WisDOT contract 20251111016 bid tabulation
Lima - Sheboygan Falls; Onion River Bridge (CTH OO, Sheboygan County Lima - Sheboygan Falls). Let by Wisconsin DOT on November 11, 2025, Sheboygan. 5 bids received; low bid $1,397,256 by Lunda Construction Company.
- Owner
- Wisconsin DOT
- Letting
- 11 NOV 2025
- Pay items
- 76
- Data through
- 10 NOV 2026
4 of the 5 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Lunda Construction Company | $1,397,256 | Low |
| 2 | Radtke Contractors Inc. | $1,471,377 | +5.0% |
| 4 | Sheet Piling Services LLC | $1,576,219 | +13% |
| 5 | Kraemer North America, LLC | $1,757,696 | +26% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Lunda Construction Company | 2. Radtke Contractors Inc. | 3. Sheet Piling Services LLC | 4. Kraemer North America, LLC |
|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 4 | $2,995.00 | $2,995.00 | $2,995.00 | $2,995.00 |
| 2 | Grubbing (201.0205) | STA | 4 | $238.44 | $238.44 | $238.44 | $238.44 |
| 3 | Abatement of asbestos containing material (structure) 01. P-59-069 (203.0211.S) | EACH | 1 | $8,440.00 | $8,440.00 | $8,440.00 | $8,440.00 |
| 4 | Removing structure over waterway remove debris (structure) 01. P-59- 069 (203.0250) | EACH | 1 | $350,000 | $199,816 | $195,000 | $300,000 |
| 5 | Removing asphaltic surface (204.0110) | SY | 620 | $4.00 | $2.90 | $4.00 | $2.90 |
| 6 | Removing delineators and markers (204.0180) | EACH | 3 | $40.00 | $50.00 | $40.00 | $40.00 |
| 7 | Excavation common (205.0100) | CY | 500 | $22.00 | $0.01 | $22.00 | $0.01 |
| 8 | Excavation for structures bridges (structure) 01. B-59-330 (206.1001) | EACH | 1 | $40,000 | $88,755 | $95,000 | $136,000 |
| 9 | Borrow (208.0100) | CY | 630 | $34.00 | $44.82 | $34.00 | $44.82 |
| 10 | Backfill structure type A (210.1500) | TON | 250 | $28.00 | $35.59 | $28.00 | $49.70 |
| 11 | Prepare foundation for asphaltic paving (project) 01. 4273-00-71 (211.0101) | EACH | 1 | $5,970.00 | $5,970.00 | $5,970.00 | $5,970.00 |
| 12 | Finishing roadway (project) 01. 4273-00-71 (213.0100) | EACH | 1 | $1,500.00 | $1,500.00 | $1,000.00 | $1,500.00 |
| 13 | Base aggregate dense 3/4-inch (305.0110) | TON | 130 | $26.00 | $85.00 | $26.00 | $85.00 |
| 14 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 1,280 | $22.00 | $26.25 | $22.00 | $26.25 |
| 15 | Tack coat (455.0605) | GAL | 60 | $12.30 | $12.30 | $12.30 | $12.30 |
| 16 | Asphaltic surface (465.0105) | TON | 298 | $109.50 | $109.50 | $109.50 | $109.50 |
| 17 | Concrete masonry bridges (502.0100) | CY | 593 | $550.00 | $615.59 | $1,025.00 | $800.00 |
| 18 | Protective surface treatment (502.3200) | SY | 585 | $2.00 | $3.60 | $5.00 | $4.00 |
| 19 | Pigmented surface sealer (502.3210) | SY | 210 | $5.00 | $17.47 | $8.00 | $14.00 |
