WisDOT contract 20251209046 bid tabulation
T Hoard, Center Road; N Fk Popple River Bridge B-10-0267 (LOC STR, Clark County T Hoard, Center Road). Let by Wisconsin DOT on December 9, 2025, Clark. 6 bids received; low bid $566,250 by Larson Construction Co., Inc..
- Owner
- Wisconsin DOT
- Letting
- 09 DEC 2025
- Pay items
- 60
- Data through
- 10 NOV 2026
4 of the 6 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Larson Construction Co., Inc. | $566,250 | Low |
| 2 | Radtke Contractors Inc. | $615,505 | +9.0% |
| 3 | Sheet Piling Services LLC | $648,173 | +14% |
| 5 | Janke General Contractors, Inc. | $689,998 | +22% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Larson Construction Co., Inc. | 2. Radtke Contractors Inc. | 3. Sheet Piling Services LLC | 4. Janke General Contractors, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 1 | $519.00 | $519.00 | $519.00 | $300.00 |
| 2 | Grubbing (201.0205) | STA | 1 | $346.00 | $346.00 | $346.00 | $1,100.00 |
| 3 | Removing structure over waterway minimal debris (structure) 01. P-10- 0075 (203.0260) | EACH | 1 | $26,700 | $44,686 | $68,750 | $75,000 |
| 4 | Excavation common (205.0100) | CY | 73 | $26.10 | $26.10 | $26.10 | $29.00 |
| 5 | Excavation, hauling, and disposal of potential creosote contaminated soil (205.0508.S) | TON | 272 | $137.00 | $106.86 | $100.00 | $31.00 |
| 6 | Excavation for structures bridges (structure) 01. B-10-0267 (206.1001) | EACH | 1 | $18,000 | $33,211 | $30,000 | $35,120 |
| 7 | Cofferdams (structure) 01. B-10- 0267 (206.5001) | EACH | 1 | $31,300 | $32,405 | $40,000 | $23,000 |
| 8 | Borrow (208.0100) | CY | 3 | $50.00 | $50.00 | $50.00 | $16.50 |
| 9 | Backfill structure type A (210.1500) | TON | 220 | $17.80 | $33.42 | $17.80 | $35.00 |
| 10 | Finishing roadway (project) 01. 8881-00-72 (213.0100) | EACH | 1 | $500.00 | $500.00 | $500.00 | $100.00 |
| 11 | Base aggregate dense 3/4-inch (305.0110) | TON | 235 | $23.70 | $23.70 | $23.70 | $31.00 |
| 12 | Concrete masonry bridges (502.0100) | CY | 246.50 | $633.00 | $644.43 | $806.00 | $855.00 |
| 13 | Protective surface treatment (502.3200) | SY | 340 | $3.00 | $3.69 | $4.00 | $5.00 |
| 14 | Underwater substructure inspection (structure) 01. B-10-0267 (502.9000.S) | EACH | 1 | $1,000.00 | $500.00 | $6,000.00 | $2,500.00 |
| 15 | Bar steel reinforcement HS structures (505.0400) | LB | 4,440 | $1.55 | $1.44 | $1.50 | $2.25 |
| 16 | Bar steel reinforcement HS coated structures (505.0600) | LB | 32,520 | $1.55 | $1.38 | $1.45 | $2.25 |
| 17 | Structural steel carbon (506.0105) | LB | 530 | $6.00 | $9.14 | $8.00 | $9.00 |
| 18 | Railing tubular type M (513.4061) | LF | 222 | $313.00 | $268.62 | $250.00 | $335.00 |
| 19 | Rubberized membrane waterproofing (516.0500) | SY | 18 | $58.00 | $64.32 | $25.00 | $40.00 |
| 20 | Pile points (550.0500) | EACH | 15 | $115.00 | $105.50 | $250.00 | $200.00 |
| 21 | Piling steel HP 10-inch X 42 LB (550.1100) | LF | 675 | $59.00 | $36.98 | $63.50 | $80.00 |
| 22 | Riprap heavy (606.0300) | CY | 240 | $78.00 | $73.17 | $82.00 | $80.00 |
| 23 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 180 | $6.80 | $4.26 | $6.80 | $12.00 |
| 24 | Maintenance and repair of haul roads (project) 01. 8881-00-72 (618.0100) | EACH | 1 | $1,500.00 | $250.00 | $0.01 | $100.00 |
| 25 | Mobilization (619.1000) | EACH | 1 | $52,194 | $102,035 | $48,350 | $38,000 |
| 26 | Water (624.0100) | MGAL | 5 | $1.00 | $1.00 | $1.00 | $20.00 |
| 27 | Topsoil (625.0100) | SY | 280 | $8.25 | $8.25 | $8.25 | $5.00 |
| 28 | Mulching (627.0200) | SY | 230 | $1.15 | $1.15 | $1.15 | $1.60 |
| 29 | Silt fence (628.1504) | LF | 330 | $3.00 | $3.00 | $3.00 | $2.40 |
| 30 | Silt fence maintenance (628.1520) | LF | 660 | $0.01 | $0.01 | $0.01 | $0.01 |
| 31 | Mobilizations erosion control (628.1905) | EACH | 4 | $400.00 | $400.00 | $400.00 | $1.00 |
| 32 | Mobilizations emergency erosion control (628.1910) | EACH | 4 | $10.00 | $10.00 | $10.00 | $100.00 |
| 33 | Erosion mat class II type C (628.2027) | SY | 200 | $4.65 | $4.65 | $4.65 | $6.50 |
| 34 | Turbidity barriers (628.6005) | SY | 270 | $38.00 | $38.00 | $38.00 | $26.00 |
| 35 | Temporary ditch checks (628.7504) | LF | 50 | $7.15 | $7.15 | $7.15 | $8.00 |
| 36 | Fertilizer type B (629.0210) | CWT | 0.30 | $300.00 | $300.00 | $300.00 | $250.00 |
| 37 | Seeding mixture no. 20 (630.0120) | LB | 19 | $20.75 | $20.75 | $20.75 | $6.50 |
| 38 | Seeding temporary (630.0200) | LB | 11 | $6.65 | $6.65 | $6.65 | $3.50 |
| 39 | Seed water (630.0500) | MGAL | 9 | $0.01 | $0.01 | $0.01 | $30.00 |
| 40 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 4 | $90.25 | $90.25 | $90.25 | $160.00 |
| 41 | Signs type II reflective F (637.2230) | SF | 12 | $28.75 | $28.75 | $28.75 | $19.00 |
| 42 | Removing signs type II (638.2602) | EACH | 6 | $15.00 | $15.00 | $15.00 | $50.00 |
| 43 | Removing small sign supports (638.3000) | EACH | 6 | $15.00 | $15.00 | $15.00 | $50.00 |
| 44 | Field office type B (642.5001) | EACH | 1 | $3,500.00 | $2,429.04 | $2,000.00 | $2,500.00 |
| 45 | Traffic control barricades type III (643.0420) | DAY | 1,980 | $0.45 | $0.45 | $0.45 | $0.45 |
| 46 | Traffic control warning lights type A (643.0705) | DAY | 2,640 | $0.10 | $0.10 | $0.10 | $0.10 |
| 47 | Traffic control signs (643.0900) | DAY | 1,320 | $0.45 | $0.45 | $0.45 | $0.45 |
| 48 | Traffic control (643.5000) | EACH | 1 | $1,400.00 | $1,400.00 | $1,400.00 | $1,400.00 |
| 49 | Geotextile type DF schedule A (645.0111) | SY | 40 | $4.75 | $4.71 | $4.75 | $4.00 |
| 50 | Geotextile type HR (645.0120) | SY | 400 | $3.50 | $5.10 | $4.00 | $5.00 |
| 51 | Construction staking subgrade (650.4500) | LF | 100 | $0.01 | $0.01 | $0.01 | $0.01 |
| 52 | Construction staking base (650.5000) | LF | 100 | $0.01 | $0.01 | $0.01 | $0.01 |
| 53 | Construction staking structure layout (structure) 01. B-10-0267 (650.6501) | EACH | 1 | $1,866.00 | $2,000.00 | $1,866.00 | $1,866.00 |
| 54 | Construction staking supplemental control (project) 01. 8881-00-72 (650.9911) | EACH | 1 | $442.00 | $1,400.00 | $442.00 | $442.00 |
| 55 | Construction staking slope stakes (650.9920) | LF | 100 | $1.50 | $0.01 | $1.50 | $1.50 |
| 56 | Incentive strength concrete structures (715.0502) | DOL | 1,482 | $1.00 | $1.00 | $1.00 | $1.00 |
| 57 | Installing and maintaining bird deterrent system (station) 01. 10+00 (999.2000.S) | EACH | 1 | $1,000.00 | $0.01 | $0.01 | $6,000.00 |
| 58 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 300 | $5.00 | $5.00 | $5.00 | $5.00 |
| 59 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 300 | $5.00 | $5.00 | $5.00 | $5.00 |
| 60 | Special 01. select crushed material for travel corridor (SPV.0195) | TON | 12 | $121.00 | $102.27 | $110.00 | $70.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of December 9, 2025. Compiled by Mirage Metrics.