WisDOT contract 20251209040 bid tabulation

C Eau Claire, Various Highways; STH 93, 312 & USH 12 Curb Ramps (VAR HWY, Eau Claire County C Eau Claire, Various Highways). Let by Wisconsin DOT on December 9, 2025, Eau Claire. 1 bid received; low bid $2,912,936 by Chippewa Concrete Services, Inc..

Owner
Wisconsin DOT
Letting
09 DEC 2025
Pay items
103
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Chippewa Concrete Services, Inc.$2,912,936Low
WisDOT contract 20251209040: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Chippewa Concrete Services, Inc.
1Removing structure (structure) 01. B-18-0173 (203.0220)EACH1$19,967
2Removing concrete pavement (204.0100)SY380$71.78
3Removing asphaltic surface (204.0110)SY1,660$32.35
4Removing curb & gutter (204.0150)LF4,010$24.26
5Removing concrete sidewalk (204.0155)SY2,680$17.19
6Removing surface drains (204.0190)EACH5$859.35
7Removing concrete bases (204.0195)EACH1$343.74
8Finishing roadway (project) 01. 7995-02-72 (213.0100)EACH1$7,582.50
9Base aggregate dense 3/4-inch (305.0110)TON370$104.13
10Concrete pavement 9-inch (415.0090)SY48$136.21
11Drilled tie bars (416.0610)EACH1,770$15.76
12Tack coat (455.0605)GAL15.60$19.44
13Asphaltic surface (465.0105)TON180$245.62
14Concrete masonry bridges (502.0100)CY16$2,780.25
15Protective surface treatment (502.3200)SY79$31.34
16Adhesive anchors no. 4 bar (502.4204)EACH69$39.43
17Bar steel reinforcement HS coated structures (505.0600)LB600$8.09
18Concrete collars for pipe (520.8000)EACH1$1,213.20
19Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024)EACH1$2,856.08
20Concrete curb type A (601.0105)LF181$49.78
21Concrete curb type G (601.0115)LF98$49.78
22Concrete curb & gutter 30-inch type A (601.0409)LF1,680$84.40
23Concrete curb & gutter 30-inch type D (601.0411)LF590$84.40
24Concrete curb & gutter 6-inch sloped 30-inch type G (601.0413)LF710$84.40
25Concrete curb & gutter 6-inch sloped 36-inch type A (601.0555)LF510$86.23
26Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557)LF260$86.23
27Concrete curb pedestrian (601.0600)LF1,765$68.02
28Concrete sidewalk 5-inch (602.0410)SF31,300$22.29
29Curb ramp detectable warning field yellow (602.0505)SF2,302$63.20
30Curb ramp detectable warning field radial yellow (602.0605)SF1,032$68.59
31Concrete safety islands (602.2400)SF1,310$16.30
32Concrete surface drains (602.3010)CY8$1,624.04
33Riprap light (606.0100)CY23$176.93
34Storm sewer pipe reinforced concrete class III 24-inch (608.0324)LF17$227.48
35Adjusting manhole covers (611.8110)EACH12$985.73
36Adjusting inlet covers (611.8115)EACH12$616.71
37Fence safety (616.0700.S)LF100$5.06
38Mobilization (619.1000)EACH1$219,599
39Concrete median sloped nose (620.0300)SF20$16.30
40Salvaged topsoil (625.0500)SY3,040$18.20
41Silt fence (628.1504)LF2,880$2.43
42Silt fence maintenance (628.1520)LF17,250$0.01
43Mobilizations erosion control (628.1905)EACH30$707.70
44Mobilizations emergency erosion control (628.1910)EACH7$1.01
45Erosion mat urban class I type A (628.2006)SY3,040$3.03
46Inlet protection type A (628.7005)EACH10$107.17
47Inlet protection type B (628.7010)EACH15$90.99
48Inlet protection type C (628.7015)EACH95$90.99
49Culvert pipe checks (628.7555)EACH4$21.53
50Fertilizer type B (629.0210)CWT170$111.21
51Seeding mixture no. 40 (630.0140)LB225$18.20
