.3018) | LF | 31 | $85.05 | $80.00 | $85.05 |
| 29 | Manhole covers type J (611.0530) | EACH | 1 | $965.00 | $850.00 | $965.00 |
| 30 | Inlet covers type HM (611.0627) | EACH | 4 | $1,415.00 | $1,100.00 | $1,415.00 |
| 31 | Manholes 4-FT diameter (611.2004) | EACH | 1 | $3,990.00 | $4,200.00 | $3,990.00 |
| 32 | Inlets 2X3-FT (611.3230) | EACH | 4 | $2,440.00 | $2,247.00 | $2,440.00 |
| 33 | Guardrail mow strip emulsified asphalt (614.0397) | SY | 400 | $21.27 | $20.00 | $27.50 |
| 34 | MGS guardrail 3 (614.2300) | LF | 612.50 | $28.50 | $30.00 | $28.50 |
| 35 | MGS guardrail terminal eat (614.2610) | EACH | 2 | $3,650.00 | $5,000.00 | $3,650.00 |
| 36 | Maintenance and repair of haul roads (project) 01. 1410-16-71 (618.0100) | EACH | 1 | $5,600.00 | $1.00 | $1.00 |
| 37 | Mobilization (619.1000) | EACH | 1 | $95,000 | $285,000 | $345,919 |
| 38 | Water (624.0100) | MGAL | 4.10 | $90.00 | $50.00 | $90.00 |
| 39 | Topsoil (625.0100) | SY | 1,223 | $9.50 | $8.00 | $9.50 |
| 40 | Erosion bales (628.1104) | EACH | 144 | $17.50 | $8.00 | $17.50 |
| 41 | Silt fence (628.1504) | LF | 417 | $3.00 | $3.00 | $3.00 |
| 42 | Silt fence maintenance (628.1520) | LF | 417 | $0.25 | $0.01 | $0.25 |
| 43 | Silt fence heavy duty (628.1530.S) | LF | 576 | $13.50 | $20.00 | $13.50 |
| 44 | Silt fence heavy duty maintenance (628.1535.S) | LF | 576 | $5.00 | $0.01 | $5.00 |
| 45 | Mobilizations erosion control (628.1905) | EACH | 3 | $250.00 | $500.00 | $250.00 |
| 46 | Mobilizations emergency erosion control (628.1910) | EACH | 4 | $250.00 | $1.00 | $250.00 |
| 47 | Erosion mat urban class I type B (628.2008) | SY | 1,223 | $1.80 | $3.00 | $1.80 |
| 48 | Rock bags (628.7570) | EACH | 36 | $17.50 | $20.00 | $17.50 |
| 49 | Seeding mixture no. 30 (630.0130) | LB | 55 | $12.00 | $10.00 | $12.00 |
| 50 | Seed water (630.0500) | MGAL | 28 | $75.00 | $10.00 | $75.00 |
| 51 | Markers culvert end (633.5200) | EACH | 1 | $75.00 | $100.00 | $75.00 |
| 52 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 3 | $115.00 | $150.00 | $115.00 |
| 53 | Foundation drilling (diameter) 01. 30-inch (636.0050.S) | LF | 1,971 | $30.25 | $80.00 | $5.00 |
| 54 | Signs type II reflective H (637.2210) | SF | 10 | $35.00 | $50.00 | $35.00 |
| 55 | Signs type II reflective F (637.2230) | SF | 16 | $35.00 | $50.00 | $35.00 |
| 56 | Removing signs type II (638.2602) | EACH | 2 | $50.00 | $50.00 | $50.00 |
| 57 | Removing small sign supports (638.3000) | EACH | 2 | $50.00 | $50.00 | $50.00 |
| 58 | Field office type B (642.5001) | EACH | 1 | $12,000 | $7,500.00 | $4,000.00 |
| 59 | Traffic control barricades type III (643.0420) | DAY | 1,168 | $0.88 | $1.05 | $0.50 |
| 60 | Traffic control warning lights type A (643.0705) | DAY | 2,336 | $0.19 | $0.16 | $0.15 |
| 61 | Traffic control signs (643.0900) | DAY | 7,811 | $0.50 | $0.70 | $0.15 |
| 62 | Traffic control signs PCMS (643.1050) | DAY | 14 | $50.00 | $35.00 | $75.00 |
| 63 | Traffic control (643.5000) | EACH | 1 | $7,568.00 | $15,582 | $14,725 |
| 64 | Geotextile type DF schedule B (645.0112) | SY | 640 | $6.00 | $5.00 | $6.00 |
| 65 | Geotextile type HR (645.0120) | SY | 26 | $20.00 | $10.00 | $20.00 |
| 66 | Marking line epoxy 6-inch (646.2020) | LF | 3,520 | $1.75 | $2.35 | $2.00 |
| 67 | Construction staking storm sewer (650.4000) | EACH | 5 | $85.00 | $85.00 | $85.00 |
| 68 | Construction staking base (650.5000) | LF | 876 | $1.24 | $1.24 | $1.24 |
| 69 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 738 | $1.24 | $1.24 | $1.24 |
| 70 | Construction staking pipe culverts (650.6000) | EACH | 1 | $150.00 | $150.00 | $150.00 |
| 71 | Construction staking structure layout (structure) 01. R-45-47 (650.6501) | EACH | 1 | $5,382.00 | $5,382.00 | $5,382.00 |
| 72 | Construction staking supplemental control (project) 01. 1410-16-71 (650.9911) | EACH | 1 | $433.96 | $433.96 | $433.96 |
| 73 | Construction staking slope stakes 01. 1410-16-71 (650.9920) | LF | 925 | $1.50 | $1.50 | $1.50 |
| 74 | Sawing asphalt (690.0150) | LF | 894 | $1.25 | $3.00 | $1.10 |
| 75 | Sawing concrete (690.0250) | LF | 3 | $50.00 | $3.00 | $2.50 |
| 76 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 450 | $5.00 | $5.00 | $5.00 |
| 77 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 1,500 | $5.00 | $5.00 | $5.00 |
| 78 | Special 01. construction staking right-of-way (SPV.0090) | LF | 600 | $7.69 | $7.69 | $7.69 |
| 79 | Special 01. timber lagging (SPV.0110) | MBM | 15.63 | $5,500.00 | $4,035.00 | $5,500.00 |
| 80 | Special 01. precast panels for soldier pile walls (SPV.0165) | SF | 5,396 | $34.50 | $32.50 | $42.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of September 9, 2025. Compiled by Mirage Metrics.