WisDOT contract 20251111021 bid tabulation
Marinette - Wausaukee; STH 64 - USH 141 (STH 180, Marinette County Marinette - Wausaukee). Let by Wisconsin DOT on November 11, 2025, Marinette. 4 bids received; low bid $3,742,494 by Relyco Plus, LLC.
- Owner
- Wisconsin DOT
- Letting
- 11 NOV 2025
- Pay items
- 115
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Relyco Plus, LLC | $3,742,494 | Low |
| 2 | Highway Landscapers, Inc. | $3,990,173 | +7.0% |
| 3 | James Peterson Sons, Inc. | $4,213,784 | +13% |
| 4 | Musson Bros., Inc. | $4,529,198 | +21% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Relyco Plus, LLC | 2. Highway Landscapers, Inc. | 3. James Peterson Sons, Inc. | 4. Musson Bros., Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 19 | $800.00 | $850.00 | $1,204.47 | $2,335.78 |
| 2 | Grubbing (201.0205) | STA | 19 | $400.00 | $450.00 | $445.86 | $996.84 |
| 3 | Removing small pipe culverts (203.0100) | EACH | 32 | $593.13 | $500.00 | $810.00 | $1,332.74 |
| 4 | Removing structure (structure) 01. C-38-117 (203.0220) | EACH | 1 | $6,850.00 | $10,000 | $4,620.00 | $26,336 |
| 5 | Removing structure (structure) 02. C-38-639 (203.0220) | EACH | 1 | $10,895 | $12,500 | $9,320.00 | $16,133 |
| 6 | Removing structure (structure) 03. C-38-111 (203.0220) | EACH | 1 | $4,735.00 | $8,500.00 | $1,664.00 | $6,703.09 |
| 7 | Removing structure (structure) 04. C-38-121 (203.0220) | EACH | 1 | $5,540.00 | $8,500.00 | $1,664.00 | $9,384.33 |
| 8 | Removing structure (structure) 05. station 804+94, CPRC 66-inch (203.0220) | EACH | 1 | $3,180.00 | $6,500.00 | $5,976.00 | $7,075.81 |
| 9 | Removing structure (structure) 06. C-38-113 (203.0220) | EACH | 1 | $2,065.00 | $6,500.00 | $1,663.00 | $9,384.33 |
| 10 | Removing structure (structure) 07. C-38-115 (203.0220) | EACH | 1 | $2,770.00 | $8,500.00 | $1,663.00 | $6,703.09 |
| 11 | Removing structure (structure) 08. C-38-116 (203.0220) | EACH | 1 | $4,425.00 | $8,500.00 | $1,663.00 | $10,725 |
| 12 | Removing structure (structure) 09. C-38-124 (203.0220) | EACH | 1 | $4,735.00 | $8,500.00 | $1,663.00 | $9,384.33 |
| 13 | Removing guardrail (204.0165) | LF | 448 | $3.00 | $5.00 | $4.00 | $3.00 |
| 14 | Removing delineators and markers (204.0180) | EACH | 46 | $30.00 | $50.00 | $15.00 | $30.00 |
| 15 | Excavation common (205.0100) | CY | 10,814 | $19.45 | $22.50 | $16.00 | $23.08 |
| 16 | Excavation for structures culverts (structure) 01. C-38-128 (206.2001) | EACH | 1 | $69,000 | $56,600 | $193,548 | $75,530 |
| 17 | Cofferdams (structure) 01. station 551+02, CPRC 78-inch (206.5001) | EACH | 1 | $10,975 | $15,000 | $1,503.00 | $3,930.51 |
| 18 | Cofferdams (structure) 02. station 668+12, CPRC 108-inch (206.5001) | EACH | 1 | $14,741 | $15,000 | $2,902.74 | $3,930.51 |
| 19 | Cofferdams (structure) 03. station 903+83, CPRC 66-inch (206.5001) | EACH | 1 | $12,130 | $15,000 | $1,503.00 | $3,930.51 |
| 20 | Cofferdams (structure) 04. station 1010+52, cprche 58X91-inch (206.5001) | EACH | 1 | $12,708 | $15,000 | $1,503.00 | $1,965.26 |
| 21 | Cofferdams (structure) 05. station 1176+47, cprche 63X98-inch (206.5001) | EACH | 1 | $12,708 | $15,000 | $1,503.00 | $3,930.51 |
| 22 | Cofferdams (structure) 06. station 1524+58, CPRC 96-inch (206.5001) | EACH | 1 | $29,266 | $40,000 | $27,266 | $19,653 |
