WisDOT contract 20251111031 bid tabulation
Weston - Menomonie; Red Cedar River Bridge B-17-0078 (CTH D, Dunn County Weston - Menomonie). Let by Wisconsin DOT on November 11, 2025, Dunn. 3 bids received; low bid $816,921 by Lunda Construction Company.
- Owner
- Wisconsin DOT
- Letting
- 11 NOV 2025
- Pay items
- 72
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Lunda Construction Company | $816,921 | Low |
| 2 | Janke General Contractors, Inc. | $875,993 | +7.0% |
| 3 | Zenith Tech., Inc. - Waukesha | $892,397 | +9.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Lunda Construction Company | 2. Janke General Contractors, Inc. | 3. Zenith Tech., Inc. - Waukesha |
|---|---|---|---|---|---|---|
| 1 | Abatement of asbestos containing material (structure) 01. B-17-78 (203.0211.S) | EACH | 1 | $10,000 | $12,500 | $27,455 |
| 2 | Debris containment over waterway (structure) 01. B-17-78 (203.0335) | EACH | 1 | $500.00 | $12,000 | $3,000.00 |
| 3 | Removing curb & gutter (204.0150) | LF | 157 | $4.90 | $15.00 | $4.90 |
| 4 | Removing guardrail (204.0165) | LF | 383 | $3.45 | $9.35 | $3.45 |
| 5 | Removing inlets (204.0220) | EACH | 4 | $368.00 | $500.00 | $368.00 |
| 6 | Removing storm sewer (size) 01. 12-inch (204.0245) | LF | 66 | $11.15 | $17.00 | $11.15 |
| 7 | Removing storm sewer (size) 02. 15-inch (204.0245) | LF | 37 | $11.15 | $25.00 | $11.15 |
| 8 | Excavation common (205.0100) | CY | 378 | $16.20 | $28.00 | $16.20 |
| 9 | Finishing roadway (project) 01. 7881-05-74 (213.0100) | EACH | 1 | $920.00 | $100.00 | $920.00 |
| 10 | Base aggregate dense 3/4-inch (305.0110) | TON | 25 | $52.00 | $55.00 | $52.00 |
| 11 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 700 | $26.10 | $32.00 | $26.10 |
| 12 | Tack coat (455.0605) | GAL | 39 | $12.97 | $12.97 | $12.97 |
| 13 | Incentive density HMA pavement (460.2000) | DOL | 110 | $1.00 | $1.00 | $1.00 |
| 14 | HMA pavement 3 LT 58-28 S (460.5223) | TON | 75 | $165.93 | $165.93 | $165.93 |
| 15 | HMA pavement 4 LT 58-34 S (460.5244) | TON | 96 | $175.00 | $175.00 | $175.00 |
| 16 | Protective surface treatment (502.3200) | SY | 1,047 | $3.00 | $5.00 | $5.00 |
| 17 | Pigmented surface sealer reseal (502.3205) | SY | 254 | $5.00 | $13.00 | $22.00 |
| 18 | Preparation decks type 1 (509.0301) | SY | 405 | $150.00 | $170.00 | $190.00 |
| 19 | Preparation decks type 2 (509.0302) | SY | 162 | $175.00 | $180.00 | $275.00 |
| 20 | Cleaning decks (509.0500) | SY | 1,047 | $23.48 | $18.00 | $45.00 |
| 21 | Concrete surface repair (509.1500) | SF | 90 | $175.00 | $200.00 | $300.00 |
| 22 | Full-depth deck repair (509.2000) | SY | 2 | $500.00 | $1,900.00 | $1,600.00 |
| 23 | Concrete masonry overlay decks (509.2500) | CY | 80 | $1,500.00 | $1,520.00 | $1,250.00 |
| 24 | Apron endwalls for culvert pipe steel 12-inch (521.1012) | EACH | 2 | $470.00 | $480.00 | $470.00 |
| 25 | Culvert pipe corrugated polyethylene 12-inch (530.0112) | LF | 43 | $61.10 | $70.00 | $61.10 |
| 26 | Concrete curb & gutter integral 30- inch type D (601.0452) | LF | 101 | $65.97 | $65.00 | $65.97 |
| 27 | Concrete curb & gutter 4-inch sloped 36-inch type TBT (601.0588) | LF | 76 | $67.81 | $68.00 | $67.81 |
| 28 | Riprap medium (606.0200) | CY | 5 | $170.00 | $250.00 | $170.00 |
| 29 | Storm sewer pipe reinforced concrete class III 12-inch (608.0312) | LF | 66 | $124.10 | $88.26 | $124.10 |
| 30 | Inlet covers type V (611.0654) | EACH | 4 | $1,067.00 | $1,000.00 | $1,067.00 |
| 31 | Inlets 2X2-FT (611.3220) | EACH | 4 | $1,995.00 | $2,400.00 | $1,995.00 |
| 32 | MGS guardrail 3 (614.2300) | LF | 75 | $28.20 | $28.60 | $28.20 |
