WisDOT contract 20251209018 bid tabulation
Brown Co, CTH Kb; Neshota River Bridge (CTH KB, Brown County BROWN CO, CTH KB). Let by Wisconsin DOT on December 9, 2025, Brown. 4 bids received; low bid $1,050,218 by Sheet Piling Services LLC.
- Owner
- Wisconsin DOT
- Letting
- 09 DEC 2025
- Pay items
- 84
- Data through
- 10 NOV 2026
3 of the 4 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Sheet Piling Services LLC | $1,050,218 | Low |
| 2 | Radtke Contractors Inc. | $1,056,339 | +1.0% |
| 4 | Lunda Construction Company | $1,167,583 | +11% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Sheet Piling Services LLC | 2. Radtke Contractors Inc. | 3. Lunda Construction Company |
|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 2 | $1,000.00 | $1,000.00 | $750.00 |
| 2 | Grubbing (201.0205) | STA | 2 | $1,000.00 | $1,000.00 | $425.00 |
| 3 | Removing small pipe culverts (203.0100) | EACH | 1 | $655.00 | $655.00 | $350.00 |
| 4 | Abatement of asbestos containing material (structure) 01. B-05-0008 (203.0211.S) | EACH | 1 | $5,985.00 | $5,985.00 | $6,000.00 |
| 5 | Removing structure over waterway minimal debris (structure) 01. B-05- 0008 (203.0260) | EACH | 1 | $80,000 | $64,537 | $209,904 |
| 6 | Removing asphaltic surface (204.0110) | SY | 1,010 | $4.50 | $4.50 | $8.00 |
| 7 | Removing guardrail (204.0165) | LF | 213 | $5.00 | $3.50 | $5.00 |
| 8 | Removing delineators and markers (204.0180) | EACH | 7 | $50.00 | $35.00 | $50.00 |
| 9 | Excavation common (205.0100) | CY | 764 | $11.00 | $11.00 | $18.00 |
| 10 | Excavation for structures bridges (structure) 01. B-05-0485 (206.1001) | EACH | 1 | $55,800 | $44,143 | $2,500.00 |
| 11 | Cofferdams (structure) 01. B-05- 0485 (206.5001) | EACH | 1 | $45,000 | $87,726 | $45,000 |
| 12 | Borrow (208.0100) | CY | 1,110 | $12.70 | $12.70 | $1.00 |
| 13 | Backfill structure type A (210.1500) | TON | 570 | $33.56 | $31.08 | $27.25 |
| 14 | Prepare foundation for asphaltic paving (project) 01. 4538-02-73 (211.0101) | EACH | 1 | $0.01 | $6,080.00 | $6,080.00 |
| 15 | Finishing roadway (project) 01. 4538-02-73 (213.0100) | EACH | 1 | $2,000.00 | $2,000.00 | $1,500.00 |
| 16 | Base aggregate dense 3/4-inch (305.0110) | TON | 155 | $85.00 | $85.00 | $34.50 |
| 17 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 545 | $16.05 | $16.05 | $22.50 |
| 18 | Breaker run (311.0110) | TON | 1,115 | $18.50 | $18.50 | $22.50 |
| 19 | Tack coat (455.0605) | GAL | 80 | $15.85 | $15.85 | $15.85 |
| 20 | Incentive density HMA pavement (460.2000) | DOL | 260 | $1.00 | $1.00 | $1.00 |
| 21 | HMA pavement 3 MT 58-28 S (460.6223) | TON | 220 | $115.00 | $115.00 | $115.00 |
| 22 | HMA pavement 4 MT 58-28 S (460.6224) | TON | 180 | $124.60 | $124.60 | $124.60 |
| 23 | Concrete masonry bridges (502.0100) | CY | 353 | $850.00 | $624.03 | $750.00 |
| 24 | Protective surface treatment (502.3200) | SY | 435 | $2.50 | $3.69 | $2.00 |
| 25 | Underwater substructure inspection (structure) 01. B-05-0485 (502.9000.S) | EACH | 1 | $750.00 | $500.00 | $5,000.00 |
| 26 | Bar steel reinforcement HS structures (505.0400) | LB | 8,580 | $1.45 | $1.37 | $1.03 |
| 27 | Bar steel reinforcement HS coated structures (505.0600) | LB | 43,560 | $1.55 | $1.34 | $1.13 |
| 28 | Railing tubular type M (513.4061) | LF | 169 | $325.00 | $256.75 | $255.00 |
| 29 | Rubberized membrane waterproofing (516.0500) | SY | 20 | $15.00 | $64.32 | $25.00 |
| 30 | Apron endwalls for culvert pipe 24- inch (520.1024) | EACH | 2 | $779.00 | $779.00 | $530.00 |
| 31 | Culvert pipe class III-A 24-inch (520.3324) | LF | 32 | $149.00 | $149.00 | $126.30 |
| 32 | Pre-boring rock or consolidated materials (550.0020) | LF | 116 | $35.00 | $286.65 | $475.00 |
| 33 | Piling steel HP 10-inch X 42 LB (550.1100) | LF | 700 | $40.00 | $37.74 | $38.00 |
| 34 | Riprap heavy (606.0300) | CY | 410 | $81.00 | $67.69 | $98.00 |
| 35 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 130 | $10.00 | $4.26 | $12.00 |
| 36 | MGS guardrail 3 (614.2300) | LF | 162.50 | $29.00 | $32.50 | $30.00 |
| 37 | MGS thrie beam transition (614.2500) | LF | 157.60 | $97.00 | $92.00 | $94.00 |
| 38 | MGS guardrail terminal eat (614.2610) | EACH | 4 | $3,495.00 | $3,800.00 | $4,950.00 |