| 20 | Bar steel reinforcement HS structures (505.0400) | LB | 7,190 | $0.93 | $1.30 | $1.42 | $1.30 |
| 21 | Bar steel reinforcement HS coated structures (505.0600) | LB | 77,920 | $1.04 | $1.28 | $1.34 | $1.35 |
| 22 | Rubberized membrane waterproofing (516.0500) | SY | 12 | $25.00 | $77.21 | $25.00 | $12.00 |
| 23 | Piling cip concrete 10 3/4 X 0.25- inch (550.2104) | LF | 510 | $40.21 | $36.71 | $62.00 | $65.00 |
| 24 | Piling cip concrete 12 3/4 X 0.375- inch (550.2126) | LF | 1,170 | $58.48 | $47.19 | $70.00 | $75.00 |
| 25 | Concrete curb & gutter 4-inch sloped 36-inch type TBT (601.0588) | LF | 126 | $70.00 | $65.00 | $70.00 | $65.00 |
| 26 | Concrete surface drains (602.3010) | CY | 2 | $800.00 | $2,500.00 | $800.00 | $2,500.00 |
| 27 | Riprap medium (606.0200) | CY | 8 | $96.00 | $185.00 | $96.00 | $185.00 |
| 28 | Riprap heavy (606.0300) | CY | 185 | $98.00 | $95.72 | $98.00 | $123.00 |
| 29 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 150 | $4.50 | $4.20 | $4.50 | $6.50 |
| 30 | Anchor assemblies for steel plate beam guard (614.0150) | EACH | 4 | $250.00 | $376.25 | $275.00 | $31.11 |
| 31 | MGS thrie beam transition (614.2500) | LF | 160 | $92.00 | $105.00 | $92.00 | $92.00 |
| 32 | MGS guardrail terminal eat (614.2610) | EACH | 4 | $3,750.00 | $4,200.00 | $3,750.00 | $3,750.00 |
| 33 | Mobilization (619.1000) | EACH | 1 | $107,975 | $223,343 | $119,853 | $174,650 |
| 34 | Water (624.0100) | MGAL | 21 | $95.00 | $35.00 | $95.00 | $40.00 |
| 35 | Salvaged topsoil (625.0500) | SY | 1,650 | $2.50 | $6.70 | $2.50 | $6.70 |
| 36 | Mulching (627.0200) | SY | 1,650 | $0.30 | $0.55 | $0.30 | $0.30 |
| 37 | Silt fence (628.1504) | LF | 940 | $2.25 | $2.25 | $2.25 | $2.25 |
| 38 | Silt fence maintenance (628.1520) | LF | 1,880 | $0.01 | $0.01 | $0.01 | $0.01 |
| 39 | Mobilizations erosion control (628.1905) | EACH | 6 | $200.00 | $250.00 | $200.00 | $200.00 |
| 40 | Mobilizations emergency erosion control (628.1910) | EACH | 5 | $100.00 | $250.00 | $100.00 | $100.00 |
| 41 | Turbidity barriers (628.6005) | SY | 300 | $48.00 | $40.00 | $48.00 | $48.00 |
| 42 | Temporary ditch checks (628.7504) | LF | 32 | $8.75 | $9.95 | $8.75 | $8.75 |
| 43 | Rock bags (628.7570) | EACH | 21 | $17.50 | $20.00 | $17.50 | $17.50 |
| 44 | Fertilizer type B (629.0210) | CWT | 2 | $90.00 | $125.00 | $90.00 | $90.00 |
| 45 | Seeding mixture no. 20 (630.0120) | LB | 90 | $8.45 | $15.00 | $8.45 | $8.45 |
| 46 | Seeding mixture no. 60 (630.0160) | LB | 2 | $25.00 | $250.00 | $25.00 | $25.00 |
| 47 | Seeding mixture no. 70 (630.0170) | LB | 1 | $100.00 | $400.00 | $100.00 | $100.00 |
| 48 | Seeding temporary (630.0200) | LB | 52 | $8.00 | $10.00 | $8.00 | $8.00 |
| 49 | Seeding borrow pit (630.0300) | LB | 17 | $8.45 | $15.00 | $8.45 | $8.45 |