| 33 | MGS guardrail short radius (614.2350) | LF | 158 | $31.00 | $37.90 | $31.00 |
| 34 | MGS guardrail terminal eat (614.2610) | EACH | 1 | $3,785.00 | $4,200.00 | $3,785.00 |
| 35 | MGS guardrail short radius terminal (614.2630) | EACH | 2 | $2,725.00 | $2,509.00 | $2,725.00 |
| 36 | Maintenance and repair of haul roads (project) 01. 7881-05-74 (618.0100) | EACH | 1 | $0.01 | $100.00 | $500.00 |
| 37 | Mobilization (619.1000) | EACH | 1 | $207,133 | $159,280 | $100,000 |
| 38 | Water (624.0100) | MGAL | 20 | $18.00 | $17.00 | $18.00 |
| 39 | Salvaged topsoil (625.0500) | SY | 675 | $2.45 | $7.50 | $2.45 |
| 40 | Silt fence (628.1504) | LF | 730 | $2.40 | $2.30 | $2.40 |
| 41 | Silt fence maintenance (628.1520) | LF | 640 | $0.01 | $0.08 | $0.01 |
| 42 | Mobilizations erosion control (628.1905) | EACH | 3 | $185.00 | $400.00 | $185.00 |
| 43 | Mobilizations emergency erosion control (628.1910) | EACH | 2 | $185.00 | $50.00 | $185.00 |
| 44 | Erosion mat class I type A (628.2002) | SY | 670 | $1.90 | $1.70 | $1.90 |
| 45 | Turbidity barriers (628.6005) | SY | 640 | $38.80 | $20.00 | $38.80 |
| 46 | Inlet protection type A (628.7005) | EACH | 4 | $72.00 | $106.00 | $72.00 |
| 47 | Inlet protection type C (628.7015) | EACH | 4 | $45.90 | $72.00 | $45.90 |
| 48 | Seeding mixture no. 20 (630.0120) | LB | 20 | $12.00 | $8.75 | $12.00 |
| 49 | Seeding temporary (630.0200) | LB | 20 | $5.00 | $3.55 | $5.00 |
| 50 | Markers culvert end (633.5200) | EACH | 2 | $70.00 | $71.00 | $70.00 |
| 51 | Field office type B (642.5001) | EACH | 1 | $2,500.00 | $2,500.00 | $7,500.00 |
| 52 | Traffic control drums (643.0300) | DAY | 660 | $0.50 | $0.50 | $0.50 |
| 53 | Traffic control barricades type III (643.0420) | DAY | 1,188 | $0.50 | $0.50 | $0.50 |
| 54 | Traffic control warning lights type A (643.0705) | DAY | 1,848 | $0.10 | $0.10 | $0.10 |
| 55 | Traffic control signs (643.0900) | DAY | 924 | $0.50 | $0.50 | $0.50 |
| 56 | Traffic control signs PCMS (643.1050) | DAY | 14 | $40.00 | $40.00 | $40.00 |
| 57 | Traffic control (643.5000) | EACH | 1 | $1,740.00 | $1,740.00 | $15,000 |
| 58 | Geotextile type DF schedule C (645.0113) | SY | 324 | $5.00 | $3.00 | $5.00 |
| 59 | Geotextile type HR (645.0120) | SY | 12 | $4.35 | $13.00 | $4.35 |
| 60 | Marking line epoxy 6-inch (646.2020) | LF | 1,485 | $3.00 | $3.00 | $3.00 |
| 61 | Construction staking storm sewer (650.4000) | EACH | 6 | $145.00 | $165.00 | $145.00 |
| 62 | Construction staking subgrade (650.4500) | LF | 317 | $0.01 | $0.01 | $0.01 |
| 63 | Construction staking base (650.5000) | LF | 317 | $1.00 | $0.01 | $1.00 |
| 64 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 177 | $2.00 | $2.75 | $2.00 |
| 65 | Construction staking supplemental control (project) 01. 7881-05-74 (650.9911) | EACH | 1 | $2,500.00 | $1,150.00 | $2,500.00 |
| 66 | Construction staking slope stakes (650.9920) | LF | 317 | $1.00 | $2.75 | $1.00 |
| 67 | Sawing asphalt (690.0150) | LF | 466 | $1.80 | $1.80 | $1.80 |
| 68 | Maintaining bird deterrent system (station) 01. 10+00 (999.2005.S) | EACH | 1 | $0.01 | $2,800.00 | $1.00 |
| 69 | Special 01. scour repair grout bags (SPV.0035) | CY | 116 | $1,425.00 | $2,000.00 | $2,150.00 |
| 70 | Special 01. foam void filling B-17- 78 (SPV.0060) | EACH | 1 | $5,000.00 | $8,500.00 | $10,000 |
| 71 | Special 02. MGS guardrail terminal eat TL-2 (SPV.0060) | EACH | 1 | $3,215.00 | $4,200.00 | $3,215.00 |
| 72 | Special 01. MGS thrie beam transition TL-2 (SPV.0090) | LF | 81 | $91.00 | $99.00 | $91.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of November 11, 2025. Compiled by Mirage Metrics.