WisDOT contract 20250909025 bid tabulation
Stratford - Goodrich; Bridge Overlay B-37-0548 (STH 097, Marathon County Stratford - Goodrich). Let by Wisconsin DOT on September 9, 2025, Marathon. 4 bids received; low bid $772,900 by Janke General Contractors, Inc..
- Owner
- Wisconsin DOT
- Letting
- 09 SEP 2025
- Pay items
- 101
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Janke General Contractors, Inc. | $772,900 | Low |
| 2 | Lunda Construction Company | $1,000,563 | +29% |
| 3 | Zenith Tech., Inc. - Waukesha | $1,064,260 | +38% |
| 4 | Norcon Corporation | $1,159,386 | +50% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Janke General Contractors, Inc. | 2. Lunda Construction Company | 3. Zenith Tech., Inc. - Waukesha | 4. Norcon Corporation |
|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 6 | $560.00 | $3,059.00 | $1,500.00 | $3,059.00 |
| 2 | Grubbing (201.0205) | STA | 6 | $100.00 | $720.00 | $1,000.00 | $720.00 |
| 3 | Removing concrete pavement (204.0100) | SY | 143 | $35.00 | $38.35 | $15.50 | $38.35 |
| 4 | Removing curb & gutter (204.0150) | LF | 127 | $9.00 | $20.50 | $13.75 | $20.50 |
| 5 | Removing concrete sidewalk (204.0155) | SY | 11 | $45.00 | $26.50 | $14.25 | $26.50 |
| 6 | Removing guardrail (204.0165) | LF | 787 | $3.00 | $3.05 | $3.00 | $3.05 |
| 7 | Removing surface drains (204.0190) | EACH | 1 | $890.00 | $360.00 | $1,500.00 | $360.00 |
| 8 | Removing (item description) 01. removing apron endwalls (204.9060.S) | EACH | 1 | $595.00 | $360.00 | $500.00 | $360.00 |
| 9 | Excavation common (205.0100) | CY | 281 | $27.00 | $25.45 | $22.50 | $25.45 |
| 10 | Borrow (208.0100) | CY | 1,400 | $36.00 | $28.55 | $21.25 | $28.55 |
| 11 | Finishing roadway (project) 01. 9535-05-72 (213.0100) | EACH | 1 | $250.00 | $720.00 | $500.00 | $720.00 |
| 12 | Base aggregate dense 3/4-inch (305.0110) | TON | 59 | $50.00 | $36.95 | $33.50 | $36.95 |
| 13 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 427 | $30.00 | $30.05 | $20.95 | $30.05 |
| 14 | Concrete pavement 7-inch (415.0070) | SY | 18 | $262.00 | $131.31 | $131.31 | $147.00 |
| 15 | Concrete pavement approach slab (415.0410) | SY | 132 | $300.00 | $293.86 | $293.86 | $277.00 |
| 16 | Drilled tie bars (416.0610) | EACH | 83 | $16.00 | $16.03 | $16.03 | $14.00 |
| 17 | Drilled dowel bars (416.0620) | EACH | 27 | $21.00 | $20.71 | $20.71 | $19.00 |
| 18 | Asphaltic surface (465.0105) | TON | 81 | $195.30 | $195.30 | $195.30 | $312.00 |
| 19 | Concrete masonry bridges (502.0100) | CY | 5.30 | $2,735.00 | $2,000.00 | $2,500.00 | $2,850.00 |
| 20 | Expansion device (502.3101) | LF | 163 | $300.00 | $300.00 | $550.00 | $310.00 |
| 21 | Pigmented surface sealer reseal (502.3205) | SY | 129 | $13.00 | $8.00 | $35.00 | $21.00 |
| 22 | Pigmented surface sealer (502.3210) | SY | 10 | $10.00 | $5.00 | $20.00 | $21.00 |
| 23 | Adhesive anchors no. 5 bar (502.4205) | EACH | 78 | $30.00 | $5.00 | $35.00 | $29.00 |
| 24 | Bar steel reinforcement HS coated structures (505.0600) | LB | 5,750 | $2.80 | $3.50 | $3.50 | $3.35 |
| 25 | Preparation decks type 1 (509.0301) | SY | 10 | $375.00 | $175.00 | $400.00 | $215.00 |
| 26 | Preparation decks type 2 (509.0302) | SY | 5 | $450.00 | $150.00 | $500.00 | $280.00 |
| 27 | Sawing pavement deck preparation areas (509.0310.S) | LF | 100 | $9.00 | $5.00 | $15.00 | $6.00 |
| 28 | Joint repair (509.1000) | SY | 82 | $1,155.00 | $2,000.00 | $1,750.00 | $1,325.00 |
| 29 | Concrete surface repair (509.1500) | SF | 116 | $185.00 | $150.00 | $375.00 | $195.00 |
| 30 | Concrete masonry deck repair (509.2100.S) | CY | 35 | $1,030.00 | $750.00 | $2,500.00 | $1,350.00 |