| 23 | Borrow (208.0100) | CY | 504 | $0.01 | $1.00 | $18.80 | $1.00 |
| 24 | Backfill structure type B (210.2500) | TON | 1,260 | $21.39 | $28.00 | $21.00 | $29.62 |
| 25 | Finishing roadway (project) 01. 9670-16-71 (213.0100) | EACH | 1 | $5,000.00 | $1,500.00 | $5,000.00 | $100.00 |
| 26 | Base aggregate dense 3/4-inch (305.0110) | TON | 1,100 | $33.70 | $34.00 | $36.44 | $46.71 |
| 27 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 5,210 | $12.74 | $22.80 | $18.43 | $42.04 |
| 28 | Base aggregate dense 3-inch (305.0130) | TON | 989 | $25.57 | $28.00 | $23.91 | $21.01 |
| 29 | HMA cold weather paving (450.4000) | TON | 3,441 | $3.25 | $3.25 | $3.25 | $3.25 |
| 30 | Tack coat (455.0605) | GAL | 1,264 | $4.20 | $4.20 | $4.20 | $4.20 |
| 31 | Incentive density HMA pavement (460.2000) | DOL | 3,160 | $1.00 | $1.00 | $1.00 | $1.00 |
| 32 | HMA pavement 4 LT 58-28 S (460.5224) | TON | 4,935 | $168.40 | $168.40 | $214.75 | $168.40 |
| 33 | Asphaltic rumble strips, shoulder (465.0520) | LF | 1,654 | $8.60 | $8.60 | $8.60 | $8.60 |
| 34 | Asphaltic rumble strips, centerline (465.0560) | LF | 883 | $9.30 | $9.30 | $9.30 | $9.30 |
| 35 | Concrete masonry culverts (504.0100) | CY | 171 | $772.00 | $1,080.00 | $812.74 | $758.00 |
| 36 | Concrete masonry endwalls (504.0900) | CY | 60 | $1,685.00 | $2,887.00 | $1,648.75 | $1,450.00 |
| 37 | Bar steel reinforcement HS structures (505.0400) | LB | 25,440 | $1.12 | $4.00 | $1.12 | $1.12 |
| 38 | Bar steel reinforcement HS coated structures (505.0600) | LB | 2,200 | $1.23 | $4.00 | $1.23 | $1.23 |
| 39 | Rubberized membrane waterproofing (516.0500) | SY | 29 | $48.00 | $50.00 | $48.00 | $48.00 |
| 40 | Apron endwalls for culvert pipe 24- inch (520.1024) | EACH | 26 | $606.94 | $530.00 | $443.37 | $754.95 |
| 41 | Apron endwalls for culvert pipe 30- inch (520.1030) | EACH | 8 | $949.86 | $750.00 | $768.01 | $1,227.26 |
| 42 | Apron endwalls for culvert pipe 36- inch (520.1036) | EACH | 5 | $1,192.99 | $1,100.00 | $1,064.21 | $1,564.17 |
| 43 | Culvert pipe class III-A non-metal 24-inch (520.3424) | LF | 838 | $142.02 | $113.00 | $141.12 | $168.13 |
| 44 | Culvert pipe class III-A non-metal 30-inch (520.3430) | LF | 270 | $168.75 | $142.00 | $162.49 | $187.78 |
| 45 | Culvert pipe class III-A non-metal 36-inch (520.3436) | LF | 286 | $183.28 | $185.00 | $188.72 | $203.94 |
| 46 | Apron endwalls for culvert pipe sloped cross drains steel 36-inch 4 to 1 (521.0336) | EACH | 5 | $3,796.55 | $4,615.00 | $3,626.29 | $4,893.95 |
| 47 | Culvert pipe reinforced concrete class III 48-inch (522.0148) | LF | 128 | $380.15 | $311.31 | $340.71 | $382.49 |
| 48 | Culvert pipe reinforced concrete class III 66-inch (522.0166) | LF | 96 | $438.26 | $428.24 | $661.78 | $680.27 |
| 49 | Culvert pipe reinforced concrete class III 72-inch (522.0172) | LF | 120 | $536.71 | $583.95 | $794.57 | $948.40 |
| 50 | Culvert pipe reinforced concrete class III 78-inch (522.0178) | LF | 120 | $777.90 | $698.94 | $989.89 | $1,179.15 |
| 51 | Culvert pipe reinforced concrete class III 96-inch (522.0196) | LF | 96 | $884.97 | $817.10 | $1,248.40 | $1,400.45 |
| 52 | Culvert pipe reinforced concrete class III 108-inch (522.0208) | LF | 108 | $1,426.18 | $1,337.76 | $1,793.18 | $2,150.79 |