| 39 | Maintenance and repair of haul roads (project) 01. 4538-02-73 (618.0100) | EACH | 1 | $0.01 | $500.00 | $250.00 |
| 40 | Mobilization (619.1000) | EACH | 1 | $83,563 | $134,117 | $115,385 |
| 41 | Water (624.0100) | MGAL | 13 | $50.00 | $50.00 | $10.00 |
| 42 | Salvaged topsoil (625.0500) | SY | 3,000 | $4.00 | $4.00 | $4.25 |
| 43 | Mulching (627.0200) | SY | 1,500 | $0.65 | $0.75 | $0.50 |
| 44 | Silt fence (628.1504) | LF | 1,500 | $2.25 | $2.00 | $2.00 |
| 45 | Silt fence maintenance (628.1520) | LF | 1,500 | $0.03 | $0.01 | $0.01 |
| 46 | Mobilizations erosion control (628.1905) | EACH | 6 | $203.00 | $75.00 | $250.00 |
| 47 | Mobilizations emergency erosion control (628.1910) | EACH | 3 | $353.00 | $75.00 | $1.00 |
| 48 | Erosion mat urban class I type B (628.2008) | SY | 3,000 | $2.05 | $1.80 | $4.00 |
| 49 | Turbidity barriers (628.6005) | SY | 375 | $48.00 | $55.00 | $55.00 |
| 50 | Temporary ditch checks (628.7504) | LF | 125 | $8.05 | $7.75 | $10.00 |
| 51 | Culvert pipe checks (628.7555) | EACH | 4 | $25.00 | $25.00 | $15.00 |
| 52 | Fertilizer type B (629.0210) | CWT | 2.40 | $100.00 | $100.00 | $200.00 |
| 53 | Seeding mixture no. 30 (630.0130) | LB | 175 | $9.00 | $7.50 | $10.00 |
| 54 | Seed water (630.0500) | MGAL | 95 | $5.00 | $5.00 | $1.00 |
| 55 | Posts wood 4X6-inch X 12-FT (634.0612) | EACH | 4 | $100.00 | $95.00 | $160.00 |
| 56 | Signs type II reflective F (637.2230) | SF | 12 | $50.00 | $30.00 | $45.00 |
| 57 | Moving signs type II (638.2102) | EACH | 2 | $100.00 | $75.00 | $150.00 |
| 58 | Removing signs type II (638.2602) | EACH | 4 | $30.00 | $35.00 | $50.00 |
| 59 | Removing small sign supports (638.3000) | EACH | 4 | $30.00 | $35.00 | $100.00 |
| 60 | Moving small sign supports (638.4000) | EACH | 2 | $100.00 | $75.00 | $100.00 |
| 61 | Field office type B (642.5001) | EACH | 1 | $3,500.00 | $2,224.20 | $4,000.00 |
| 62 | Traffic control drums (643.0300) | DAY | 93 | $5.00 | $5.00 | $5.00 |
| 63 | Traffic control barricades type III (643.0420) | DAY | 2,200 | $1.00 | $0.75 | $1.00 |
| 64 | Traffic control warning lights type A (643.0705) | DAY | 3,520 | $0.50 | $0.25 | $0.50 |
| 65 | Traffic control signs (643.0900) | DAY | 22,116 | $0.20 | $0.65 | $0.20 |
| 66 | Traffic control covering signs type II (643.0920) | EACH | 7 | $25.00 | $75.00 | $25.00 |
| 67 | Traffic control signs PCMS (643.1050) | DAY | 14 | $99.00 | $105.00 | $99.00 |
| 68 | Traffic control (643.5000) | EACH | 1 | $5,000.00 | $3,500.00 | $5,000.00 |
| 69 | Geotextile type DF schedule A (645.0111) | SY | 80 | $6.00 | $4.71 | $6.00 |
| 70 | Geotextile type HR (645.0120) | SY | 680 | $3.50 | $5.10 | $6.00 |
| 71 | Marking line epoxy 6-inch (646.2020) | LF | 1,800 | $3.50 | $3.70 | $3.70 |
| 72 | Locating no-passing zones (648.0100) | MI | 0.10 | $600.00 | $625.00 | $625.00 |
| 73 | Construction staking subgrade (650.4500) | LF | 478 | $0.01 | $0.01 | $0.01 |
| 74 | Construction staking base (650.5000) | LF | 478 | $0.55 | $0.55 | $0.55 |
| 75 | Construction staking pipe culverts (650.6000) | EACH | 1 | $250.00 | $250.00 | $250.00 |
| 76 | Construction staking structure layout (structure) 01. B-05-0485 (650.6501) | EACH | 1 | $4,500.00 | $3,500.00 | $3,500.00 |
| 77 | Construction staking supplemental control (project) 01. 4538-02-73 (650.9911) | EACH | 1 | $10.00 | $10.00 | $10.00 |
| 78 | Construction staking slope stakes (650.9920) | LF | 478 | $2.00 | $2.00 | $2.00 |
| 79 | Sawing asphalt (690.0150) | LF | 60 | $2.95 | $2.95 | $2.95 |
| 80 | Incentive strength concrete structures (715.0502) | DOL | 2,574 | $1.00 | $1.00 | $1.00 |
| 81 | Installing and maintaining bird deterrent system (station) 01. station 106+54 (999.2000.S) | EACH | 1 | $0.01 | $0.01 | $1,500.00 |
| 82 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 300 | $5.00 | $5.00 | $5.00 |
| 83 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 600 | $5.00 | $5.00 | $5.00 |
| 84 | Special 01. superstructure 3/4" X 5 1/2" drip edges B-05-0485 (SPV.0060) | EACH | 1 | $0.01 | $6,768.19 | $5,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of December 9, 2025. Compiled by Mirage Metrics.