| 31 | Polymer overlay (509.5100.S) | SY | 565 | $39.00 | $38.72 | $39.21 | $38.72 |
| 32 | Removing polymer overlay (structure) 01. B-37-548 (509.9015.S) | SY | 565 | $21.00 | $20.10 | $21.21 | $20.10 |
| 33 | Preparation and coating of top flanges (structure) 01. B-37-548 (517.0901.S) | EACH | 1 | $4,000.00 | $10,395 | $15,000 | $15,000 |
| 34 | Structure overcoating cleaning and priming (structure) 01. B-37-548 (517.3001.S) | EACH | 1 | $6,500.00 | $39,120 | $100,000 | $100,000 |
| 35 | Containment and collection of waste materials (structure) 01. B- 37-548 (517.4001.S) | EACH | 1 | $1,500.00 | $20,000 | $68,000 | $68,000 |
| 36 | Portable decontamination facility (517.6001.S) | EACH | 1 | $1,000.00 | $4,000.00 | $2,000.00 | $2,000.00 |
| 37 | Apron endwalls for culvert pipe 18- inch (520.1018) | EACH | 1 | $450.00 | $557.00 | $650.00 | $557.00 |
| 38 | Concrete collars for pipe (520.8000) | EACH | 1 | $750.00 | $1,102.00 | $900.00 | $1,102.00 |
| 39 | Culvert pipe reinforced concrete class III 18-inch (522.0118) | LF | 13 | $180.00 | $183.05 | $78.50 | $183.05 |
| 40 | Apron endwalls for culvert pipe reinforced concrete 18-inch (522.1018) | EACH | 1 | $1,500.00 | $1,997.00 | $1,850.00 | $1,997.00 |
| 41 | Culvert pipe corrugated polyethylene 18-inch (530.0118) | LF | 44 | $85.00 | $85.85 | $58.50 | $85.85 |
| 42 | Concrete curb & gutter 30-inch type A (601.0409) | LF | 57 | $70.00 | $57.65 | $57.65 | $54.00 |
| 43 | Concrete curb & gutter 4-inch sloped 36-inch type TBT (601.0588) | LF | 35 | $95.00 | $59.37 | $59.37 | $72.00 |
| 44 | Concrete curb & gutter 4-inch sloped 36-inch type TBTT (601.0590) | LF | 145 | $85.00 | $59.37 | $59.37 | $72.00 |
| 45 | Concrete sidewalk 5-inch (602.0410) | SF | 261 | $14.00 | $23.65 | $23.65 | $18.00 |
| 46 | Curb ramp detectable warning field natural patina (602.0515) | SF | 8 | $70.00 | $62.53 | $62.53 | $83.00 |
| 47 | Riprap medium (606.0200) | CY | 6 | $110.00 | $97.95 | $115.00 | $97.95 |
| 48 | Riprap heavy (606.0300) | CY | 105 | $200.00 | $75.00 | $95.50 | $337.00 |
| 49 | Inlet covers type V (611.0654) | EACH | 2 | $1,200.00 | $1,263.00 | $1,895.00 | $1,263.00 |
| 50 | Inlets 2X2.5-FT (611.3225) | EACH | 1 | $3,200.00 | $2,568.00 | $2,250.00 | $2,568.00 |
| 51 | Adjusting inlet covers (611.8115) | EACH | 1 | $550.00 | $895.00 | $975.00 | $895.00 |
| 52 | Pipe underdrain 6-inch (612.0106) | LF | 230 | $20.00 | $12.50 | $6.15 | $28.00 |
| 53 | Anchor assemblies for steel plate beam guard (614.0150) | EACH | 2 | $250.00 | $200.00 | $425.00 | $330.00 |
| 54 | Guardrail mow strip asphalt (614.0396) | SY | 67 | $75.00 | $136.50 | $121.80 | $97.00 |
| 55 | MGS guardrail 3 (614.2300) | LF | 512.50 | $29.60 | $25.05 | $29.60 | $25.05 |
| 56 | MGS guardrail short radius (614.2350) | LF | 53.80 | $41.00 | $32.45 | $41.00 | $32.45 |
| 57 | MGS thrie beam transition (614.2500) | LF | 118.20 | $96.00 | $95.30 | $96.00 | $95.30 |
| 58 | MGS guardrail terminal eat (614.2610) | EACH | 2 | $4,060.00 | $3,600.00 | $4,060.00 | $3,600.00 |
| 59 | MGS guardrail short radius terminal (614.2630) | EACH | 1 | $2,100.00 | $2,726.00 | $2,100.00 | $2,726.00 |
| 60 | Maintenance and repair of haul roads (project) 01. 9535-05-72 (618.0100) | EACH | 1 | $300.00 | $0.01 | $1,000.00 | $2,500.00 |
| 61 | Mobilization (619.1000) | EACH | 1 | $69,071 | $258,849 | $80,000 | $175,600 |
| 62 | Water (624.0100) | MGAL | 7.90 | $27.00 | $1.00 | $40.00 | $1.00 |
| 63 | Topsoil (625.0100) | SY | 3,648 | $4.00 | $3.95 | $6.35 | $3.95 |
| 64 | Silt fence (628.1504) | LF | 980 | $2.40 | $2.35 | $2.40 | $2.35 |
| 65 | Silt fence maintenance (628.1520) | LF | 980 | $0.02 | $0.01 | $0.02 | $0.01 |