| 53 | Culvert pipe reinforced concrete class IV 24-inch (522.0424) | LF | 264 | $155.73 | $142.10 | $188.58 | $210.98 |
| 54 | Culvert pipe reinforced concrete class IV 30-inch (522.0430) | LF | 288 | $182.66 | $178.67 | $221.28 | $233.75 |
| 55 | Culvert pipe reinforced concrete class IV 36-inch (522.0436) | LF | 104 | $241.15 | $217.36 | $259.88 | $308.07 |
| 56 | Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024) | EACH | 10 | $1,765.46 | $1,473.75 | $1,646.21 | $2,168.72 |
| 57 | Apron endwalls for culvert pipe reinforced concrete 30-inch (522.1030) | EACH | 10 | $2,165.75 | $1,700.00 | $1,884.00 | $2,504.37 |
| 58 | Apron endwalls for culvert pipe reinforced concrete 48-inch (522.1048) | EACH | 4 | $3,526.15 | $3,189.00 | $3,364.90 | $4,593.44 |
| 59 | Apron endwalls for culvert pipe reinforced concrete 66-inch (522.1066) | EACH | 2 | $5,042.65 | $4,991.50 | $5,632.40 | $6,464.20 |
| 60 | Apron endwalls for culvert pipe reinforced concrete 72-inch (522.1072) | EACH | 2 | $7,584.65 | $5,311.50 | $6,573.15 | $7,088.10 |
| 61 | Culvert pipe reinforced concrete horizontal elliptical class HE-III 58X91-inch (522.2358) | LF | 64 | $815.97 | $730.59 | $914.15 | $1,065.35 |
| 62 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 58X91-inch (522.2658) | EACH | 4 | $6,993.03 | $7,250.00 | $8,681.31 | $9,386.53 |
| 63 | Riprap medium (606.0200) | CY | 150 | $70.00 | $125.00 | $77.66 | $193.44 |
| 64 | Riprap heavy (606.0300) | CY | 61 | $70.00 | $125.00 | $77.66 | $115.52 |
| 65 | MGS guardrail 3 (614.2300) | LF | 325 | $27.00 | $32.00 | $32.00 | $27.00 |
| 66 | MGS guardrail terminal eat (614.2610) | EACH | 4 | $3,433.00 | $5,100.00 | $5,100.00 | $3,433.00 |
| 67 | Maintenance and repair of haul roads (project) 01. 9670-16-71 (618.0100) | EACH | 1 | $0.01 | $500.00 | $1.00 | $1.00 |
| 68 | Mobilization (619.1000) | EACH | 1 | $417,000 | $209,680 | $239,663 | $446,044 |
| 69 | Water (624.0100) | MGAL | 88 | $0.01 | $50.00 | $50.00 | $32.60 |
| 70 | Salvaged topsoil (625.0500) | SY | 12,800 | $2.74 | $5.00 | $5.31 | $1.36 |
| 71 | Mulching (627.0200) | SY | 2,550 | $0.50 | $1.30 | $1.30 | $0.50 |
| 72 | Silt fence (628.1504) | LF | 9,930 | $1.70 | $2.00 | $2.00 | $1.70 |
| 73 | Silt fence maintenance (628.1520) | LF | 9,930 | $0.03 | $0.01 | $0.01 | $0.03 |
| 74 | Mobilizations erosion control (628.1905) | EACH | 32 | $303.00 | $1.00 | $1.00 | $303.00 |
| 75 | Mobilizations emergency erosion control (628.1910) | EACH | 9 | $413.00 | $1.00 | $1.00 | $413.00 |
| 76 | Erosion mat urban class I type A (628.2006) | SY | 12,800 | $1.77 | $3.50 | $3.50 | $1.77 |
| 77 | Turbidity barriers (628.6005) | SY | 50 | $52.00 | $80.00 | $80.00 | $52.00 |
| 78 | Temporary ditch checks (628.7504) | LF | 350 | $8.00 | $9.00 | $9.00 | $8.00 |
| 79 | Culvert pipe checks (628.7555) | EACH | 210 | $20.00 | $11.00 | $11.00 | $20.00 |
| 80 | Rock bags (628.7570) | EACH | 320 | $6.00 | $11.00 | $11.00 | $6.00 |
| 81 | Fertilizer type B (629.0210) | CWT | 5 | $100.00 | $150.00 | $150.00 | $100.00 |
| 82 | Seeding mixture no. 30 (630.0130) | LB | 760 | $7.13 | $8.00 | $8.00 | $7.13 |
| 83 | Seeding temporary (630.0200) | LB | 70 | $5.33 | $5.00 | $5.00 | $5.33 |
| 84 | Seed water (630.0500) | MGAL | 380 | $1.03 | $1.00 | $1.00 | $1.03 |