| 50 | Seed water (630.0500) | MGAL | 64 | $65.00 | $25.00 | $65.00 | $65.00 |
| 51 | Markers row (633.5100) | EACH | 7 | $55.00 | $85.00 | $55.00 | $55.00 |
| 52 | Posts wood 4X6-inch X 12-FT (634.0612) | EACH | 6 | $75.00 | $150.00 | $75.00 | $75.00 |
| 53 | Signs type II reflective F (637.2230) | SF | 32.25 | $28.00 | $35.00 | $28.00 | $28.00 |
| 54 | Removing signs type II (638.2602) | EACH | 12 | $30.00 | $35.00 | $30.00 | $30.00 |
| 55 | Removing small sign supports (638.3000) | EACH | 11 | $30.00 | $35.00 | $30.00 | $30.00 |
| 56 | Field office type B (642.5001) | EACH | 1 | $3,000.00 | $2,629.04 | $1,500.00 | $8,000.00 |
| 57 | Traffic control barricades type III (643.0420) | DAY | 2,215 | $0.72 | $0.75 | $1.00 | $0.72 |
| 58 | Traffic control warning lights type A (643.0705) | DAY | 3,445 | $0.22 | $0.10 | $0.10 | $0.22 |
| 59 | Traffic control signs (643.0900) | DAY | 24,970 | $0.33 | $0.25 | $0.10 | $0.33 |
| 60 | Traffic control covering signs type II (643.0920) | EACH | 18 | $44.88 | $75.00 | $25.00 | $44.88 |
| 61 | Traffic control signs PCMS (643.1050) | DAY | 14 | $73.02 | $85.00 | $99.99 | $73.02 |
| 62 | Traffic control (643.5000) | EACH | 1 | $8,385.10 | $1,750.00 | $5,000.00 | $15,000 |
| 63 | Geotextile type DF schedule A (645.0111) | SY | 70 | $5.00 | $4.81 | $5.00 | $5.00 |
| 64 | Geotextile type HR (645.0120) | SY | 310 | $7.00 | $5.26 | $7.00 | $5.80 |
| 65 | Marking line epoxy 4-inch (646.1020) | LF | 1,710 | $3.50 | $3.50 | $3.50 | $3.50 |
| 66 | Construction staking subgrade (650.4500) | LF | 355 | $0.01 | $3.00 | $8.35 | $0.01 |
| 67 | Construction staking base (650.5000) | LF | 355 | $1.32 | $3.00 | $1.32 | $1.32 |
| 68 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 126 | $0.71 | $4.00 | $0.71 | $0.71 |
| 69 | Construction staking structure layout (structure) 01. B-59-330 (650.6501) | EACH | 1 | $6,613.52 | $3,500.00 | $6,613.52 | $6,613.52 |
| 70 | Construction staking supplemental control (project) 01. 4273-00-71 (650.9911) | EACH | 1 | $460.39 | $1,800.00 | $460.39 | $460.39 |
| 71 | Construction staking slope stakes (650.9920) | LF | 355 | $0.93 | $3.00 | $0.93 | $0.93 |
| 72 | Sawing asphalt (690.0150) | LF | 56 | $2.95 | $2.95 | $2.95 | $2.95 |
| 73 | Incentive strength concrete structures (715.0502) | DOL | 3,570 | $1.00 | $1.00 | $1.00 | $1.00 |
| 74 | Installing and maintaining bird deterrent system (station) 01. 12+85 (999.2000.S) | EACH | 1 | $2,875.00 | $500.00 | $0.01 | $0.01 |
| 75 | Special 01. parapet concrete type 'TX' (SPV.0090) | LF | 385 | $300.00 | $291.90 | $150.00 | $300.00 |
| 76 | Special 01. select crushed material for travel corridor (SPV.0195) | TON | 45 | $30.00 | $72.80 | $30.00 | $85.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of November 11, 2025. Compiled by Mirage Metrics.