| 66 | Mobilizations erosion control (628.1905) | EACH | 5 | $200.00 | $500.00 | $400.00 | $500.00 |
| 67 | Mobilizations emergency erosion control (628.1910) | EACH | 3 | $350.00 | $200.00 | $350.00 | $200.00 |
| 68 | Erosion mat urban class I type B (628.2008) | SY | 3,648 | $2.40 | $1.80 | $2.40 | $1.80 |
| 69 | Turbidity barriers (628.6005) | SY | 136 | $45.00 | $51.50 | $45.00 | $51.50 |
| 70 | Inlet protection type C (628.7015) | EACH | 4 | $79.00 | $73.00 | $79.00 | $73.00 |
| 71 | Temporary ditch checks (628.7504) | LF | 80 | $8.95 | $7.30 | $8.95 | $7.30 |
| 72 | Rock bags (628.7570) | EACH | 25 | $14.00 | $17.50 | $14.00 | $17.50 |
| 73 | Fertilizer type B (629.0210) | CWT | 2.30 | $110.00 | $182.25 | $110.00 | $182.25 |
| 74 | Seeding mixture no. 30 (630.0130) | LB | 164.30 | $8.80 | $13.05 | $8.80 | $13.05 |
| 75 | Seed water (630.0500) | MGAL | 84 | $1.00 | $0.50 | $1.00 | $0.50 |
| 76 | Moving signs type II (638.2102) | EACH | 7 | $195.00 | $110.00 | $195.00 | $110.00 |
| 77 | Traffic control barricades type III (643.0420) | DAY | 1,377 | $1.20 | $0.40 | $0.40 | $0.40 |
| 78 | Traffic control warning lights type A (643.0705) | DAY | 2,106 | $0.40 | $0.10 | $0.10 | $0.10 |
| 79 | Traffic control signs (643.0900) | DAY | 14,742 | $1.20 | $0.40 | $0.40 | $0.40 |
| 80 | Traffic control covering signs type II (643.0920) | EACH | 4 | $20.00 | $20.00 | $20.00 | $20.00 |
| 81 | Traffic control signs fixed message (643.1000) | SF | 70 | $11.10 | $11.10 | $11.10 | $11.10 |
| 82 | Traffic control (643.5000) | EACH | 1 | $1,840.00 | $1,840.00 | $1,840.00 | $1,840.00 |
| 83 | Geotextile type HR (645.0120) | SY | 492 | $4.56 | $7.00 | $6.15 | $29.00 |
| 84 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 3,116 | $3.30 | $3.30 | $2.50 | $3.30 |
| 85 | Construction staking storm sewer (650.4000) | EACH | 1 | $200.00 | $200.00 | $200.00 | $200.00 |
| 86 | Construction staking subgrade (650.4500) | LF | 642 | $0.01 | $0.01 | $0.70 | $1.00 |
| 87 | Construction staking base (650.5000) | LF | 642 | $1.40 | $0.70 | $0.70 | $0.70 |
| 88 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 181 | $0.97 | $0.97 | $0.97 | $0.97 |
| 89 | Construction staking pipe culverts (650.6000) | EACH | 1 | $150.00 | $150.00 | $150.00 | $150.00 |
| 90 | Construction staking curb ramps (650.9000) | EACH | 1 | $200.00 | $200.00 | $200.00 | $200.00 |
| 91 | Construction staking sidewalk (project) 01. 9535-05-72 (650.9500) | EACH | 1 | $200.00 | $200.00 | $200.00 | $200.00 |
| 92 | Construction staking supplemental control (project) 01. 9535-05-72 (650.9911) | EACH | 1 | $2,025.00 | $2,025.00 | $2,025.00 | $2,025.00 |
| 93 | Construction staking slope stakes (650.9920) | LF | 642 | $1.32 | $1.32 | $1.32 | $1.32 |
| 94 | Sawing asphalt (690.0150) | LF | 783 | $1.80 | $1.80 | $1.80 | $1.80 |
| 95 | Sawing concrete (690.0250) | LF | 166 | $2.35 | $2.35 | $2.35 | $2.35 |
| 96 | Incentive strength concrete structures (715.0502) | DOL | 500 | $1.00 | $1.00 | $1.00 | $1.00 |
| 97 | Incentive compressive strength concrete pavement (715.0720) | DOL | 500 | $1.00 | $1.00 | $1.00 | $1.00 |
| 98 | Special 01. partially grouted riprap (SPV.0035) | CY | 104 | $368.39 | $250.00 | $150.00 | $417.00 |
| 99 | Special 01. temporary construction access (SPV.0060) | EACH | 1 | $33,301 | $0.01 | $20,000 | $67,500 |
| 100 | Special 02. temporary emergency action plan (SPV.0060) | EACH | 1 | $750.00 | $0.01 | $10,000 | $6,250.00 |
| 101 | Special 03. emergency response (SPV.0060) | EACH | 1 | $1.00 | $0.01 | $5,000.00 | $7,770.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of September 9, 2025. Compiled by Mirage Metrics.