| 85 | Markers culvert end (633.5200) | EACH | 80 | $65.00 | $70.00 | $70.00 | $65.00 |
| 86 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 7 | $95.00 | $175.00 | $175.00 | $95.00 |
| 87 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 2 | $98.00 | $200.00 | $200.00 | $98.00 |
| 88 | Moving signs type II (638.2102) | EACH | 8 | $150.00 | $100.00 | $100.00 | $150.00 |
| 89 | Removing small sign supports (638.3000) | EACH | 9 | $25.00 | $50.00 | $50.00 | $25.00 |
| 90 | Field office type B (642.5001) | EACH | 1 | $9,000.00 | $15,000 | $9,000.00 | $15,000 |
| 91 | Traffic control drums (643.0300) | DAY | 210 | $1.54 | $1.54 | $1.54 | $1.54 |
| 92 | Traffic control barricades type III (643.0420) | DAY | 14,330 | $0.47 | $0.47 | $0.47 | $0.47 |
| 93 | Traffic control warning lights type A (643.0705) | DAY | 27,436 | $0.15 | $0.15 | $0.15 | $0.15 |
| 94 | Traffic control signs (643.0900) | DAY | 28,375 | $0.44 | $0.44 | $0.44 | $0.44 |
| 95 | Traffic control covering signs type II (643.0920) | EACH | 18 | $87.36 | $87.36 | $87.36 | $87.36 |
| 96 | Traffic control signs fixed message (643.1000) | SF | 96 | $22.62 | $22.62 | $22.62 | $22.62 |
| 97 | Traffic control signs PCMS (643.1050) | DAY | 28 | $68.79 | $68.79 | $68.79 | $68.79 |
| 98 | Traffic control (643.5000) | EACH | 1 | $36,801 | $36,801 | $36,801 | $36,801 |
| 99 | Geotextile type C (645.0105) | SY | 444 | $3.50 | $6.00 | $12.29 | $5.55 |
| 100 | Geotextile type HR (645.0120) | SY | 604 | $3.50 | $6.00 | $8.31 | $10.18 |
| 101 | Marking line epoxy 6-inch (646.2020) | LF | 10,140 | $2.20 | $2.20 | $2.20 | $2.20 |
| 102 | Cold weather marking epoxy 6-inch (646.6466) | LF | 6,837 | $0.50 | $0.50 | $0.50 | $0.50 |
| 103 | Construction staking subgrade (650.4500) | LF | 3,579 | $0.01 | $0.01 | $0.76 | $0.01 |
| 104 | Construction staking base (650.5000) | LF | 3,579 | $0.01 | $0.01 | $0.96 | $0.01 |
| 105 | Construction staking pipe culverts (650.6000) | EACH | 41 | $135.93 | $200.00 | $227.25 | $200.00 |
| 106 | Construction staking structure layout (structure) 01. C-38-128 (650.6501) | EACH | 1 | $3,460.14 | $1,677.00 | $1,212.00 | $1,677.00 |
| 107 | Construction staking supplemental control (project) 01. 9670-16-71 (650.9911) | EACH | 1 | $460.39 | $10.00 | $1,212.00 | $10.00 |
| 108 | Construction staking slope stakes (650.9920) | LF | 4,074 | $0.01 | $0.01 | $1.52 | $0.01 |
| 109 | Sawing asphalt (690.0150) | LF | 3,161 | $2.00 | $4.00 | $3.00 | $2.25 |
| 110 | Incentive strength concrete structures (715.0502) | DOL | 1,026 | $1.00 | $1.00 | $1.00 | $1.00 |
| 111 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,400 | $5.00 | $5.00 | $5.00 | $5.00 |
| 112 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 2,100 | $5.00 | $5.00 | $5.00 | $5.00 |
| 113 | Special 01. foundation backfill (SPV.0035) | CY | 7,120 | $22.29 | $39.00 | $33.47 | $34.50 |
| 114 | Special 01. apron endwalls for culvert pipe reinforced concrete 78-inch (SPV.0060) | EACH | 2 | $9,693.75 | $8,750.00 | $9,689.25 | $9,743.46 |
| 115 | Special 01. culvert pipe reinforced concrete horizontal elliptical class HE-IV 58X91-in (SPV.0090) | LF | 64 | $926.76 | $872.88 | $1,045.16 | $1,210.40 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of November 11, 2025. Compiled by Mirage Metrics.