52Seed water (630.0500)MGAL400$1.01
53Markers culvert end (633.5200)EACH1$71.78
54Moving signs type II (638.2102)EACH36$120.31
55Moving small sign supports (638.4000)EACH23$121.32
56Field office type B (642.5001)EACH1$7,582.50
57Traffic control drums (643.0300)DAY16,800$0.20
58Traffic control barricades type III (643.0420)DAY985$1.52
59Traffic control warning lights type A (643.0705)DAY1,950$0.20
60Traffic control warning lights type C (643.0715)DAY2,415$0.20
61Traffic control connected arrow boards (643.0810)DAY260$35.39
62Traffic control signs (643.0900)DAY7,860$0.30
63Traffic control covering signs type II (643.0920)EACH15$146.60
64Traffic control signs PCMS (643.1050)DAY119$55.61
65Traffic control cones 42-inch (643.1070)DAY7,860$0.20
66Traffic control connected work zone start and end location markers (643.1220)DAY260$20.22
67Temporary marking line removable tape 6-inch (643.3180)LF5,550$2.17
68Temporary marking stop line removable tape 18-inch (643.3850)LF230$7.08
69Traffic control (643.5000)EACH1$87,957
70Temporary pedestrian surface matting (644.1440)SF15,600$3.54
71Temporary pedestrian curb ramp (644.1601)DAY240$70.77
72Temporary pedestrian detectable warning field (644.1605)SF1,175$5.06
73Temporary pedestrian barricade (644.1810)LF11,100$7.68
74Temporary audible message devices (644.1900.S)DAY1,230$7.33
75Geotextile type R (645.0130)SY135$10.11
76Marking stop line epoxy 18-inch (646.6120)LF930$12.74
77Marking yield line epoxy 18-inch (646.6220)EACH19$35.64
78Marking crosswalk epoxy transverse line 6-inch (646.7420)LF6,980$9.66
79Marking curb epoxy (646.8120)LF590$15.01
80Marking island nose epoxy (646.8220)EACH1$257.81
81Marking removal line water blasting 4-inch (646.9010)LF70$5.06
82Marking removal line water blasting wide (646.9210)LF5,670$7.08
83Construction staking storm sewer (650.4000)EACH1$303.30
84Construction staking curb gutter and curb & gutter (650.5500)LF850$2.02
85Construction staking curb ramps (650.9000)EACH239$176.93
86Construction staking sidewalk (project) 01. 7995-02-72 (650.9500)EACH1$5,055.00
87Construction staking supplemental control (project) 01. 7995-02-72 (650.9911)EACH1$5,055.00
88Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF126$13.14
89Install conduit into existing item (652.0700.S)EACH7$353.85
90Adjusting pull boxes (653.0900)EACH21$252.75
91Concrete bases type 1 (654.0101)EACH8$1,440.68
92Electrical wire traffic signals 12 AWG (655.0510)LF169$1.52
93Sawing asphalt (690.0150)LF1,770$1.97
94Sawing concrete (690.0250)LF6,520$2.78
95Incentive strength concrete structures (715.0502)DOL500$1.00
96Incentive compressive strength concrete pavement (715.0720)DOL500$1.00
97On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS300$5.00
98On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS300$5.00
99Special 01. grading for temporary pedestrian access route (SPV.0060)EACH11$6,571.50
100Special 02. temporary pedestrian signal unit (SPV.0060)EACH26$2,780.25
101Special 01. ditch cleaning (SPV.0090)LF50$25.28
102Special 02. sawing curb head for ramp opening (SPV.0090)LF158$30.33
103Special 03. trimming trees (SPV.0090)LF20$25.28
WisDOT contract 20251209040: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of December 9, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy